2 | JICA Assisted Kerala Water Supply Project status | |||||||||
3 | Sl No | Scheme | AS Amount (Cr) | No. of Packages | Packages | Description of work | Scope of work | Name of Contractor | Status | Balance pending |
4 | 1 | Trivandrum Scheme | 407.2 | Original packages - 5 Rearranged package - 1 | P I | Intake, Raw Water Pipeline and WTP | 74 MLD | M/s Degremont, France, (Consortium) | Completed | Nil |
5 | P II | Treated Water Transmission Pipeline | 38.50 km | M/s Larsen & Toubro Ltd., Chennai | Completed | Nil | ||||
6 | P III | Distribution Systems | 394 km | M/s Electrosteel Castings Ltd., Kolkata | Contract closed with reduced scope of works and rearranged as PIII –R1 | Nil | ||||
7 | PIII R1 | Distribution Systems-Balance works | 133 km out of 394 km | M/s Shriram EPC Ltd., Chennai | Completed | MoP approved and informed the firm. | ||||
8 | P IV | Service Reservoirs | 11 Nos. and capacity 45.26 ML | M/s IVRCL Ltd., Hyderabad | Completed | Nil | ||||
9 | P V | Rehabilitation Works of Existing System | 2 WTPs -Rehabilitation works of existing 72 mld plant at Aruvikkara & 36 mld plant at Vellayambalam. | M/s Abhiram Infra Projects Pvt Ltd, Hyderabad | Work terminated due to breach of contract and urgent balance works were arranged in 4 tenders from HW Division, Aruvikkara and completed. | MoP approved and informed the firm on 17.04.2023.The contractor raised objection. | ||||
10 | 2 | Meenad Scheme | 295.6 | Original packages - 4 Rearranged package - 2 | P I | Intake, Raw Water Pipeline and WTP | 73 MLD | M/s Kirloskar Brothers Ltd., Pune, (Consortium) | Completed | Nil |
11 | P II | Treated Water Transmission Pipeline | 80.33 km | M/s SPML Infra Ltd., Bangalore | Completed | Nil | ||||
12 | P III | Distribution Systems | 963 km | M/s K. Ramakrishna Contractors Pvt. Ltd., Hyderabad | Contract terminated and rearranged as PIII –R1 | Court case pending. | ||||
13 | PIII R1 | Distribution Systems- Balance works | 237 km | M/s TECPRO Infra Ltd., Kochi | Contract terminated and rearranged as PIII –RR1 | Final bill closed and informed the Resolution Processional of Tecpro | ||||
14 | PIII RR1 | Distribution Systems- Balance works | 135 km | M/s Multitech JV/Shibu Zacharia | Work closed as on 31.12.2020 | Nil | ||||
15 | P IV | Service Reservoirs | 14 Nos. of capacity 25.02 ML | M/s IVRCL Ltd., Hyderabad | Completed | Nil | ||||
16 | 3 | Cherthala Scheme | 491.3 | Original packages - 4 Rearranged package - 0 | P I | Intake, Raw Water Pipeline and WTP | 107 MLD | M/s VA Tech Wabag Ltd., Chennai, (Consortium) | Completed | Court case and Arbitration case pending. |
17 | P II | Treated Water Transmission Pipeline | 81 Km | M/s IVRCL Ltd., Hyderabad | Completed | Bill closed. SCADA rectification works was arranged by CDAC at the risk and cost of M/s IVRCL. | ||||
18 | P III | Distribution Systems | 663 Km | M/s IVRCL Ltd., Hyderabad | Completed | Nil | ||||
19 | P IV | Service Reservoirs | 18 Nos. of capacity 35.83 ML | M/s Engineering Projects India Ltd. | Completed | Nil | ||||
20 | 4 | Kozhikode Scheme | 805.6 | Original packages - 6 Rearranged package - 5 | P I | Intake, Raw Water Pipeline and WTP | 174 MLD | M/s Degremont, France, (Consortium) | Completed | Final bill closed. |
21 | P IIA | Treated Water Transmission Pipeline | 122.2 Km | M/s Larsen & Toubro Ltd., Chennai | Completed | Final bill closed | ||||
22 | P IIB | Treated Water Transmission Pipeline | M/s Larsen & Toubro Ltd., Chennai | Completed | Final bill closed | |||||
