1 | Epic | User Story ID | Parent PBI | ID | Status | PBI -- Sizing [0, 1, 1, 2, 3, 5, 8, 13, 21, 34, 55, 89] | Value [1-5] | Size/Effort | Risk [1-5] | Priority | Notes | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
4 | BIZ | XXXX.XX-XX-XX | BIZ-03 | blocked (external) | Work with Legal on Trademark Filing | |||||||
5 | PIC | 2018.05-01-01 | PIC-01 | not done | Submit application to Crowd Supply to see if they would be interested in Holoseat | 5 | 3 | 1 | 30.00 | |||
6 | RAT | 2018.02-01-01 | RAT-01 | outsource | Design basic survey for how much the holoseat has been used and what they have played | 2 | 2 | 1 | 20.00 | |||
7 | RAT | 2018.02-01-01 | RAT-02 | outsource | Design automated email with mailing list for notifying users to fill out data survey weekly | 2 | 1 | 1 | 30.00 | |||
8 | RAT | 2018.02-01-03 | RAT-03 | outsource | Design a survey template to ask about changes over the last month for testers | 2 | 2 | 1 | 20.00 | |||
9 | RAT | 2018.02-01-02 | RAT-04 | outsource | Design a survey to see how satisfied the users are with their experience in using the Holoseat (SW, HW, UX) | 2 | 2 | 1 | 20.00 | |||
10 | RAT | 2018.02-01-02 | RAT-05 | outsource | Design automated email with mailing list for notifying users to fill out the satisfaction survey weekly | 2 | 1 | 1 | 30.00 | |||
11 | RAT | 2018.02-02-01 | RAT-06 | outsource | Design a generic survey to ask about specific issues for games (focus on general UX and asking if there are issues) | 2 | 2 | 1 | 20.00 | |||
12 | RAT | 2018.02-02-04 | RAT-07 | outsource | Setup notifications for new game survey so that we are aware someone has submitted it immediately | 2 | 2 | 1 | 20.00 | |||
13 | RAT | 2018.02-02-03 | RAT-08 | outsource | Design a generic survey focusing on changes to the Holoseat application needed for classes of games | 2 | 2 | 1 | 20.00 | |||
14 | RAT | 2018.02-02-04 | RAT-09 | outsource | Set expectation to fill out new game survey each time they try out a new game with the Holoseat | 2 | 1 | 1 | 30.00 | |||
15 | RAT | 2018.02-02-02 | RAT-10 | outsource | Include a drop down for game type so that we can collate data across multiple games | 2 | 1 | 1 | 30.00 | |||
16 | RAT | 2018.02-02-02 | RAT-11 | outsource | Design reporting to pull data together based on game types | 2 | 2 | 1 | 20.00 | |||
17 | RAT | 2018.02-03-01 | RAT-12 | outsource | Ask Lawyer about collecting health data and verify requirements for data security | 5 | 2 | 2 | 46.67 | |||
18 | RAT | 2018.02-03-02 | RAT-13 | outsource | Implement the required data security | 3 | 5 | 3 | 20.00 | |||
19 | RAT | 2018.02-03-02 | RAT-14 | outsource | Identify method to collect health data anonymously | 5 | 2 | 2 | 46.67 | |||
20 | RAT | 2018.02-03-02 | RAT-15 | outsource | Generate survey to get heath and lifestyle data from users using anonymous method | 2 | 2 | 1 | 20.00 | |||
21 | RAT | 2018.02-03-06 | RAT-16 | outsource | Notify users to take the health survey prior to shipping the units | 4 | 1 | 1 | 50.00 | |||
22 | RAT | 2018.02-03-04 | RAT-17 | outsource | Setup monthly notification to submit new health survey | 2 | 1 | 1 | 30.00 | |||
23 | RAT | 2018.02-03-05 | RAT-18 | Identify what statistics we want to share with the users | 3 | 1 | 1 | 40.00 | ||||
24 | RAT | 2018.02-03-05 | RAT-19 | outsource | Design reporting to pull statistics together while hiding the base data | 2 | 2 | 1 | 20.00 | |||
30 | SME | 2018.04-01-07 | SME-06 | not done | Publish at least one blog post in November | 3 | 3 | 1 | 20.00 | |||
