1 | www.siroccoconsulting.com | SQF Implementation Chart | ||||||||||||||||||||||||
2 | Write in your start date | |||||||||||||||||||||||||
3 | Start Date: | May 15, 2020 | Mark down the amount of weeks and the length of time to complete each section | Write an "X" in the column of the person responsible for the task — you can also add the name or change the title of each participant. | ||||||||||||||||||||||
4 | Number | Title | Steps | Duration (Weeks) | Hours to complete | SQF Practitioner (project lead) | CEO / Owner | Senior Site Manager | Logistics | Procurement | Operation Manufacturing | Operation Sanitation | Operation Maintenance | HR/Training | ||||||||||||
5 | QM 001 | Management Policy | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
6 | Train | X | X | |||||||||||||||||||||||
7 | Implement | X | ||||||||||||||||||||||||
8 | QM 002 | Management Commitment | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
9 | Train | X | X | |||||||||||||||||||||||
10 | Implement | X | ||||||||||||||||||||||||
11 | QM 003 | Food Safety Culture Plan | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
12 | Train | X | X | |||||||||||||||||||||||
13 | Implement | X | ||||||||||||||||||||||||
14 | QM 004 | Management Review | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
15 | Train | X | X | |||||||||||||||||||||||
16 | Implement | X | ||||||||||||||||||||||||
17 | QM 005 | Customer Complaint Procedure | Approve | 0.5 | 0.0 | X | ||||||||||||||||||||
18 | Train | X | X | |||||||||||||||||||||||
19 | Implement | X | ||||||||||||||||||||||||
20 | QM 006 | Food Safety Management System | Approve | 0.5 | 0.0 | X | ||||||||||||||||||||
21 | Train | X | X | |||||||||||||||||||||||
22 | Implement | X | ||||||||||||||||||||||||
23 | QM 007 | Document and Record Control Procedure | Approve | 0.5 | 0.0 | X | ||||||||||||||||||||
24 | Train | X | X | |||||||||||||||||||||||
25 | Implement | X | ||||||||||||||||||||||||
26 | QM 008 | Product Development and Realization | Approve | 0.5 | 0.0 | X | ||||||||||||||||||||
27 | Train | X | X | |||||||||||||||||||||||
28 | Implement | X | ||||||||||||||||||||||||
29 | QM 009 | Specifications for Raw Materials and Packaging | Approve | 0.5 | 0.0 | X | ||||||||||||||||||||
30 | Train | X | X | |||||||||||||||||||||||
31 | Implement | X | ||||||||||||||||||||||||
32 | QM 010 | Specifications for Finished Products | Approve | 0.5 | 0.0 | X | X | X | ||||||||||||||||||
33 | Train | X | X | X | X | |||||||||||||||||||||
34 | Implement | X | X | X | ||||||||||||||||||||||
35 | QM 011 | Specifications for Contract Service Providers | Approve | 0.5 | 0.0 | X | ||||||||||||||||||||
36 | Train | X | X | |||||||||||||||||||||||
37 | Implement | X | ||||||||||||||||||||||||
38 | QM 012 | Specifications for Contract Manufacturers | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
39 | Train | X | X | |||||||||||||||||||||||
40 | Implement | X | ||||||||||||||||||||||||
41 | QM 013 | Supplier Approval program | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
42 | Train | X | X | X | ||||||||||||||||||||||
43 | Implement | X | X | |||||||||||||||||||||||
44 | QM 014 | Food Legislation | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
45 | Train | X | X | X | ||||||||||||||||||||||
46 | Implement | X | X | |||||||||||||||||||||||
47 | QM 015 | Good Manufacturing Practices | Approve | 0.5 | 0.0 | X | ||||||||||||||||||||
48 | Train | X | X | |||||||||||||||||||||||
49 | Implement | X | ||||||||||||||||||||||||
50 | QM 016 | Food Safety Plan(s) | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
51 | Train | X | X | X | ||||||||||||||||||||||
52 | Implement | X | X | |||||||||||||||||||||||
53 | QM 017 | Product Sampling, Inspection, Analysis and Release | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
54 | Train | X | X | X | ||||||||||||||||||||||
55 | Implement | X | X | |||||||||||||||||||||||
56 | QM 018 | Non-Conforming Materials and Product | Approve | 0.5 | 0.0 | X | X | X | ||||||||||||||||||
57 | Train | X | X | X | X | |||||||||||||||||||||
58 | Implement | X | X | X | ||||||||||||||||||||||
59 | QM 019 | Product Rework | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
60 | Train | X | X | X | ||||||||||||||||||||||
61 | Implement | X | X | |||||||||||||||||||||||
62 | QM 020 | Environmental Monitoring Program | Approve | 0.5 | 0.0 | X | ||||||||||||||||||||
63 | Train | X | X | |||||||||||||||||||||||
64 | Implement | X | ||||||||||||||||||||||||
65 | QM 021 | Verification Schedule, Validation & Effectiveness | Approve | 0.5 | 0.0 | X | ||||||||||||||||||||
66 | Train | X | X | |||||||||||||||||||||||
67 | Implement | X | ||||||||||||||||||||||||
68 | QM 022 | Corrective Action Preventive Action | Approve | 0.5 | 0.0 | X | ||||||||||||||||||||
69 | Train | X | X | |||||||||||||||||||||||
70 | Implement | X | ||||||||||||||||||||||||
71 | QM 023 | Internal Audits | Approve | 0.5 | 0.0 | X | X | X | X | |||||||||||||||||
72 | Train | X | X | X | ||||||||||||||||||||||
73 | Implement | X | X | |||||||||||||||||||||||
74 | QM 024 and QM 024-1 | Product Coding and Traceability, Startup and Changeover & label Reconciliation | Approve | 0.5 | 0.0 | X | ||||||||||||||||||||
75 | Train | X | X | |||||||||||||||||||||||
76 | Implement | X | ||||||||||||||||||||||||
77 | QM 025 | Withdrawal and Recall | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
78 | Train | X | X | X | ||||||||||||||||||||||
79 | Implement | X | X | |||||||||||||||||||||||
80 | QM 026 | Crisis Management | Approve | 0.5 | 0.0 | X | X | X | ||||||||||||||||||
81 | Train | X | X | |||||||||||||||||||||||
82 | Implement | X | X | |||||||||||||||||||||||
83 | QM 027 | Food Defense | Approve | 0.5 | 0.0 | X | ||||||||||||||||||||
84 | Train | X | X | |||||||||||||||||||||||
85 | Implement | X | ||||||||||||||||||||||||
86 | QM 028 | Food Fraud Vulnerability Assessment and Mitigation | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
87 | Train | X | X | X | ||||||||||||||||||||||
88 | Implement | X | X | |||||||||||||||||||||||
89 | QM 029 | Allergen Control procedure | Approve | 0.5 | 0.0 | X | ||||||||||||||||||||
90 | Train | X | X | |||||||||||||||||||||||
91 | Implement | X | ||||||||||||||||||||||||
92 | QM 030 | Training procedure | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
93 | Train | X | X | X | ||||||||||||||||||||||
94 | Implement | X | X | |||||||||||||||||||||||
95 | QM 101 | Premises and Building Exterior Inspection | Approve | 0.5 | 0.0 | X | X | |||||||||||||||||||
96 | Train | X | X | X | ||||||||||||||||||||||
97 | Implement | X | X | |||||||||||||||||||||||
98 | QM 102 | Non-Conforming Equipment | Approve | 0.5 | 0.0 | |||||||||||||||||||||
99 | Train | X | ||||||||||||||||||||||||
100 | Implement | |||||||||||||||||||||||||