1 | Johannesburg | Johannesburg | Nairobi | Nairobi | |
---|---|---|---|---|---|
2 | ZAR | USD | KES | USD | |
3 | Commercial | ||||
4 | CBD Offices – high-rise prestige | 21,600 | 1,146 | 132,000 | 1,006 |
5 | CBD Offices – up to 20 floors medium (A-Grade) | 17,300 | 918 | 94,500 | 720 |
6 | Education | ||||
7 | Primary and secondary | 11,000 | 584 | 50,000 | 381 |
8 | General Hospital (e.g. city teaching hospital) | 31,800 | 1,687 | 143,000 | 1,090 |
9 | Hotels | ||||
10 | 3-Star travellers | 20,100 | 1,067 | 142,000 | 1,082 |
11 | 5-Star luxury | 29,200 | 1,549 | 173,000 | 1,318 |
12 | Resort style | 28,300 | 1,502 | 157,500 | 1,200 |
13 | Industrial | ||||
14 | Advanced manufacturing facility | 18,000 | 955 | 115,500 | 880 |
15 | Large warehouse distribution centre | 7,300 | 387 | 70,000 | 533 |
16 | Retail | ||||
17 | Large shopping centre including mall | 19,100 | 1,014 | 80,000 | 610 |
18 | Neighbourhood incl supermarket | 14,100 | 748 | 70,000 | 533 |
19 | Prestige car showroom | 15,700 | 833 | 84,000 | 640 |
20 | Residential | ||||
21 | Apartments high-rise | 20,400 | 1,082 | 70,000 | 533 |
22 | Townhouses medium standard | 11,800 | 626 | 60,000 | 457 |
1 | Labour, material and plant costs | Johannesburg | Johannesburg | Nairobi | Nairobi |
---|---|---|---|---|---|
2 | ZAR | USD | KES | USD | |
3 | Labour costs (rates per hour) | ||||
4 | Group 1 Tradesman e.g. plumber/electrician | 116 | 6 | 250 | 2 |
5 | Group 2 Tradesman e.g. carpenter bricklayer | 90 | 5 | 250 | 2 |
6 | Group 3 Tradesman e.g. carpet layer, tiler, plasterer | 90 | 5 | 250 | 2 |
7 | Group 4 Green collar installation operative e.g. insulation/solar/heat pump | 116 | 6 | 300 | 2 |
8 | General labourer | 65 | 3 | 100 | 1 |
9 | Site foreman | 272 | 14 | 375 | 3 |
10 | Material costs | ||||
11 | 13 mm plasterboard (m²) | 98 | 5 | 585 | 4 |
12 | Concrete 30 MPa (m³) (1500m³ job) | 1,987 | 105 | 11,400 | 87 |
13 | Concrete block (400x200) per 1000 (>10,000 block job) | 8,200 | 435 | 55,000 | 419 |
14 | Copper cable (metre) (3C + E, 2.5mm PVC) (100,000m+ job) | 50 | 3 | 450 | 3 |
15 | Copper pipe 15 mm (metre) (1000+ metre job) | 129 | 7 | 1,600 | 12 |
16 | Emulsion paint (litre) | 50 | 3 | 950 | 7 |
17 | Glass pane 10mm tempered (m²) | 1,750 | 93 | 7,000 | 53 |
18 | Reinforcement bar 16mm (tonne) (120 tonne job) | 22,664 | 1,203 | 136,000 | 1,036 |
19 | Softwood timber for framing 100mm X 50mm (m) | 97 | 5 | 900 | 7 |
20 | Standard brick per 1000 | 2,520 | 134 | 49,000 | 373 |
21 | Structural steel beams (tonne) (100 tonne+ job) | 31,715 | 1,683 | 160,000 | 1,219 |
22 | Plant costs (rates per day) | ||||
23 | Hire 50t mobile crane + operator (day) | 13,600 | 722 | 100,000 | 762 |
1 | International building costs per m² of internal area | Hong Kong | Hong Kong | Jakarta | Jakarta | Mumbai | Mumbai | Shanghai | Shanghai | Kuala Lumpur | Kuala Lumpur | Seoul | Seoul | Singapore | Singapore | Tokyo | Tokyo |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2 | CNY | USD | IDR | USD | INR | USD | CNY | USD | MYR | USD | KRW | USD | SGD | USD | JPY | USD | |
3 | Commercial | ||||||||||||||||
4 | CBD Offices – high-rise prestige | 34,500 | 4,409 | 18,000,000 | 1,134 | 60,800 | 730 | 9,300 | 1,288 | 7,000 | 1,482 | 3,178,000 | 2,365 | 4,100 | 3,041 | 733,000 | 4,845 |
5 | CBD Offices – up to 20 floors medium (A-Grade) | 29,500 | 3,770 | 13,900,000 | 876 | 54,700 | 656 | 8,000 | 1,108 | 5,750 | 1,218 | 2,524,000 | 1,878 | 3,650 | 2,707 | 611,000 | 4,038 |
6 | Education | ||||||||||||||||
7 | Primary and secondary | 30,800 | 3,936 | 9,200,000 | 580 | 35,600 | 427 | 4,150 | 575 | 2,770 | 587 | 1,869,000 | 1,391 | 2,000 | 1,484 | 494,000 | 3,265 |
8 | General Hospital (e.g. city teaching hospital) | 44,000 | 5,624 | 22,200,000 | 1,399 | 69,550 | 835 | 6,500 | 900 | 5,500 | 1,165 | 2,734,000 | 2,034 | 5,450 | 4,043 | 466,000 | 3,080 |
9 | Hotels | ||||||||||||||||
10 | 3-Star travellers | 34,800 | 4,448 | 14,750,000 | 929 | 69,600 | 835 | 6,550 | 907 | 6,600 | 1,398 | 2,752,000 | 2,048 | 4,600 | 3,412 | 695,000 | 4,594 |
11 | 5-Star luxury | 45,000 | 5,751 | 23,000,000 | 1,449 | 95,200 | 1,142 | 12,500 | 1,732 | 11,600 | 2,457 | 5,872,000 | 4,369 | 6,000 | 4,451 | 972,000 | 6,424 |