33 | SME | 2018.04-01-07 | SME-09 | not done | Publish at least one blog post in Feb | 3 | 3 | 1 | 20.00 | |||
34 | SME | 2018.04-01-09 | SME-10 | outsource | Research gamify exercise competition (e.g. Pelaton and Virzoom) | 3 | 3 | 1 | 20.00 | |||
35 | SME | 2018.04-01-01 | SME-11 | outsource | Publish overview of gamification and gamification of exercise | 2 | 3 | 1 | 15.00 | |||
36 | SME | 2018.04-01-01 | SME-12 | outsource | Publish essay on gamification of exercise and it's failures | 2 | 3 | 1 | 15.00 | |||
37 | SME | 2018.04-01-09 | SME-13 | outsource | Research exerfy games competition (e.g. PC Gamer Bike and Hack a Day DIY projects) | 3 | 3 | 1 | 20.00 | |||
38 | SME | 2018.04-01-01 | SME-14 | Publish essay on concept of Exerfication and it's advantages compared to gamification | 2 | 3 | 1 | 15.00 | ||||
42 | V04 | 2018.01-01-06 | V04-04 | outsource | Get all testers to post on the ODE forums | 3 | 2 | 1 | 26.67 | |||
43 | V04 | 2018.01-01-07 | V04-05 | outsource | Get all testers to interact with one of the social media presenses | 3 | 2 | 1 | 26.67 | |||
44 | V04 | 2018.01-01-04 | V04-06 | Have testers review and provide feedback for UX mockup | 3 | 2 | 1 | 26.67 | ||||
45 | V04 | 2018.01-01-03 | V04-07 | outsource | Invite testers to our normal meetings through email list | 2 | 1 | 1 | 30.00 | |||
47 | V04 | 2018.01-01-05 | V04-09 | Have testers review and provide feedback for 3D renders of housing | 3 | 2 | 1 | 26.67 | ||||
52 | V04 | 2018.01-02-01 | V04-14 | selected | Select tone ring based on ease to adapt, costs, identical or faster response times, improved single step | 5 | 2 | 2 | 46.67 | |||
67 | V04 | 2018.01-02-06 | V04-29 | outsource | Design a housing in Fusion 360 for the Feather and daughter board as well as the LED button and TRRS jack (Controller Housing) | 5 | 5 | 1 | 20.00 | |||
68 | V04 | 2018.01-02-06 | V04-30 | selected | Test prints of both housings to confirm they will work | 5 | 2 | 2 | 46.67 | |||
70 | V04 | 2018.01-02-07 | V04-32 | outsource | Make sure we have CircuitMaker models of all electronics | 3 | 2 | 2 | 33.33 | |||
71 | V04 | 2018.01-02-07 | V04-33 | outsource | Make sure we have Fusion 360 drawings of all 3D printed objects | 3 | 2 | 3 | 40.00 | |||
72 | V04 | 2018.01-02-07 | V04-34 | Make sure the BOM is up to date | 3 | 1 | 1 | 40.00 | ||||
73 | V04 | 2018.01-02-07 | V04-35 | Make sure the firmware is loaded onto ODE | 3 | 1 | 1 | 40.00 | ||||
74 | V04 | 2018.01-02-07 | V04-36 | Make sure assembly instructions are on ODE wiki | 3 | 5 | 1 | 13.33 | ||||
75 | V04 | 2018.01-02-07 | V04-37 | Make sure the operating manual is on the ODE wiki | 3 | 3 | 1 | 20.00 | ||||
76 | V04 | 2018.01-02-07 | V04-38 | Make sure version landing page is set on ODE | 3 | 1 | 1 | 40.00 | ||||
77 | V04 | 2018.01-02-07 | V04-39 | Make sure block diagram is up to date on ODE | 3 | 5 | 1 | 13.33 | ||||
78 | V04 | 2018.01-02-07 | V04-40 | Make sure software page is up to date | 3 | 3 | 1 | 20.00 | ||||
79 | V04 | 2018.01-02-07 | V04-41 | File for OSHWA certification | 3 | 2 | 1 | 26.67 | ||||
85 | V04 | 2018.01-03-01 | V04-47 | Develop and document outline of new version of HSP | 4 | 3 | 1 | 25.00 | ||||
86 | V04 | 2018.01-03-01 | V04-48 | Implement new version of HSP in controller firmware | 3 | 5 | 1 | 13.33 | ||||
90 | V04 | 2018.01-02-04 | V04-52 | outsource | Figure out how to stabilize the TRRS jack when using female header | 5 | 2 | 2 | 46.67 | |||
