Activity Unit Number of units Unit cost in local currency Total cost (local currency) Unit cost (Eur)Total cost (Eur)Comment (if any)
3
1. Human Resources00EUR 0.00EUR 0.00
4
1.1 Staff 100EUR 0.00EUR 0.00
5
1.2 Staff 200EUR 0.00EUR 0.00
6
1.3 ….00EUR 0.00EUR 0.00
7
Subtotal HREUR 0.00
8
2.Contractual
9
2.1 Consultant 100EUR 0.00EUR 0.00
10
2.2 Consulting/Marketing firm
00EUR 0.00EUR 0.00
11
2.3 Audit00EUR 0.00EUR 0.00
12
2.4 …00EUR 0.00EUR 0.00
13
Subtotal contractualEUR 0.00
14
3. Supplies
15
3.1 Office supplies00EUR 0.00EUR 0.00
16
3.2 ….00EUR 0.00EUR 0.00
17
Subtotal suppliesEUR 0.00
18
4. Other direct costs
19
4.1 Office rent00EUR 0.00EUR 0.00
20
4.2 Training venue00EUR 0.00EUR 0.00
21
4.3…..00EUR 0.00EUR 0.00
22
Subtotal other dc0EUR 0.00
23
Total Budget0EUR 0.00
24
25
26
Activity
This can be detailed as per each category
27
Unit
For example: per year / per project / per month / per week/ per hour / package /piece/ etc.
28
Number of units
Measurable amounts for each budget line
29
Unit cost
This should be in Eur. The amout of total expenditure incurred to pay, produce, deliver 1 unit of the particular service or goods
30
Total Cost
This should be Unit Item x Value Per Unit
31
Comment
If you have any comment, or you want to explain the activity.
32
33
The exchange rate1
the exchange rate (local currency/EUR) should be from a reliable financial intermediary and be kept as supportive document.
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100