Project Number/Name
Project DescriptionStatusArchitectAnticipated Construction Timeline
2

3
4
5
AA36 AHS NEW CTE Classroom BuildingAddition of new classroom building for general education classrooms, CTE programs (Culinary, Ag and Maker) along with bathroom facilities and associated campus upgrades10-12-22- Board identified project as a priority.
10-12-22 - Board awarded Consultant Contract Awarded to QKA
First round of Education Partner Meetings are Complete
2-1-23 - QKA met with Executive Committee to discuss progress of project, we will meet again on February 28 to finalize the building program before presenting it to the full Education Committee. QKA to start schematic design ASAP. District to update costs of project based on updated estimate of building sq footage. Site Admin and District staff to give project update to all Analy staff at March staff meeting. Staff to start CEQA process and get Geotechnical and other surveys started. Looking at possible increments I and II for adding temporary housing and demolition of Auto/Annex 1 & Annex 2
3-9-23 - District staff met with Legal Council regarding CEQA, Lease Leaseback and other building procurement methods, staff will be bringing items to the Board in the next few months
4-2023 Surveys being conducted by consultants (Topographic, Subtronics Survey (utilities)
5-3-23 District staff bringing consultant contract to the Board for Geotech and Hazmat Survey for project
8-2023 - QKA is almost finished with Schematic Design; District/Site Administration are meeting with CTE teachers on Thursday, August 31st to go over some of the changed plans; after that meeting we hope to have a meeting with CTE teachers, QKA to finalize the project schematic plans and present those plans to the Board in Sept/Oct depending on the timing of those final meetings.
10-2023 - QKA, District Administration, Site Administration and Site Staff continue to finalize the Schematic Design of the new buildings. We anticipate finishing mid November.
12-12-23 - Schematic Design is complete, district administration is working with QKA on the design development phase, hiring all the additional consultants (Commissioning, Hazmat Report, submission of the California Geological Survey, fire hydrant flow test, coordinating a mtg with IT staff, going over interior finishes, etc.
2-2024 - We are 50% through design development. On 2-15 district administration met with the design team about colors and finishes for inside and outside the building; we will be having a second meeting in a few weeks to go over the two different color schemes and plan to present those to the committee for further discussion. At the 2-21-24 Board meeting staff is presenting to the Board for consideration approval of the commissioning contract for this project.
3-2024 - RFP for Lease Leaseback Contractor issued, responses due March 28th; interviews scheduled for April 3rd/4th, anticipated recommendation to the Board for a selected contractor for April 10, 2024. Design Development is 100% complete, meetings with landscape architect/exterior lighting designer and district and page turn meetings are occurring and or have occurred with District/architect. District/architect reviewed color scheme for the buildings and will be bringing that back to the committee for full review before finalizing.
4-2024 anticipate PSA award to General Contractor; DSA submission is on track for June 2024
5-28-24 - Project has been registered with DSA, project app #01-121813; DSA project submission date is 6/26/24
8-2024 Project is in DSA for review; OAC Team has met to start to strategize the project sequencing
9-10-24 - OAC Mtg to strategize project sequencing, what can we start now, March and spring break
10-9-24 - OA meetings occuring weekly for sequencing and getting project finalized; OAC meetings are occuring montly to discuss phases of the project; DSA update, intial review has occured, architect/consultants are finalizing back check comments, we are a few weeks away from submitting for second review
11-13-24 - OAC Team met today, discussed P1, going to board tonight for approval of the lease/GMP; P2 is currently out to bid, expected to recommend award in January 2025 and start bidding P3 in January 2025. Project is expected to go to back check end of November.
12-18-24 - GMP for P2 is on the agenda tonight for board review and approval. P2 is the demo of two existing buildings on the Analy campus; this portion of the project is scheduled for March with the demo over spring break.
12-20-24 - antipcate back check review to be completed by DSA by 1-10-25
QKAactivley under construction estimated completion fall 2026
6
7
8
9
AA43 - Analy Stadium Improvement Project 10-2023 - project is still being investigated; we are awaiting Civil engineer evaluation of storm drain video footage, so we can determine if we can repair the broken pipe with internal coating vs. having to expose the pipe. This repair would allow the District and architects to work on a long term plan that could include recommendation to replace the visitor bleachers, track resurfacing and re-carpeting of the stadium turf.