93 | V04 | 2018.01-03-06 | V04-55 | Implement basic configuration for defaults for standard settings in UI | 4 | 3 | 2 | 30.00 | ||||
94 | V04 | 2018.01-03-06 | V04-56 | Implement basic configuration for live modification of settings in UI | 4 | 3 | 2 | 30.00 | ||||
95 | V04 | 2018.01-03-06 | V04-57 | not done | Implement about screen to include versions, licensing, and other required information for all major elements of the Holoseat (SW,HW,FW,HSP,REST API) | 4 | 2 | 1 | 33.33 | |||
99 | V04 | 2018.01-03-02 | V04-61 | Implement v0.4 required REST API methods for HSP | 4 | 5 | 1 | 16.67 | ||||
100 | V04 | 2018.01-03-04 | V04-62 | outsource | Review system resource usage to confirm we aren't using more than is necessary | 3 | 2 | 1 | 26.67 | |||
101 | V04 | 2018.01-03-07 | V04-63 | Package up the desktop app with pyinstaller | 3 | 2 | 3 | 40.00 | ||||
102 | V04 | 2018.01-03-07 | V04-64 | outsource | Package Adafruit driver and pyinstaller in a single Holoseat installer for Windows | 2 | 2 | 1 | 20.00 | |||
103 | V04 | 2018.01-04-06 | V04-65 | Design unit test for tone ring | 3 | 3 | 1 | 20.00 | ||||
104 | V04 | 2018.01-04-06 | V04-66 | Design unit test for Wing | 3 | 3 | 2 | 25.00 | ||||
105 | V04 | 2018.01-04-06 | V04-67 | Design unit test for Sensor assembly | 3 | 2 | 1 | 26.67 | ||||
106 | V04 | 2018.01-04-06 | V04-68 | Design troubleshooting unit test for TRRS jack | 2 | 2 | 1 | 20.00 | ||||
107 | V04 | 2018.01-04-06 | V04-69 | Design troubleshooting unit test for the keyswitch | 2 | 2 | 1 | 20.00 | ||||
108 | V04 | 2018.01-04-08 | V04-70 | outsource | Brand tone ring | 3 | 3 | 2 | 25.00 | |||
110 | V04 | 2018.01-04-08 | V04-72 | branding on housing | 3 | 2 | 2 | 33.33 | ||||
111 | V04 | 2018.01-04-09 | V04-73 | outsource | Compare shipping between UPS/FedEx/DHL/USPS and see what will be most cost effective | 2 | 1 | 1 | 30.00 | |||
112 | V04 | 2018.01-04-07 | V04-74 | Develop assembly plan for units | 3 | 5 | 2 | 16.67 | ||||
113 | V04 | 2018.01-04-07 | V04-75 | Develop test plan for units | 3 | 3 | 2 | 25.00 | ||||
114 | V04 | 2018.01-04-07 | V04-76 | develop shipping plan for units | 3 | 2 | 1 | 26.67 | ||||
115 | V04 | 2018.01-04-05 | V04-77 | Unpack Deskcycle making notes and carefully documenting how it was placed in the packaging | 3 | 1 | 1 | 40.00 | ||||
116 | V04 | 2018.01-04-05 | V04-78 | outsource | Carefully put deskcycle back in using the notes from unpacking so we reuse the original packaging | 3 | 8 | 1 | 8.89 | |||
117 | V04 | 2018.01-04-02 | V04-79 | Assemble wings and run through unit tests | 3 | 8 | 2 | 11.11 | ||||
118 | V04 | 2018.01-04-02 | V04-80 | Assemble tone rings and run thorugh unit tests | 3 | 8 | 2 | 11.11 | ||||
120 | V04 | 2018.01-04-03 | V04-82 | Perform final assembly and run through final assembly tests | 3 | 8 | 2 | 11.11 | ||||
121 | V04 | 2018.01-04-06 | V04-83 | Design final assembly test to confirm functionality when assembled | 3 | 5 | 2 | 16.67 | ||||
122 | V04 | 2018.01-04-04 | V04-84 | Sign each unit in orange sharpie | 3 | 1 | 1 | 40.00 | ||||
124 | V10 | 2018.03-01-03 | V10-01 | outsource | Have a volunteer familiar with injection molding review the Sensor Housing and make suggestions to allow the design to be usable for both | 5 | 2 | 1 | 40.00 | |||
125 | V10 | 2018.03-01-04 | V10-02 | outsource | Have a volunteer familiar with injection molding review the Controller Housing and make suggestions to allow the design to be usable for both | 5 | 2 | 1 | 40.00 | |||
129 | V10 | 2018.03-02-01 | V10-06 | Contact deskcycle for wholesale volume pricing for reduced costs | 3 | 3 | 2 | 25.00 | ||||