12 | Resort style | 46,500 | 5,943 | 27,900,000 | 1,758 | 119,200 | 1,430 | 7,800 | 1,080 | 9,800 | 2,075 | 3,762,000 | 2,799 | 6,800 | 5,044 | 750,000 | 4,957 |
13 | Industrial | ||||||||||||||||
14 | Advanced manufacturing facility | 29,600 | 3,783 | 23,600,000 | 1,487 | 155,100 | 1,861 | 4,200 | 582 | 14,800 | 3,134 | 4,767,000 | 3,547 | 4,700 | 3,486 | 607,000 | 4,012 |
15 | Large warehouse distribution centre | 24,800 | 3,170 | 12,200,000 | 769 | 30,450 | 365 | 3,500 | 485 | 3,600 | 762 | 1,283,000 | 955 | 2,300 | 1,706 | 370,000 | 2,446 |
16 | Retail | ||||||||||||||||
17 | Large shopping centre including mall | 37,000 | 4,729 | 11,400,000 | 718 | 40,200 | 482 | 6,000 | 831 | 5,500 | 1,165 | 3,115,000 | 2,318 | 4,000 | 2,967 | 512,000 | 3,384 |
18 | Neighbourhood incl supermarket | 29,000 | 3,706 | 8,850,000 | 558 | 36,100 | 433 | 4,050 | 561 | 4,450 | 942 | 1,742,000 | 1,296 | 3,350 | 2,485 | 420,000 | 2,776 |
19 | Prestige car showroom | 35,400 | 4,524 | 17,100,000 | 1,077 | 43,600 | 523 | 4,500 | 623 | 4,650 | 985 | 3,429,000 | 2,552 | 4,300 | 3,190 | 630,000 | 4,164 |
20 | Residential | ||||||||||||||||
21 | Apartments high-rise | 33,800 | 4,320 | 14,800,000 | 933 | 56,500 | 678 | 4,650 | 644 | 3,450 | 731 | 2,568,000 | 1,911 | 3,550 | 2,633 | 650,000 | 4,296 |
22 | Townhouses medium standard | 37,000 | 4,729 | 8,700,000 | 548 | 39,700 | 476 | 4,450 | 616 | 1,850 | 392 | 2,496,000 | 1,857 | 3,750 | 2,782 | 525,000 | 3,470 |
1 | Labour, material and plant costs | Hong Kong | Hong Kong | Jakarta | Jakarta | Mumbai | Mumbai | Shanghai | Shanghai | Kuala Lumpur | Kuala Lumpur | Seoul | Seoul | Singapore | Singapore | Tokyo | Tokyo |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2 | CNY | USD | IDR | USD | INR | USD | CNY | USD | MYR | USD | KRW | USD | SGD | USD | JPY | USD | |
3 | Labour costs (rates per hour) | ||||||||||||||||
4 | Group 1 Tradesman e.g. plumber/electrician | 200 | 26 | 25,000 | 2 | 149 | 2 | 49 | 7 | 30 | 6 | 37,600 | 28 | 41 | 30 | 4,320 | 29 |
5 | Group 2 Tradesman e.g. carpenter bricklayer | 280 | 36 | 25,000 | 2 | 154 | 2 | 49 | 7 | 30 | 6 | 37,600 | 28 | 30 | 22 | 4,140 | 27 |
6 | Group 3 Tradesman e.g. carpet layer, tiler, plasterer | 216 | 28 | 25,000 | 2 | 140 | 2 | 48 | 7 | 28 | 6 | 37,600 | 28 | 37 | 27 | 4,470 | 30 |
7 | Group 4 Green collar installation operative e.g. insulation/solar/heat pump | 195 | 25 | 28,000 | 2 | 187 | 2 | 52 | 7 | 30 | 6 | 40,200 | 30 | 36 | 27 | 3,810 | 25 |
8 | General labourer | 175 | 22 | 22,000 | 1 | 135 | 2 | 33 | 5 | 23 | 5 | 23,600 | 18 | 33 | 24 | 3,585 | 24 |
9 | Site foreman | 240 | 31 | 32,000 | 2 | 226 | 3 | 65 | 9 | 45 | 10 | 48,200 | 36 | 50 | 37 | 6,900 | 46 |
10 | Material costs | ||||||||||||||||
11 | 13 mm plasterboard (m²) | 113 | 14 | 95,000 | 6 | 253 | 3 | 25 | 3 | 38 | 8 | 4,260 | 3 | 11 | 8 | 332 | 2 |
12 | Concrete 30 MPa (m³) (1500m³ job) | 885 | 113 | 975,000 | 61 | 6,383 | 77 | 650 | 90 | 280 | 59 | 110,420 | 82 | 116 | 86 | 21,800 | 144 |
13 | Concrete block (400x200) per 1000 (>10,000 block job) | 13,000 | 1,662 | 5,700,000 | 359 | 37,735 | 453 | 6,200 | 859 | 3,800 | 805 | 700,000 | 521 | 800 | 593 | 140,000 | 925 |
14 | Copper cable (metre) (3C + E, 2.5mm PVC) (100,000m+ job) | 27 | 3 | 32,000 | 2 | 264 | 3 | 13 | 2 | 6 | 1 | 2,735 | 2 | 4 | 3 | 335 | 2 |
15 | Copper pipe 15 mm (metre) (1000+ metre job) | 57 | 7 | 128,000 | 8 | 556 | 7 | 52 | 7 | 48 | 10 | 8,092 | 6 | 12 | 9 | 1,360 | 9 |
16 | Emulsion paint (litre) | 82 | 10 | 105,000 | 7 | 263 | 3 | 38 | 5 | 25 | 5 | 7,000 | 5 | 14 | 10 | 622 | 4 |
17 | Glass pane 10mm tempered (m²) | 1,000 | 128 | 850,000 | 54 | 2,460 | 30 | 155 | 21 | 330 | 70 | 32,200 | 24 | 145 | 108 | 15,600 | 103 |
18 | Reinforcement bar 16mm (tonne) (120 tonne job) | 8,000 | 1,022 | 13,000,000 | 819 | 62,300 | 748 | 4,490 | 622 | 3,060 | 648 | 1,026,000 | 763 | 825 | 612 | 114,000 | 753 |
19 | Softwood timber for framing 100mm X 50mm (m) | 113 | 14 | 87,000 | 5 | 330 | 4 | 33 | 5 | 26 | 6 | 7,500 | 6 | 17 | 12 | 1,393 | 9 |
20 | Standard brick per 1000 | 4,500 | 575 | 850,000 | 54 | 8,755 | 105 | 600 | 83 | 400 | 85 | 79,000 | 59 | 400 | 297 | 110,000 | 727 |