12-12-23 - District administration is recommending this project be prioritized for the next round of bond projects at the 12-13-23 Board mtg.
2-2024 - this project is in the schematic design phase as approved by the board at the 12-12-23 board meeting; the first meeting for this project has already occurred and the next meeting is planned for early March
3-2024 - schematic design process continues, we will bring preliminary plans and costs to the Board in June for further direction.
8-2024 - schematic design complete; QKA/District Admin to present to the Board this project and others with recommendations for next round of prioritized projects Sept 11th Board Mtg
10-9-2024 - Board prioritized this project for next phase of MEasure A Bond funds at the 9-11 Board Mtg. Staff will be presenting consultant contracts in late 2025 for board consideration.
11-2024 no new updates
12-18-24- no new updates; will likely take architect proposal for the project to the Board for consideration in Spring 2025
11-13-25 - Architect agreement was approved by board to start the full project design (QKA)
QKAsummer 2027
10
AA51 - El Molino Kitchen Modernization Project11-13-25 - Board reviewed project priorities and approved this project moving forward; they also approved the architect agreement for design servicesQKAsummer/fall 2026
11
12
13
14
last updated 11-13-25 by JBruneman
15
16
17
18
19
FUTURE PROJECTS - ON HOLD
20
AA46 - Analy Cafeteria/Kitchen Modernization 2-2024 - this project is in the schematic design phase as approved by the board at the 12-12-23 board meeting; the first meeting for the project is planned for Feb 27th
3-2024 - schematic design process continues, we will bring preliminary plans and costs to the Board in June for further direction.
8-2024 - schematic design complete; QKA/District Admin to present to the Board this project and others with recommendations for next round of prioritized projects Sept 11th Board Mtg
QKA
21
AA44 - Analy Main Gym Modernization2-2024 - this project is in the schematic design phase as approved by the board at the 12-12-23 board meeting; the first meeting for the project has already occurred and the next meeting is planned for mid March.
3-2024 - schematic design process continues, we will bring preliminary plans and costs to the Board in June for further direction.
8-2024 - schematic design complete; QKA/District Admin to present to the Board this project and others with recommendations for next round of prioritized projects Sept 11th Board Mtg
QKA
22
AA33 DW Door and Security Locksupgrade of door, locks, closures, panic and related hardware associated with classroom, corridor and office doors district wide--- Integrate Access Control with existing cameras where possible10-11-22- Project was identified as a priority
12-14-22- Board Awarded Contract to Assa Abloy for a survey of all doors/locks district wide
1-25-23- District staff met with Assa Abloy to discuss the project, survey likely to happen the week of March 20, 2023 during spring break
3-15-23 - Assa will be onsite the week of Spring Break completing the door survey for Analy HS.
5-10-23 Assa and District staff will meet to discuss results of the survey they have partially completed.
8-2023 Assa completed their door survey, we have a meeting scheduled for Sept 7th to discuss the survey and discuss project scope and timeline
12-12-23 - District staff is working with Assa Abloy, QKA to develop district standards and identify products for the lock project
2-21-24 - Recommendation at Board Mtg on 2-21 to adopt district standards for locks and accessories; once these are approved we can start to build a project for Board consideration.
3-2024 no new info
Assa AbloyTBD
23
AA45 - Analy East Wing Modernization w classrooms L1/L22-2024 - this project is in the schematic design phase as approved by the board at the 12-12-23 board meeting; the first meeting for the project has already occurred and the next meeting is planned for mid March.
3-2024 - schematic design process continues, we will bring preliminary plans and costs to the Board in June for further direction.
8-2024 - schematic design complete; QKA/District Admin to present to the Board this project and others with recommendations for next round of prioritized projects Sept 11th Board Mtg
10-9-2024 - Board prioritized this project for next phase of MEasure A Bond funds at the 9-11 Board Mtg. Staff will be presenting consultant contracts in late 2025 for board consideration.
11-2024 - no new updates
12-18-24- no new updates; will likely take architect proposal for the project to the Board for consideration in Spring 2025
11-12-25 - Project moved to on hold until funding is available
QKATBD
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100