130 | V10 | 2018.03-02-01 | V10-07 | Contact cubii for wholesale volume pricing for reduced costs | 3 | 3 | 1 | 20.00 | ||||
131 | V10 | 2018.03-02-01 | V10-08 | Contact FitDesk for wholesale volume pricing for reduced costs | 3 | 3 | 1 | 20.00 | ||||
132 | V10 | 2018.03-02-04 | V10-09 | Move to 4 week sprint cadence during alpha test | 2 | 1 | 1 | 30.00 | ||||
133 | V10 | 2018.03-02-04 | V10-10 | outsource | Train testers on where to report support issues and feature requests | 2 | 1 | 1 | 30.00 | |||
134 | V10 | 2018.03-02-04 | V10-11 | outsource | Train testers on the differences between issues and feature requests | 2 | 1 | 1 | 30.00 | |||
135 | V10 | 2018.03-02-04 | V10-12 | Set expectations for when feature requests will be discussed and pulled into development | 2 | 1 | 1 | 30.00 | ||||
136 | V10 | 2018.03-02-05 | V10-13 | Set expectations for what software will be capable of at launch | 4 | 1 | 1 | 50.00 | ||||
137 | V10 | 2018.03-02-05 | V10-14 | Set expectations on what features we're trying to implement throughout testing | 4 | 1 | 1 | 50.00 | ||||
138 | V10 | 2018.03-02-05 | V10-15 | Develop basic profiles editing in UI | 3 | 5 | 2 | 16.67 | ||||
139 | V10 | 2018.03-02-05 | V10-16 | Develop profile selection within UI | 3 | 2 | 1 | 26.67 | ||||
140 | V10 | 2018.03-02-05 | V10-17 | Develop advanced profile features ("sprinting" etc...) | 3 | 3 | 2 | 25.00 | ||||
141 | V10 | 2018.03-02-05 | V10-18 | Develop advanced profile editing within UI | 3 | 8 | 3 | 13.33 | ||||
142 | V10 | 2018.03-02-02 | V10-19 | Design stand alone (non-feather) component version of the holoseat | 4 | 8 | 1 | 11.11 | ||||
143 | V10 | 2018.03-02-02 | V10-20 | Do a small scale run and test stand alone PCB | 3 | 5 | 1 | 13.33 | ||||
144 | V10 | 2018.03-02-02 | V10-21 | Finalize stand alone (non-feather) design | 4 | 3 | 1 | 25.00 | ||||
145 | V10 | 2018.03-02-06 | V10-22 | Make adjustments to controller housing so injection molding is possible | 4 | 5 | 2 | 20.00 | ||||
146 | V10 | 2018.03-02-06 | V10-23 | Confirm adjustments with manufacturer | 4 | 2 | 2 | 40.00 | ||||
147 | V10 | 2018.03-02-07 | V10-24 | Make adjustments for the sensor housing so injection molding is possible | 4 | 5 | 2 | 20.00 | ||||
148 | V10 | 2018.03-02-07 | V10-25 | Confirm adjustments w/ manufacturer | 4 | 2 | 2 | 40.00 | ||||
149 | V10 | 2018.03-02-03 | V10-26 | outsource | Review cost data from single build/BOM | 3 | 1 | 1 | 40.00 | |||
150 | V10 | 2018.03-02-03 | V10-27 | Review costing research regarding crowdsource campaigns | 3 | 3 | 1 | 20.00 | ||||
151 | V10 | 2018.03-02-03 | V10-28 | Review discounts for bulk and wholesale purchasing and compare to possible volume | 3 | 2 | 1 | 26.67 | ||||
152 | V10 | 2018.03-02-03 | V10-29 | Review labour costs compared to volume | 3 | 3 | 1 | 20.00 | ||||
153 | V10 | 2018.03-02-03 | V10-30 | Review for secondary costs such as marketing | 3 | 3 | 1 | 20.00 | ||||
154 | V10 | 2018.03-02-03 | V10-31 | outsource | Review shipping costs | 3 | 1 | 1 | 40.00 | |||
155 | V10 | 2018.03-02-03 | V10-32 | outsource | Compute expected COGS/unit | 3 | 2 | 1 | 26.67 | |||
156 | V10 | 2018.03-02-03 | V10-33 | outsource | Calculate MSRP | 3 | 2 | 1 | 26.67 | |||
157 | BIZ | XXXX.XX-XX-XX | BIZ-04 | blocked (external) | Work with legal on finalizing any updates to testing agreement | |||||||
158 | BIZ | XXXX.XX-XX-XX | BIZ-05 | not done | Communication Plan | |||||||