21 | Structural steel beams (tonne) (100 tonne+ job) | 20,400 | 2,607 | 25,000,000 | 1,575 | 73,000 | 876 | 4,600 | 637 | 7,000 | 1,482 | 1,610,000 | 1,198 | 2,950 | 2,188 | 550,000 | 3,635 |
22 | Plant costs (rates per day) | ||||||||||||||||
23 | Hire 50t mobile crane + operator (day) | 14,000 | 1,789 | 12,000,000 | 756 | 39,655 | 476 | 3,200 | 443 | 3,200 | 678 | 1,400,000 | 1,042 | 2,350 | 1,743 | 97,000 | 641 |
1 | International building costs per m² of internal area | Auckland | Auckland | Melbourne | Melbourne | Sydney | Sydney |
---|---|---|---|---|---|---|---|
2 | NZD | USD | AUD | USD | AUD | USD | |
3 | Commercial | ||||||
4 | CBD Offices – high-rise prestige | 5,950 | 3,560 | 5,700 | 3,718 | 7,320 | 4,775 |
5 | CBD Offices – up to 20 floors medium (A-Grade) | 4,800 | 2,872 | 4,100 | 2,675 | 5,500 | 3,588 |
6 | Education | ||||||
7 | Primary and secondary | 5,750 | 3,440 | 3,600 | 2,348 | 4,500 | 2,935 |
8 | General Hospital (e.g. city teaching hospital) | 8,100 | 4,846 | 7,100 | 4,632 | 7,380 | 4,814 |
9 | Hotels | ||||||
10 | 3-Star travellers | 4,000 | 2,393 | 4,000 | 2,609 | 4,830 | 3,151 |
11 | 5-Star luxury | 6,600 | 3,949 | 6,900 | 4,501 | 7,107 | 4,636 |
12 | Resort style | 5,750 | 3,440 | 4,600 | 3,001 | 5,460 | 3,562 |
13 | Industrial | ||||||
14 | Advanced manufacturing facility | 7,300 | 4,367 | 6,500 | 4,240 | 6,350 | 4,142 |
15 | Large warehouse distribution centre | 2,100 | 1,256 | 1,400 | 913 | 1,850 | 1,207 |
16 | Retail | ||||||
17 | Large shopping centre including mall | 4,900 | 2,932 | 3,850 | 2,511 | 4,200 | 2,740 |
18 | Neighbourhood incl supermarket | 2,850 | 1,705 | 3,300 | 2,153 | 3,800 | 2,479 |
19 | Prestige car showroom | 3,800 | 2,273 | 4,000 | 2,609 | 3,750 | 2,446 |
20 | Residential | ||||||
21 | Apartments high-rise | 4,550 | 2,722 | 3,950 | 2,577 | 4,100 | 2,675 |
22 | Townhouses medium standard | 3,650 | 2,184 | 2,850 | 1,859 | 2,950 | 1,924 |
1 | Labour, material and plant costs | Auckland | Auckland | Melbourne | Melbourne | Sydney | Sydney |
---|---|---|---|---|---|---|---|
2 | NZD | USD | AUD | USD | AUD | USD | |
3 | Labour costs (rates per hour) | ||||||
4 | Group 1 Tradesman e.g. plumber/electrician | 85 | 51 | 108 | 70 | 115 | 75 |
5 | Group 2 Tradesman e.g. carpenter bricklayer | 80 | 48 | 105 | 68 | 105 | 68 |
6 | Group 3 Tradesman e.g. carpet layer, tiler, plasterer | 75 | 45 | 105 | 68 | 95 | 62 |
7 | Group 4 Green collar installation operative e.g. insulation/solar/heat pump | 85 | 51 | 115 | 75 | 110 | 72 |
8 | General labourer | 60 | 36 | 87 | 57 | 85 | 55 |
9 | Site foreman | 80 | 48 | 150 | 98 | 141 | 92 |
10 | Material costs | ||||||
11 | 13 mm plasterboard (m²) | 15 | 9 | 10 | 7 | 13 | 8 |
12 | Concrete 30 MPa (m³) (1500m³ job) | 330 | 197 | 230 | 150 | 273 | 178 |
13 | Concrete block (400x200) per 1000 (>10,000 block job) | 3,810 | 2,279 | 4,500 | 2,935 | 4,150 | 2,707 |
14 | Copper cable (metre) (3C + E, 2.5mm PVC) (100,000m+ job) | 6 | 4 | 4 | 3 | 6 | 4 |
15 | Copper pipe 15 mm (metre) (1000+ metre job) | 20 | 12 | 11 | 7 | 11 | 7 |
16 | Emulsion paint (litre) | 35 | 21 | 15 | 10 | 17 | 11 |
17 | Glass pane 10mm tempered (m²) | 195 | 117 | 320 | 209 | 335 | 219 |
18 | Reinforcement bar 16mm (tonne) (120 tonne job) | 2,900 | 1,735 | 2,100 | 1,370 | 2,400 | 1,566 |
19 | Softwood timber for framing 100mm X 50mm (m) | 5 | 3 | 8 | 5 | 9 | 6 |
20 | Standard brick per 1000 | 1,750 | 1,047 | 1,500 | 978 | 1,560 | 1,018 |
21 | Structural steel beams (tonne) (100 tonne+ job) | 2,925 | 1,750 | 3,500 | 2,283 | 3,500 | 2,283 |
22 | Plant costs (rates per day) | ||||||
23 | Hire 50t mobile crane + operator (day) | 3,500 | 2,094 | 3,500 | 2,283 | 3,200 | 2,087 |
1 | International building costs per m² of internal area | Amsterdam | Amsterdam | Dublin | Dublin | Munich | Munich | Paris | Paris |
---|---|---|---|---|---|---|---|---|---|
2 | EUR | USD | EUR | USD | EUR | USD | EUR | USD | |
3 | Commercial | ||||||||
4 | CBD Offices – high-rise prestige | 4,570 | 4,929 | 4,700 | 5,069 | 5,200 | 5,608 | 4,520 | 4,875 |
5 | CBD Offices – up to 20 floors medium (A-Grade) | 3,250 | 3,505 | 3,700 | 3,990 | 3,950 | 4,260 | 3,207 | 3,459 |
