1 | Contract No. | Description | Type (Goods/Consulting Services/Works) | Company | Signed Date | Estimated Completion Date | Contract Amount | Approved Variations/Change Orders | Adjusted Contract Amount | Paid Amount to Date | Paid as Percentage of Total Contract | Implementation Progress (%) | Comments on Progress | Geotagging |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2 | MIPU/SHPG/V-A03.2 | Delivery, Installation, Testing, Calibration and Commissioning of ADS-B Out Avionics, Vanuatu | Goods | South Pacific Avionics Ltd | 22 February 2018 | 30 November 2019 | USD 596,830.00 | USD 0.00 | USD 596,830.00 | USD 0.00 | 0% | 70% | Supply of avionics underway. Installation schedule being confirmed with affected operators. | |
3 | MIPU/QCS/V-A06.2 Phase 1 | Design Validation, Supply & Installation, Supervision for the VSAT Point to Point Aeronautical Network | Lump Sum Consulting Services | Airways Corporation of New Zealand | 30 November 2017 | 30 June 2019 | NZD 219,661.00 | NZD 0.00 | NZD 219,661.00 | NZD 67,841.58 | 31% | 60% | Supervision of supply & install underway including FAT and commissioning | |
4 | MIPU/QCS/V-A06.2 Phase 2 | Hub Management for the VSAT Point to Point Aeronautical Network | Time Based Consulting Services | Airways Corporation of New Zealand | 30 November 2017 | 31 December 2019 | NZD 42,894.50 | NZD 0.00 | NZD 42,894.50 | NZD 0.00 | 0% | 0% | Not started. Phase 2 to commence on completion of Phase 1 | |
5 | MIPU/SSS/V-A06.3 Phase 3 | Installation of Satellite Communication Equipment (VSAT) | Works | High Gain Broadcast & Communications | 30 January 2019 | 30 June 2019 | AUD 277,473.00 | AUD 0.00 | AUD 277,473.00 | AUD 59,070.30 | 21% | 50% | Installation at TAH underway. Equipment ready for VLI and SON | |
6 | VAN/CF/V-A14.1 | Design and Procurement Services: Bauerfield International Airport | Lump Sum Consulting Services | Tonkin & Taylor International Ltd | 9 March 2015 | 31 December 2018 | NZD 450,050.00 AUD 75,600.00 | NZD 656,250.38 AUD 26,660.00 | NZD 1,242,077.20 AUD 137,100.00 | NZD 1,187,327.32 AUD 117,837.28 | 89% | 100% | Assignment completed. Awaiting final payment | |
7 | MIPU/CF/V-A14.1B | Supervision Services: Vanuatu Airports | Time Based Consulting Services | GHD Limited | 20 August 2017 | 20 October 2020 | NZD 1,639,985.43 | NZD 0.00 | NZD 1,639,985.43 | NZD 1,275,858.93 | 78% | 100% | Assignment completed. Awaiting final payment | |
8 | MIPU/ICBW/V-A15.5 Lot 1 | Rehabilitation of Runway, Aprons and Related Infrastructure for Bauerfield Airport, Port Vila, Vanuatu | ICB Works | JV - China Civil Engineering Construction Corporatio nand Northwest Civil Aviation Airport Construction Group | 12 May 2017 | 21 April 2019 | USD 47,660,000.00 | USD 0.00 | USD 47,660,000.00 | USD 43,598,225.78 | 91% | 100% | Final payment to be made. DLP underway | |
9 | MIPU/ICBW/V-A15.5 Lot 2 | Design and Build for Santo-Pekoa and Tanna-Whitegrass Short Term Runway Repairs | ICB Works | JV - China Civil Engineering Construction Corporatio nand Northwest Civil Aviation Airport Construction Group | 29 May 2017 | 21 January 2019 | USD 11,390,000.00 | USD 0.00 | USD 11,390,000.00 | USD 12,383,022.93 | 109% | 100% | Final payment to be made. DLP underway | |
10 | MIPU/SHPW/V-D04.1 | Physical Works for the Repair and Renovation of Whitegrass Airport Buildings, Tanna, Vanuatu | Shopping Works | The Fletcher Organisation (Vanuatu) Ltd | 28 June 2018 | 31 August 2019 | VUV 60,048,766.00 | VUV 0.00 | VUV 60,048,766.00 | VUV 40,710,080.00 | 68% | 80% | Works progressing well | |
11 | MIPU/ICS/V-E31 | VAIP Independent Claims Specialist | Lump Sum Consulting Services | Flagstaff Consulting | 15 April 2019 | 20 May 2019 | USD 28,225.00 | USD 16,310.00 | USD 44,535.00 | USD 28,255.00 | 63% | 100% | Assignment completed. Awaiting final payment | |
12 | MIPU/ICS/V-E32 | VAIP Construction Program Specialist | Lump Sum Consulting Services | Halliant, Australia | 15 April 2019 | 20 May 2019 | USD 15,900.00 | USD 14,760.00 | USD 30,660.00 | USD 0.00 | 0% | 100% | Assignment completed. Awaiting final payment | |
13 | ||||||||||||||
14 | As of 31 October 2019 |