159 | BIZ | XXXX.XX-XX-XX | BIZ-06 | done | Meet with SBDC Innovation and Commercialization Assistance Program |
1 | Laying out Holoseat Agile Process | ||
---|---|---|---|
2 | |||
3 | Sprint Length | 8 | weeks |
4 | Stand Up Cadence | 1/week | |
5 | |||
6 | |||
7 | Show Date | ||
8 | Delivery Date | Aug 2, 2018 | |
9 | Time Remaining | -942 days | |
10 | Sprint Start Day | Thursdays | |
11 | Stand Up Day/Time | 8:00 Thursday | |
12 | |||
13 | Current Sprint | ||
14 | Sprint Start Date | 6/3/2018 | |
15 | Sprint End Date | 7/29/2018 | |
16 | Days Remaining | -946 days | |
17 | |||
18 | |||
19 | |||
20 | |||
21 | |||
22 | |||
23 | |||
24 | |||
25 | |||
26 | |||
27 | |||
28 | |||
29 | |||
30 | |||
31 | |||
32 | |||
33 | |||
34 | |||
35 | |||
36 | |||
37 | |||
38 | |||
39 | Desired Deliverables | Breadboard prototype (HW) | |
40 | Hall Effect Sensor | ||
41 | Forward/backward motion | ||
42 | Controller overlay | ||
43 | Bluetooth | ||
44 | Leonardo Alternative | ||
45 | Switch between keyboard and HID device | ||
46 | Business (BIZ) | ||
47 | LLC Moved to DC | ||
48 | Launch Crowd Source campaign | ||
49 | Software Goals (SW) | ||
50 | Control Mapping | ||
51 | Step/distance counter | ||
52 | Social networking integration | ||
53 | Improve Configuration managment | ||
54 | Multiple profiles |
1 | Classification | Task | Responsible | OoO/Responsible | OoO | Status | Size (Fibonacci) | Work Remaining: | 8 | Date | Planned | Burn Down | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2 | Social | Install Glue between Wordpress and social media (twitter/facebook) | Bryan | 1 | 1 | done | 0 | 6/3/2018 | 105 | |||||||||||
3 | Social | Verify wordpress Template plugin | Bryan | 2 | 2 | Done | 0 | 7/29/2018 | 0 | |||||||||||
4 | Build | Count all components and order additional materials if needed for 15 total units | Everyone | 3 | 3 | done | 0 | 6/3/2018 | 105 | |||||||||||
5 | Con | Coordinate with D. about Syndcon (panel, main meeting, getting demos on official schedule, raffle) | J | 1 | 4 | done | 0 | 6/9/18 | 96 | |||||||||||
6 | Social | Make template for stand up status update posts in Wordpress | J | 2 | 5 | done | 0 | 6/16/18 | 79 | |||||||||||
7 | Social | Make Template for photo social media posts in Wordpress | J | 3 | 6 | done | 0 | 6/23/18 | 72 | |||||||||||
8 | Social | Make template for re-share posts in Wordpress | J | 4 | 7 | done | 0 | 7/7/2018 | 71 | |||||||||||
9 | Build | Confirm functionality for alternative exercise equipment (other bike) | J | 5 | 8 | done | 0 | 7/14/2018 | 52 | |||||||||||
10 | Build | Confirm functionality for alternative exercise equipment (elliptical) | Bryan | 11 | 9 | done | 0 | 7/21/2018 | 37 | |||||||||||
11 | Delivery | Message testers to let them know we will have an updated set of terms to sign (and ask t-shirt size) | Bryan | 5 | 10 | done | 0 | 7/22/2018 | 28 | |||||||||||
12 | Delivery | Message testers to let them know they will need to purchase their own equipment | Bryan | 6 | 11 | done | 0 | 7/28/2018 | 14 | |||||||||||
13 | Social | Start using templates for stand ups and pics asap (back date posts for stand ups at start) | Everyone | 1 | 12 | done | 0 | 7/31/18 | 8 | |||||||||||
14 | Build | Bag controller parts for documentation assembly (including feather and its bits) | Bryan | 4 | 13 | done | 0 | |||||||||||||
15 | Build | Build 14 snap fit tone rings | J | 6 | 14 | selected | 1 | |||||||||||||
16 | Build | Build 14 controller housings | J | 7 | 15 | done | 0 | |||||||||||||