6 | Education | ||||||||
7 | Primary and secondary | 2,200 | 2,373 | 2,500 | 2,696 | 3,100 | 3,343 | 2,074 | 2,236 |
8 | General Hospital (e.g. city teaching hospital) | 4,590 | 4,950 | 5,350 | 5,770 | 4,800 | 5,177 | 4,433 | 4,781 |
9 | Hotels | ||||||||
10 | 3-Star travellers | 2,720 | 2,934 | 3,450 | 3,721 | 3,000 | 3,236 | 2,554 | 2,755 |
11 | 5-Star luxury | 4,810 | 5,188 | 4,550 | 4,907 | 5,500 | 5,932 | 4,628 | 4,991 |
12 | Resort style | 3,580 | 3,861 | 3,900 | 4,206 | 3,850 | 4,152 | 3,408 | 3,676 |
13 | Industrial | ||||||||
14 | Advanced manufacturing facility | 3,560 | 3,840 | 2,700 | 2,912 | 3,400 | 3,667 | 2,864 | 3,089 |
15 | Large warehouse distribution centre | 1,330 | 1,434 | 1,500 | 1,618 | 1,575 | 1,699 | 1,233 | 1,330 |
16 | Retail | ||||||||
17 | Large shopping centre including mall | 3,200 | 3,451 | 3,700 | 3,990 | 3,400 | 3,667 | 3,012 | 3,249 |
18 | Neighbourhood incl supermarket | 2,880 | 3,106 | 3,500 | 3,775 | 3,300 | 3,559 | 2,798 | 3,018 |
19 | Prestige car showroom | 3,360 | 3,624 | 3,900 | 4,206 | 3,650 | 3,937 | 3,271 | 3,528 |
20 | Residential | ||||||||
21 | Apartments high-rise | 2,770 | 2,987 | 3,400 | 3,667 | 2,900 | 3,128 | 2,348 | 2,533 |
22 | Townhouses medium standard | 1,770 | 1,909 | 2,200 | 2,373 | 2,400 | 2,588 | 1,662 | 1,792 |
1 | Labour, material and plant costs | Amsterdam | Amsterdam | Dublin | Dublin | Munich | Munich | Paris | Paris |
---|---|---|---|---|---|---|---|---|---|
2 | EUR | USD | EUR | USD | EUR | USD | EUR | USD | |
3 | Labour costs (rates per hour) | ||||||||
4 | Group 1 Tradesman e.g. plumber/electrician | 63 | 68 | 50 | 54 | 94 | 101 | 70 | 75 |
5 | Group 2 Tradesman e.g. carpenter bricklayer | 53 | 57 | 46 | 50 | 78 | 84 | 58 | 63 |
6 | Group 3 Tradesman e.g. carpet layer, tiler, plasterer | 53 | 57 | 45 | 49 | 78 | 84 | 51 | 55 |
7 | Group 4 Green collar installation operative e.g. insulation/solar/heat pump | 63 | 68 | 70 | 75 | 94 | 101 | 76 | 82 |
8 | General labourer | 42 | 45 | 40 | 43 | 60 | 65 | 41 | 44 |
9 | Site foreman | 74 | 80 | 60 | 65 | 84 | 91 | 58 | 63 |
10 | Material costs | ||||||||
11 | 13 mm plasterboard (m²) | 9 | 9 | 11 | 12 | 8 | 9 | 6 | 7 |
12 | Concrete 30 MPa (m³) (1500m³ job) | 164 | 177 | 125 | 135 | 240 | 259 | 163 | 176 |
13 | Concrete block (400x200) per 1000 (>10,000 block job) | 1,800 | 1,941 | 800 | 863 | 1,420 | 1,531 | 1,538 | 1,659 |
14 | Copper cable (metre) (3C + E, 2.5mm PVC) (100,000m+ job) | 3 | 3 | 8 | 9 | 4 | 4 | 4 | 4 |
15 | Copper pipe 15 mm (metre) (1000+ metre job) | 8 | 8 | 14 | 15 | 10 | 11 | 9 | 10 |
16 | Emulsion paint (litre) | 8 | 8 | 14 | 15 | 10 | 11 | 8 | 9 |
17 | Glass pane 10mm tempered (m²) | 205 | 221 | 175 | 189 | 180 | 194 | 219 | 236 |
18 | Reinforcement bar 16mm (tonne) (120 tonne job) | 1,206 | 1,301 | 1,000 | 1,079 | 1,650 | 1,780 | 1,128 | 1,217 |
19 | Softwood timber for framing 100mm X 50mm (m) | 5 | 6 | 10 | 11 | 6 | 6 | 4 | 4 |
20 | Standard brick per 1000 | 743 | 801 | 800 | 863 | 1,020 | 1,100 | 815 | 879 |
21 | Structural steel beams (tonne) (100 tonne+ job) | 2,176 | 2,347 | 2,450 | 2,642 | 3,500 | 3,775 | 2,752 | 2,968 |
22 | Plant costs (rates per day) | ||||||||
23 | Hire 50t mobile crane + operator (day) | 1,420 | 1,531 | 1,250 | 1,348 | 1,500 | 1,618 | 1,250 | 1,348 |
1 | International building costs per m² of internal area | Dubai | Dubai | Riyadh | Riyadh |
---|---|---|---|---|---|
2 | AED | USD | SAR | USD | |
3 | Commercial | ||||
4 | CBD Offices – high-rise prestige | 7,100 | 1,933 | 8,500 | 2,266 |
5 | CBD Offices – up to 20 floors medium (A-Grade) | 5,700 | 1,552 | 7,000 | 1,866 |
6 | Education | ||||
7 | Primary and secondary | 6,400 | 1,743 | 9,000 | 2,399 |
8 | General Hospital (e.g. city teaching hospital) | 12,000 | 3,268 | 11,000 | 2,932 |
9 | Hotels | ||||
10 | 3-Star travellers | 6,000 | 1,634 | 8,500 | 2,266 |
11 | 5-Star luxury | 9,800 | 2,668 | 18,000 | 4,798 |
12 | Resort style | 12,500 | 3,404 | 20,000 | 5,331 |
13 | Industrial | ||||
14 | Advanced manufacturing facility | 6,500 | 1,770 | 10,500 | 2,799 |
15 | Large warehouse distribution centre | 3,800 | 1,035 | 6,000 | 1,599 |
16 | Retail | ||||
17 | Large shopping centre including mall | 5,900 | 1,607 | 8,000 | 2,132 |