23 | P III | Distribution Systems | 1854 km | M/s K. Ramakrishna Contractors Pvt. Ltd., Hyderabad | Contract terminated and rearranged as PIII R1 and PIII R2 | Court case pending. | ||||
24 | PIII R1 | Distribution Systems -Balance works | 435 km | M/s Shriram EPC Ltd., Chennai | Work closed as on 31.03.2020 | Risk and cost liability to be obtained from EE,Project Division, Kozhikode. Final bill to be closed. | ||||
25 | PIII R2 | Distribution Systems- Balance works | 750 km | M/s Shriram EPC Ltd., Chennai | Work closed as on 31.03.2021 | Risk and cost liability to be obtained from EE,Project Division, Kozhikode. Final bill to be closed. | ||||
26 | P IV | Service Reservoirs | 20 Nos. of capacity 100.78 ML | M/s IVRCL Ltd., Hyderabad | Completed. Scope reduced to 17 Nos, as land for reservoir construction was not available at 3 sites | Nil | ||||
27 | PIV R1 | Service Reservoirs at Thalakulathur | Thalakulathur OHSR | M/s Noble Tech Pvt. Ltd., Kerala | Completed | Nil | ||||
28 | PIV R2 | Service Reservoirs at Kakkur | Kakkur GLSR | M/s Noble Tech Pvt. Ltd., Kerala | Completed | Nil | ||||
29 | PIV R3 | Service Reservoirs at Narikunni | Narikunni OHSR | M/s Noble Tech Pvt. Ltd., Kerala | Completed | Nil | ||||
30 | P V | Rehabilitation Works of Existing System | Intake, WTP, Treated water sump and pump house, Transmission main | M/s. Koya Constructions, Hyderabad | Completed | Nil | ||||
31 | 5 | Pattuvam Scheme | 392.2 | Original packages - 4 Rearranged package - 3 | P I | Intake, Raw Water Pipeline and WTP | 90 MLD | M/s Kirloskar Brothers Ltd., Pune, (Consortium) | Completed | Nil |
32 | P II | Treated Water Transmission Pipeline | 82 km | M/s SPML Infra Ltd., Bangalore | Completed | Final bill closed. | ||||
33 | P III | Distribution Systems | 623 km | M/s K. Ramakrishna Contractors Pvt. Ltd., Hyderabad | Contract terminated and rearranged as PIII R1, PIII R5 and PIII R6 | Court case pending. | ||||
34 | PIII R1 | Distribution Systems -Balance works | 285 km | M/s Shriram EPC Ltd., Chennai | Completed | Closed | ||||
35 | PIII R5 | Distribution Systems- Balance works | 85.27 km | M/s TECPRO Infra Ltd., Kochi | Completed | Resolution Processional of Tecpro filed a case before NCLT | ||||
36 | PIII R6 | Distribution Systems -Balance works | 90.7 km | M/s TECPRO Infra Ltd., Kochi | Completed | Resolution Processional of Tecpro filed a case before NCLT | ||||
37 | P IV | Service Reservoirs | 13 Nos of 27.12 ML capacity | M/s IVRCL Ltd., Hyderabad | Completed | Nil | ||||
38 | 6 | IS | IS - Flow Meters | M/s Yokogava | Completed | Final bill settled and informed the firm M/s Yokogawa. But they submitted objection in the bill. | ||||
39 | 7 | IS-Asset Mapping | M/s. ULCCS | Completed | Final bill settled. | |||||
40 | 8 | IS- Asset Mapping | M/s. KSREC | Completed | Final bill settled. | |||||
41 | 9 | Consultancy for CCU Building | M/s Habitat | Completed | Hearing conducted with M/s Habitat by MD and the proceedings of time extension was issued to the firm. M/s Habitat raised objection on LD imposed. | |||||
42 | 10 | IS - CCU Building | M/s Mary Matha | Completed | Contractor has come with additional claims. Hearing conducted with the firm by CE on 3.11.2022 and a committee was constituted to check the anomalies. Committee met on 6.12.2022 in presence of representative of firm and verified the anomalies. | |||||
43 | Consultancy contract | M/s TECC | Completed | Final payment to be done. Proceedings for making balance payment of Rs.1,67,76,860/- approved on 14.02.23 and fund request to FM submitted on 17.02.23. |