17 | Build | Build 8 alpha units main systems for delivery (meta) | Bryan | 7 | 16 | Done | 3 | |||||||||||||
18 | Delivery | Message testers to let them know we will be delivering at Syndcon | Bryan | 8 | 17 | done | 0 | |||||||||||||
19 | Build | Build 5 more sensors for use at Syndcon | J | 8 | 18 | done | 0 | |||||||||||||
20 | Build | Build 2 alpha units main systems for raffle (meta) | Bryan | 9 | 19 | Done | 3 | |||||||||||||
21 | Con | Plan demo schedule (Need to wait on actual con schedule) | Everyone | 2 | 20 | done | 0 | |||||||||||||
22 | Con | Find and pack all items for demos (table risers, demo computers, etc.) | Bryan | 10 | 21 | Done | 0 | Post Sprint | ||||||||||||
23 | Build | Build 3-4(including ours) unit main systems for demos (meta) | Bryan | 12 | 22 | done | 0 | |||||||||||||
24 | Con | Generate panel presentation (year in review, plans, ask for follow) | Everyone | 3 | 23 | Done | 1 | Just need 2 slides from Bryan | ||||||||||||
25 | Con | Generate main meeting presentation (status, ask to follow) | Everyone | 4 | 24 | Done | 0 | Using first set of slides from panel | ||||||||||||
26 | Delivery | Ship alpha units to testers not at Syndcon | Everyone | 5 | 25 | 0 | post con, so not in this sprint | |||||||||||||
27 | Build | Build 12 controllers | Bryan | 7,9,12 |
1 | Epic | User Story ID | Parent PBI | ID | Status | PBI -- Sizing [0, 1, 1, 2, 3, 5, 8, 13, 21, 34, 55, 89] | Value [1-5] | Size/Effort | Risk [1-5] | Priority | Notes |
---|---|---|---|---|---|---|---|---|---|---|---|
52 | V04 | 2018.01-02-01 | V04-14 | selected | Select tone ring based on ease to adapt, costs, identical or faster response times, improved single step | 5 | 2 | 2 | 46.67 | <need to tweak snap fit part of design> | |
68 | V04 | 2018.01-02-06 | V04-30 | selected | Test prints of both housings to confirm they will work | 5 | 2 | 2 | 46.67 | <Sensor housing is tested> | |
69 | V04 | 2018.01-02-05 | V04-31 | selected | Take components and build prototypes for Bryan and J of v0.4 | 4 | 1 | 2 | 60.00 | B: Build and send J an updated test board. | |
119 | V04 | 2018.01-04-02 | V04-81 | selected | Assemble sensors and run through unit tests | 3 | 5 | 1 | 13.33 | J: finish sensor build docs and build qualled sensor |
1 | w | User Story ID | Parent PBI | ID | Status | PBI -- Sizing [0, 1, 1, 2, 3, 5, 8, 13, 21, 34, 55, 89] | Value [1-5] | Size/Effort | Risk [1-5] | Priority | Notes | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
77 | BIZ | XXXX.XX-XX-XX | BIZ-03 | blocked (external) | Work with Legal on Trademark Filing | Bryan | ||||||
78 | BIZ | XXXX.XX-XX-XX | BIZ-04 | blocked (external) | Work with legal on finalizing any updates to testing agreement | Bryan | ||||||
79 | BIZ | XXXX.XX-XX-XX | BIZ-01 | done | Prep books for taxes | Bryan | ||||||
80 | BIZ | XXXX.XX-XX-XX | BIZ-06 | done | Meet with SBDC Innovation and Commercialization Assistance Program | Bryan & J | ||||||
81 | SME | 2018.04-01-07 | SME-08 | done | Publish at least one blog post in Jan. | 3 | 3 | 1 | 20.00 | J | ||
82 | V04 | 2018.01-02-02 | V04-22 | done | Load Adafruit wing design into CircuitMaker | 4 | 2 | 1 | 33.33 | Bryan | ||
83 | V04 | 2018.01-02-02 | V04-23 | done | Modify Adafruit Wing to handle the required components and have the necessary headers | 5 | 3 | 1 | 30.00 | Bryan | ||
84 | V04 | 2018.01-02-02 | V04-25 | done | Order initial test run of board for Wing | 4 | 2 | 2 | 40.00 | Bryan | ||
85 | V04 | 2018.01-02-02 | V04-26 | done | Assemble a test Wings to verify design (on proto-wing) | 5 | 1 | 2 | 70.00 | Bryan | ||