18 | Neighbourhood incl supermarket | 5,900 | 1,607 | 6,500 | 1,733 |
19 | Prestige car showroom | 9,400 | 2,560 | 10,000 | 2,665 |
20 | Residential | ||||
21 | Apartments high-rise | 4,900 | 1,334 | 8,000 | 2,132 |
22 | Townhouses medium standard | 4,700 | 1,280 | 6,500 | 1,733 |
1 | Labour, material and plant costs | Dubai | Dubai | Riyadh | Riyadh |
---|---|---|---|---|---|
2 | AED | USD | SAR | USD | |
3 | Labour costs (rates per hour) | ||||
4 | Group 1 Tradesman e.g. plumber/electrician | 24 | 7 | 45 | 12 |
5 | Group 2 Tradesman e.g. carpenter bricklayer | 22 | 6 | 38 | 10 |
6 | Group 3 Tradesman e.g. carpet layer, tiler, plasterer | 22 | 6 | 38 | 10 |
7 | Group 4 Green collar installation operative e.g. insulation/solar/heat pump | 37 | 10 | 60 | 16 |
8 | General labourer | 19 | 5 | 28 | 7 |
9 | Site foreman | 57 | 16 | 50 | 13 |
10 | Material costs | ||||
11 | 13 mm plasterboard (m²) | 15 | 4 | 26 | 7 |
12 | Concrete 30 MPa (m³) (1500m³ job) | 285 | 78 | 335 | 89 |
13 | Concrete block (400x200) per 1000 (>10,000 block job) | 3,000 | 817 | 6,856 | 1,827 |
14 | Copper cable (metre) (3C + E, 2.5mm PVC) (100,000m+ job) | 14 | 4 | 18 | 5 |
15 | Copper pipe 15 mm (metre) (1000+ metre job) | 36 | 10 | 40 | 11 |
16 | Emulsion paint (litre) | 12 | 3 | 45 | 12 |
17 | Glass pane 10mm tempered (m²) | 450 | 123 | 830 | 221 |
18 | Reinforcement bar 16mm (tonne) (120 tonne job) | 2,500 | 681 | 3,800 | 1,013 |
19 | Softwood timber for framing 100mm X 50mm (m) | 16 | 4 | 24 | 6 |
20 | Standard brick per 1000 | 2,400 | 654 | 2,800 | 746 |
21 | Structural steel beams (tonne) (100 tonne+ job) | 8,750 | 2,383 | 10,500 | 2,799 |
22 | Plant costs (rates per day) | ||||
23 | Hire 50t mobile crane + operator (day) | 1,600 | 436 | 4,000 | 1,066 |
1 | International building costs per m² of internal area | Chicago | Chicago | Houston | Houston | Los Angeles | Los Angeles | Mexico City | Mexico City | Monterrey | Monterrey | New York City | New York City | San Francisco | San Francisco | Toronto | Toronto | Vancouver | Vancouver |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2 | USD (ft²) | USD (m²) | USD (ft²) | USD (m²) | USD (ft²) | USD (m²) | MXN | USD | MXN | USD | USD (ft²) | USD (m²) | USD (ft²) | USD (m²) | CAD | USD | CAD | USD | |
3 | Commercial | ||||||||||||||||||
4 | CBD Offices – high-rise prestige | 822 | 8,840 | 525 | 5,654 | 743 | 8,000 | 42,910 | 2,592 | 42,000 | 2,537 | 991 | 10,660 | 862 | 9,277 | 5,441 | 4,019 | 5,624 | 4,154 |
5 | CBD Offices – up to 20 floors medium (A-Grade) | 638 | 6,864 | 388 | 4,180 | 604 | 6,500 | 31,398 | 1,896 | 32,400 | 1,957 | 758 | 8,152 | 712 | 7,660 | 4,098 | 3,027 | 4,343 | 3,208 |
6 | Education | ||||||||||||||||||
7 | Primary and secondary | 619 | 6,656 | 346 | 3,720 | 623 | 6,700 | 23,367 | 1,411 | 24,629 | 1,488 | 758 | 8,152 | 632 | 6,800 | 3,266 | 2,412 | 4,003 | 2,957 |
8 | General Hospital (e.g. city teaching hospital) | 1,073 | 11,544 | 891 | 9,585 | 1,092 | 11,750 | 47,196 | 2,851 | 47,929 | 2,895 | 1,282 | 13,795 | 1,162 | 12,500 | 10,768 | 7,953 | 10,548 | 7,790 |
9 | Hotels | ||||||||||||||||||
10 | 3-Star travellers | 344 | 3,701 | 271 | 2,920 | 419 | 4,504 | 28,448 | 1,718 | 29,984 | 1,811 | 439 | 4,725 | 404 | 4,347 | 3,868 | 2,857 | 4,033 | 2,979 |
11 | 5-Star luxury | 684 | 7,361 | 521 | 5,610 | 743 | 8,000 | 53,632 | 3,239 | 56,528 | 3,414 | 781 | 8,400 | 770 | 8,285 | 6,052 | 4,470 | 6,345 | 4,686 |
12 | Resort style | 431 | 4,637 | 340 | 3,655 | 457 | 4,916 | 65,459 | 3,954 | 68,993 | 4,167 | 484 | 5,204 | 482 | 5,187 | 4,960 | 3,664 | 5,194 | 3,836 |
13 | Industrial | ||||||||||||||||||
14 | Advanced manufacturing facility | 714 | 7,678 | 695 | 7,480 | 843 | 9,070 | 30,531 | 1,844 | 31,754 | 1,918 | 864 | 9,293 | 861 | 9,261 | 8,757 | 6,468 | 8,346 | 6,164 |
15 | Large warehouse distribution centre | 197 | 2,124 | 125 | 1,340 | 189 | 2,039 | 18,740 | 1,132 | 19,078 | 1,152 | 222 | 2,388 | 214 | 2,304 | 1,763 | 1,302 | 1,891 | 1,397 |
16 | Retail | ||||||||||||||||||
17 | Large shopping centre including mall | 382 | 4,108 | 336 | 3,620 | 425 | 4,568 | 27,833 | 1,681 | 27,833 | 1,681 | 482 | 5,186 | 493 | 5,300 | 4,028 | 2,975 | 3,813 | 2,816 |
18 | Neighbourhood incl supermarket | 217 | 2,340 | 209 | 2,250 | 215 | 2,317 | 22,364 | 1,351 | 22,364 | 1,351 | 261 | 2,804 | 260 | 2,793 | 2,396 | 1,769 | 2,452 | 1,811 |
19 | Prestige car showroom | 387 | 4,161 | 372 | 4,000 | 413 | 4,441 | 35,275 | 2,131 | 35,275 | 2,131 | 468 | 5,040 | 464 | 4,988 | 4,754 | 3,511 | 5,014 | 3,703 |
20 | Residential | ||||||||||||||||||
21 | Apartments high-rise | 387 | 4,160 | 273 | 2,935 | 436 | 4,688 | 23,073 | 1,394 | 24,000 | 1,450 | 625 | 6,720 | 613 | 6,594 | 4,173 | 3,082 | 4,053 | 2,993 |
22 | Townhouses medium standard | 194 | 2,085 | 183 | 1,968 | 330 | 3,552 | 16,780 | 1,014 | 17,320 | 1,046 | 342 | 3,675 | 339 | 3,644 | 2,790 | 2,061 | 2,852 | 2,107 |
1 | Material costs | Chicago | Chicago | Houston | Houston | Los Angeles | Los Angeles | Mexico City | Mexico City | Monterrey | Monterrey | New York City | New York City | San Francisco | San Francisco | Toronto | Toronto | Vancouver | Vancouver |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2 | USD (ft²) | USD (m²) | USD (ft²) | USD (m²) | USD (ft²) | USD (m²) | MXN (m²) | USD (m²) | MXN (m²) | USD (m²) | USD (ft²) | USD (m²) | USD (ft²) | USD (m²) | CAD (m²) | USD (m²) | CAD (m²) | USD (m²) | |
3 | Material costs | ||||||||||||||||||
4 | 13 mm plasterboard (m²) | 1.0 | 6.0 | 1.0 | 6.0 | 1.0 | 6.0 | 171.0 | 10.0 | 180.0 | 11.0 | 1.0 | 6.0 | 1.0 | 6.0 | 8.0 | 6.0 | 7.0 | 5.0 |
5 | Concrete 30 MPa (m³) (1500m³ job) | 20.0 | 210.0 | 19.0 | 200.0 | 20.0 | 210.0 | 3,517.0 | 212.0 | 3,838.0 | 232.0 | 20.0 | 211.0 | 20.0 | 210.0 | 284.0 | 210.0 | 298.0 | 220.0 |
6 | Concrete block (400x200) per 1000 (>10,000 block job) | 195.0 | 2,100.0 | 189.0 | 2,033.0 | 195.0 | 2,100.0 | 13,290.0 | 803.0 | 13,322.0 | 805.0 | 223.0 | 2,400.0 | 220.0 | 2,365.0 | 2,957.0 | 2,184.0 | 2,776.0 | 2,050.0 |
7 | Copper cable (metre) (3C + E, 2.5mm PVC) (100,000m+ job) | 1.0 | 7.0 | 1.0 | 7.0 | 1.0 | 7.0 | 43.0 | 3.0 | 125.0 | 8.0 | 1.0 | 8.0 | 1.0 | 8.0 | 9.0 | 7.0 | 9.0 | 7.0 |
8 | Copper pipe 15 mm (metre) (1000+ metre job) | 1.0 | 10.0 | 1.0 | 9.0 | 1.0 | 10.0 | 216.0 | 13.0 | 227.0 | 14.0 | 1.0 | 12.0 | 1.0 | 12.0 | 12.0 | 9.0 | 14.0 | 10.0 |
9 | Emulsion paint (litre) | 1.0 | 9.0 | 1.0 | 9.0 | 1.0 | 10.0 | 180.0 | 11.0 | 190.0 | 11.0 | 1.0 | 13.0 | 1.0 | 11.0 | 16.0 | 12.0 | 16.0 | 12.0 |
10 | Glass pane 10mm tempered (m²) | 33.0 | 358.0 | 29.0 | 310.0 | 32.0 | 340.0 | 3,817.0 | 231.0 | 4,017.0 | 243.0 | 44.0 | 477.0 | 38.0 | 413.0 | 556.0 | 411.0 | 615.0 | 454.0 |
11 | Reinforcement bar 16mm (tonne) (120 tonne job) | 177.0 | 1,900.0 | 176.0 | 1,890.0 | 177.0 | 1,900.0 | 27,113.0 | 1,638.0 | 28,539.0 | 1,724.0 | 214.0 | 2,300.0 | 217.0 | 2,332.0 | 2,880.0 | 2,127.0 | 3,076.0 | 2,272.0 |
12 | Softwood timber for framing 100mm X 50mm (m) | 0.0 | 2.0 | 0.0 | 2.0 | 0.0 | 3.0 | 101.0 | 6.0 | 107.0 | 6.0 | 0.0 | 3.0 | 0.0 | 3.0 | 3.0 | 2.0 | 3.0 | 2.0 |
13 | Standard brick per 1000 | 90.0 | 967.0 | 96.0 | 1,029.0 | 88.0 | 950.0 | 3,610.0 | 218.0 | 3,800.0 | 230.0 | 97.0 | 1,040.0 | 97.0 | 1,040.0 | 1,479.0 | 1,092.0 | 1,453.0 | 1,073.0 |
14 | Structural steel beams (tonne) (100 tonne+ job) | 418.0 | 4,500.0 | 390.0 | 4,200.0 | 418.0 | 4,500.0 | 87,400.0 | 5,279.0 | 92,000.0 | 5,557.0 | 465.0 | 5,000.0 | 465.0 | 5,000.0 | 5,416.0 | 4,000.0 | 6,905.0 | 5,100.0 |
1 | Labour and plant costs | Chicago | Houston | Los Angeles | Mexico City | Mexico City | Monterrey | Monterrey | New York City | San Francisco | Toronto | Toronto | Vancouver | Vancouver |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2 | USD | USD | USD | MXN | USD | MXN | USD | USD | USD | CAD | USD | CAD | USD | |
3 | Labour costs (rates per hour) | |||||||||||||
4 | Group 1 Tradesman e.g. plumber/electrician | 125.0 | 79.0 | 126.0 | 222.0 | 13.0 | 262.0 | 16.0 | 178.0 | 161.0 | 97.0 | 72.0 | 85.0 | 63.0 |
5 | Group 2 Tradesman e.g. carpenter bricklayer | 95.0 | 69.0 | 96.0 | 222.0 | 13.0 | 267.0 | 16.0 | 150.0 | 147.0 | 86.0 | 63.0 | 78.0 | 58.0 |
6 | Group 3 Tradesman e.g. carpet layer, tiler, plasterer | 95.0 | 56.0 | 96.0 | 220.0 | 13.0 | 267.0 | 16.0 | 150.0 | 145.0 | 81.0 | 60.0 | 78.0 | 58.0 |