86 | V04 | 2018.01-02-06 | V04-28 | done | Design a housing in Fusion 360 for the sensor and TRRS jack (Sensor Housing) | 5 | 5 | 1 | 20.00 | J | ||
87 | V04 | 2018.01-02-08 | V04-58 | done | Implement hardware versioning system that can be detected by Holoseat software | 4 | 3 | 1 | 25.00 | J | ||
89 | V10 | 2018.03-01-02 | V10-03 | done | Research sensor mount adhesives | 4 | 1 | 1 | 50.00 | Bryan | ||
90 | V10 | 2018.03-01-02 | V10-04 | done | Test mount adhesive | 4 | 1 | 1 | 50.00 | J & Bryan | ||
91 | V10 | 2018.03-01-02 | V10-05 | done | Select mount adhesive | 4 | 1 | 1 | 50.00 | J & Bryan | ||
92 | BIZ | XXXX.XX-XX-XX | BIZ-02 | not done | Mid Year Planning - Review/Groom User Stories and Backlog* | 3. Bryan & J | ||||||
154 | BIZ | XXXX.XX-XX-XX | BIZ-05 | not done | Communication Plan* | 2. Bryan & J | ||||||
155 | PIC | 2018.05-01-01 | PIC-01 | not done | Submit application to Crowd Supply to see if they would be interested in Holoseat* | 5 | 3 | 1 | 30.00 | 1. J & Bryan | ||
156 | SME | 2018.04-01-07 | SME-09 | not done | Publish at least one blog post in Feb | 3 | 3 | 1 | 20.00 | J | ||
157 | V04 | 2018.01-02-01 | V04-13 | not done | Test the tone rings against the behavior of the existing 12 pole 3D printed design (at least same performance, but looking for faster response times and improved single stepping) | 4 | 3 | 3 | 35.00 | J & Bryan | ||
158 | V04 | 2018.01-02-01 | V04-14 | not done | Select tone ring based on ease to adapt, costs, identical or faster response times, improved single step | 5 | 2 | 2 | 46.67 | J & Bryan | ||
159 | V04 | 2018.01-03-06 | V04-57 | not done | Implement about screen to include versions, licensing, and other required information for all major elements of the Holoseat (SW,HW,FW,HSP,REST API) | 4 | 2 | 1 | 33.33 | J |
1 | Epic | User Story ID | Parent PBI | ID | Status | PBI -- Sizing [0, 1, 1, 2, 3, 5, 8, 13, 21, 34, 55, 89] | Value [1-5] | Size/Effort | Risk [1-5] | Priority | Notes | |
---|---|---|---|---|---|---|---|---|---|---|---|---|
21 | PIC | 2018.05-01-01 | PIC-01 | selected | Submit application to Crowd Supply to see if they would be interested in Holoseat | 5 | 3 | 1 | 30.00 | |||
22 | RAT | 2018.02-03-01 | RAT-12 | selected | Ask legal aid about collecting health data and verify requirements for data security | 5 | 2 | 2 | 46.67 | |||
23 | SME | 2018.04-01-04 | SME-01 | done | Get Jazmint signed up for Lastpass so we can share passwors securely for social media | 5 | 2 | 1 | 40.00 | |||
24 | SME | 2018.04-01-04 | SME-02 | done | Split social media accounts out into a seperate folder | 5 | 1 | 1 | 60.00 | |||
25 | SME | 2018.04-01-04 | SME-03 | done | share only the social media folder with Jazmint | 5 | 1 | 1 | 60.00 | |||
26 | SME | 2018.04-01-07 | SME-06 | not done | Publish at least one blog post in November | 3 | 3 | 1 | 20.00 | |||
27 | SME | 2018.04-01-07 | SME-07 | done | Publish at least one blog post in December | 3 | 3 | 1 | 20.00 | |||
28 | SME | 2018.04-01-09 | SME-10 | outsource selected | Research gamify exercise competition (e.g. Pelaton and Virzoom) | 3 | 3 | 1 | 20.00 | |||
29 | SME | 2018.04-01-01 | SME-11 | outsource selected | Publish overview of gamification and gamification of exercise | 2 | 3 | 1 | 15.00 | |||
31 | SME | 2018.04-01-09 | SME-13 | outsource selected | Research exerfy games competition (e.g. PC Gamer Bike and Hack a Day DIY projects) | 3 | 3 | 1 | 20.00 | |||