7 | Group 4 Green collar installation operative e.g. insulation/solar/heat pump | 102.0 | 75.0 | 126.0 | 360.0 | 22.0 | 381.0 | 23.0 | 175.0 | 157.0 | 90.0 | 66.0 | 90.0 | 67.0 |
8 | General labourer | 80.0 | 49.0 | 82.0 | 201.0 | 12.0 | 220.0 | 13.0 | 105.0 | 102.0 | 77.0 | 57.0 | 65.0 | 48.0 |
9 | Site foreman | 142.0 | 112.0 | 133.0 | 252.0 | 15.0 | 306.0 | 18.0 | 175.0 | 161.0 | 101.0 | 75.0 | 105.0 | 78.0 |
10 | Plant costs (rates per day) | |||||||||||||
11 | Hire 50t mobile crane + operator (day) | 4,500.0 | 3,115.0 | 4,500.0 | 37,800.0 | 2,283.0 | 52,700.0 | 3,183.0 | 5,245.0 | 4,900.0 | 2,803.0 | 2,070.0 | 3,435.0 | 2,537.0 |
1 | International building costs per m² of internal area | Bogota | Bogota | Santiago | Santiago | São Paulo | São Paulo |
---|---|---|---|---|---|---|---|
2 | COP | USD | CLP | USD | BRL | USD | |
3 | Commercial | ||||||
4 | CBD Offices – high-rise prestige | 8,074,905 | 2,092 | 2,082,953 | 2,119 | 13,056 | 2,604 |
5 | CBD Offices – up to 20 floors medium (A-Grade) | 5,343,687 | 1,385 | 1,395,808 | 1,420 | 9,344 | 1,864 |
6 | Education | ||||||
7 | Primary and secondary | 2,986,264 | 774 | 1,035,918 | 1,054 | 4,328 | 863 |
8 | General Hospital (e.g. city teaching hospital) | 7,983,270 | 2,069 | 2,124,509 | 2,161 | 3,666 | 731 |
9 | Hotels | ||||||
10 | 3-Star travellers | 6,021,120 | 1,560 | 1,394,505 | 1,418 | 9,056 | 1,806 |
11 | 5-Star luxury | 8,791,642 | 2,278 | 2,447,798 | 2,490 | 15,856 | 3,163 |
12 | Resort style | 9,827,328 | 2,547 | 2,921,820 | 2,972 | 18,615 | 3,713 |
13 | Industrial | ||||||
14 | Advanced manufacturing facility | 4,242,030 | 1,099 | 1,368,893 | 1,392 | 6,236 | 1,244 |
15 | Large warehouse distribution centre | 2,652,095 | 687 | 942,951 | 959 | 2,389 | 476 |
16 | Retail | ||||||
17 | Large shopping centre including mall | 5,758,214 | 1,492 | 1,460,910 | 1,486 | 6,644 | 1,325 |
18 | Neighbourhood incl supermarket | 4,923,380 | 1,276 | 1,726,530 | 1,756 | 3,885 | 775 |
19 | Prestige car showroom | 5,672,590 | 1,470 | 2,257,770 | 2,297 | 7,951 | 1,586 |
20 | Residential | ||||||
21 | Apartments high-rise | 4,714,879 | 1,222 | 1,011,845 | 1,029 | 4,597 | 917 |
22 | Townhouses medium standard | 4,189,380 | 1,086 | 1,261,695 | 1,283 | 2,563 | 511 |
1 | Labour, material and plant costs | Bogota | Bogota | Santiago | Santiago | São Paulo | São Paulo |
---|---|---|---|---|---|---|---|
2 | COP | USD | CLP | USD | BRL | USD | |
3 | Labour costs (rates per hour) | ||||||
4 | Group 1 Tradesman e.g. plumber/electrician | 21,267 | 6 | 7,303 | 7 | 29 | 6 |
5 | Group 2 Tradesman e.g. carpenter bricklayer | 24,640 | 6 | 8,713 | 9 | 17 | 3 |
6 | Group 3 Tradesman e.g. carpet layer, tiler, plasterer | 16,323 | 4 | 9,697 | 10 | 29 | 6 |
7 | Group 4 Green collar installation operative e.g. insulation/solar/heat pump | 28,235 | 7 | 10,821 | 11 | 37 | 7 |
8 | General labourer | 13,578 | 4 | 5,125 | 5 | 15 | 3 |
9 | Site foreman | 26,382 | 7 | 18,235 | 19 | 68 | 14 |
10 | Material costs | ||||||
11 | 13 mm plasterboard (m²) | 12,596 | 3 | 4,459 | 5 | 26 | 5 |
12 | Concrete 30 MPa (m³) (1500m³ job) | 485,000 | 126 | 87,418 | 89 | 584 | 117 |
13 | Concrete block (400x200) per 1000 (>10,000 block job) | 2,900,000 | 751 | 1,390,000 | 1,414 | 4,738 | 945 |
14 | Copper cable (metre) (3C + E, 2.5mm PVC) (100,000m+ job) | 14,000 | 4 | 945 | 1 | 2 | 0 |
15 | Copper pipe 15 mm (metre) (1000+ metre job) | 35,600 | 9 | 3,885 | 4 | 42 | 8 |
16 | Emulsion paint (litre) | 7,714 | 2 | 14,852 | 15 | 55 | 11 |
17 | Glass pane 10mm tempered (m²) | 300,800 | 78 | 65,450 | 67 | 520 | 104 |
18 | Reinforcement bar 16mm (tonne) (120 tonne job) | 4,480,000 | 1,161 | 1,145,964 | 1,166 | 6,730 | 1,342 |
19 | Softwood timber for framing 100mm X 50mm (m) | 16,531 | 4 | 3,343 | 3 | 9 | 2 |
20 | Standard brick per 1000 | 1,200,000 | 311 | 166,183 | 169 | 880 | 176 |
21 | Structural steel beams (tonne) (100 tonne+ job) | 12,650,000 | 3,278 | 1,919,206 | 1,952 | 12,101 | 2,414 |
22 | Plant costs (rates per day) | ||||||
23 | Hire 50t mobile crane + operator (day) | 3,500,000 | 907 | 991,516 | 1,009 | 5,655 | 1,128 |
1 | International building costs per m² of internal area | Birmingham | Birmingham | Glasgow | Glasgow | Leeds | Leeds | London | London | Manchester | Manchester |