32 | V04 | 2018.01-02-01 | V04-13 | selected | Test the tone rings against the behavior of the existing 12 pole 3D printed design (at least same performance, but looking for faster response times and improved single stepping) | 4 | 3 | 3 | 35.00 | Depends on V04-15 | ||
33 | V04 | 2018.01-02-01 | V04-14 | selected | Select tone ring based on ease to adapt, costs, identical or faster response times, improved single step | 5 | 2 | 2 | 46.67 | |||
40 | V04 | 2018.01-02-01 | V04-15 | selected | Adapt test rig to use the new auto-adjusting cadence firmware | 4 | 5 | 1 | 16.67 | |||
41 | V04 | 2018.01-02-04 | V04-16 | done | Place order for replacement components on the v0.4 BOM for confirming suitability | 5 | 1 | 1 | 60.00 | |||
42 | V04 | 2018.01-02-02 | V04-24 | outsource selected | Have layout double checked by a volunteer with layout experience | 4 | 1 | 1 | 50.00 | |||
49 | V04 | 2018.01-02-02 | V04-26 | selected | Assemble a test Wings to verify design (on proto-wing) | 5 | 1 | 2 | 70.00 | |||
55 | V04 | 2018.01-02-03 | V04-27 | done | Order at quanity any parts where we have high confidence and a reasonable discount | 5 | 1 | 1 | 60.00 | |||
56 | V04 | 2018.01-02-06 | V04-28 | outsource selected | Design a housing in Fusion 360 for the sensor and TRRS jack (Sensor Housing) | 5 | 5 | 1 | 20.00 | |||
61 | V04 | 2018.01-02-06 | V04-29 | outsource selected | Design a housing in Fusion 360 for the Feather and daughter board as well as the LED button and TRRS jack (Controller Housing) | 5 | 5 | 1 | 20.00 | |||
62 | V04 | 2018.01-02-06 | V04-30 | selected | Test prints of both housings to confirm they will work | 5 | 2 | 2 | 46.67 | |||
69 | V04 | 2018.01-03-01 | V04-47 | selected | Develop and document outline of new version of HSP | 4 | 3 | 1 | 25.00 | |||
82 | V04 | 2018.01-03-01 | V04-48 | selected | Implement new version of HSP in controller firmware | 3 | 5 | 1 | 13.33 | |||
91 | V04 | 2018.01-03-01 | V04-49 | done | Implement python serial library for accessing new version of HSP | 3 | 2 | 2 | 33.33 | |||
96 | V04 | 2018.01-03-03 | V04-50 | done | Implement foundation of desktop app in flask | 4 | 3 | 2 | 30.00 | |||
105 | V04 | 2018.01-03-03 | V04-51 | done | Implement Serial Monitor feature | 4 | 3 | 2 | 30.00 | |||
106 | V04 | 2018.01-02-04 | V04-52 | outsource selected | Figure out how to stabilize the TRRS jack when using female header | 5 | 2 | 2 | 46.67 | Depends on V04-26 | ||
130 | V04 | 2018.01-02-08 | V04-58 | selected | Implement hardware versioning system that can be detected by Holoseat software | 4 | 3 | 1 | 25.00 | |||
131 | V04 | 2018.01-02-08 | V04-59 | outsource selected | Design scheme for checking the hardware version so the software can find compatibility | 5 | 2 | 1 | 40.00 | |||
134 | V04 | 2018.01-03-02 | V04-60 | done | Design Rest API in seperate thread that is running using serial protocol | 4 | 3 | 2 | 30.00 | |||
135 | V04 | 2018.01-03-02 | V04-61 | selected | Implement v0.4 required REST API methods for HSP | 4 | 5 | 1 | 16.67 | |||
136 | V04 | 2018.01-04-08 | V04-71 | done | Branding on keycap | 3 | 2 | 1 | 26.67 | |||
137 | V10 | 2018.03-01-03 | V10-01 | outsource selected | Have a volunteer familiar with injection molding review the Sensor Housing and make suggestions to allow the design to be usable for both | 5 | 2 | 1 | 40.00 | |||
141 | V10 | 2018.03-01-04 | V10-02 | outsource selected | Have a volunteer familiar with injection molding review the Controller Housing and make suggestions to allow the design to be usable for both | 5 | 2 | 1 | 40.00 |