---|---|---|---|---|---|---|---|---|---|---|---|
2 | GBP | USD | GBP | USD | GBP | USD | GBP | USD | GBP | USD | |
3 | Commercial | ||||||||||
4 | CBD Offices – high-rise prestige | 3,200 | 4,038 | 2,975 | 3,754 | 3,100 | 3,912 | 4,783 | 6,036 | 3,255 | 4,107 |
5 | CBD Offices – up to 20 floors medium (A-Grade) | 2,985 | 3,767 | 2,725 | 3,438 | 2,800 | 3,533 | 4,233 | 5,342 | 2,940 | 3,710 |
6 | Education | ||||||||||
7 | Primary and secondary | 1,830 | 2,309 | 3,900 | 4,921 | 2,250 | 2,839 | 3,375 | 4,259 | 2,100 | 2,650 |
8 | General Hospital (e.g. city teaching hospital) | 3,814 | 4,813 | 4,340 | 5,476 | 3,750 | 4,732 | 4,850 | 6,120 | 4,148 | 5,233 |
9 | Hotels | ||||||||||
10 | 3-Star travellers | 2,195 | 2,770 | 2,525 | 3,186 | 2,300 | 2,902 | 3,633 | 4,585 | 2,258 | 2,849 |
11 | 5-Star luxury | 3,470 | 4,379 | 3,590 | 4,530 | 3,450 | 4,353 | 6,433 | 8,118 | 3,780 | 4,770 |
12 | Resort style | 3,012 | 3,801 | 3,145 | 3,968 | 3,100 | 3,912 | 4,200 | 5,300 | 3,675 | 4,637 |
13 | Industrial | ||||||||||
14 | Advanced manufacturing facility | 2,170 | 2,738 | 2,020 | 2,549 | 2,100 | 2,650 | 2,187 | 2,760 | 2,140 | 2,700 |
15 | Large warehouse distribution centre | 1,052 | 1,327 | 1,025 | 1,293 | 1,150 | 1,451 | 1,450 | 1,830 | 1,177 | 1,485 |
16 | Retail | ||||||||||
17 | Large shopping centre including mall | 2,279 | 2,876 | 2,235 | 2,820 | 2,350 | 2,965 | 2,800 | 3,533 | 2,468 | 3,114 |
18 | Neighbourhood incl supermarket | 1,591 | 2,008 | 1,545 | 1,950 | 1,550 | 1,956 | 1,950 | 2,461 | 1,733 | 2,186 |
19 | Prestige car showroom | 1,958 | 2,471 | 2,050 | 2,587 | 1,900 | 2,397 | 2,100 | 2,650 | 2,100 | 2,650 |
20 | Residential | ||||||||||
21 | Apartments high-rise | 2,683 | 3,385 | 2,500 | 3,155 | 3,150 | 3,975 | 4,133 | 5,216 | 3,296 | 4,159 |
22 | Townhouses medium standard | 1,911 | 2,411 | 1,965 | 2,479 | 2,150 | 2,713 | 3,280 | 4,139 | 2,163 | 2,729 |
1 | Labour, material and plant costs | Birmingham | Birmingham | Glasgow | Glasgow | Leeds | Leeds | London | London | Manchester | Manchester |
---|---|---|---|---|---|---|---|---|---|---|---|
2 | GBP | USD | GBP | USD | GBP | USD | GBP | USD | GBP | USD | |
3 | Labour costs (rates per hour) | ||||||||||
4 | Group 1 Tradesman e.g. plumber/electrician | 46 | 58 | 42 | 53 | 44 | 56 | 55 | 69 | 45 | 57 |
5 | Group 2 Tradesman e.g. carpenter bricklayer | 40 | 50 | 41 | 52 | 44 | 56 | 64 | 81 | 45 | 57 |
6 | Group 3 Tradesman e.g. carpet layer, tiler, plasterer | 38 | 48 | 36 | 45 | 44 | 56 | 42 | 53 | 43 | 54 |
7 | Group 4 Green collar installation operative e.g. insulation/solar/heat pump | 47 | 59 | 45 | 57 | 47 | 59 | 70 | 88 | 52 | 66 |
8 | General labourer | 28 | 35 | 27 | 34 | 30 | 38 | 28 | 35 | 30 | 37 |
9 | Site foreman | 42 | 53 | 48 | 61 | 52 | 66 | 68 | 86 | 52 | 66 |
10 | Material costs | ||||||||||
11 | 13 mm plasterboard (m²) | 8 | 9 | 8 | 10 | 11 | 13 | 14 | 18 | 7 | 9 |
12 | Concrete 30 MPa (m³) (1500m³ job) | 155 | 196 | 170 | 215 | 175 | 221 | 200 | 252 | 168 | 212 |
13 | Concrete block (400x200) per 1000 (>10,000 block job) | 930 | 1,174 | 1,175 | 1,483 | 960 | 1,211 | 980 | 1,237 | 960 | 1,211 |
14 | Copper cable (metre) (3C + E, 2.5mm PVC) (100,000m+ job) | 6 | 7 | 6 | 8 | 5 | 6 | 6 | 8 | 5 | 6 |
15 | Copper pipe 15 mm (metre) (1000+ metre job) | 9 | 11 | 8 | 10 | 9 | 11 | 9 | 11 | 8 | 11 |
16 | Emulsion paint (litre) | 6 | 8 | 6 | 8 | 8 | 9 | 6 | 8 | 8 | 10 |
17 | Glass pane 10mm tempered (m²) | 133 | 168 | 160 | 202 | 155 | 196 | 182 | 230 | 176 | 222 |
18 | Reinforcement bar 16mm (tonne) (120 tonne job) | 1,700 | 2,145 | 1,450 | 1,830 | 1,500 | 1,893 | 1,800 | 2,271 | 1,760 | 2,221 |
19 | Softwood timber for framing 100mm X 50mm (m) | 8 | 10 | 8 | 10 | 8 | 10 | 9 | 11 | 9 | 11 |
20 | Standard brick per 1000 | 630 | 795 | 650 | 820 | 675 | 852 | 800 | 1,009 | 840 | 1,060 |
21 | Structural steel beams (tonne) (100 tonne+ job) | 3,400 | 4,290 | 2,600 | 3,281 | 2,750 | 3,470 | 3,588 | 4,528 | 4,235 | 5,344 |
22 | Plant costs (rates per day) | ||||||||||
23 | Hire 50t mobile crane + operator (day) | 1,100 | 1,388 | 1,450 | 1,830 | 1,550 | 1,956 | 3,000 | 3,785 | 1,523 | 1,921 |