Division 16 — Electrical
6
LIGHTING
7
1RECESSED LIGHT FIXTURE8.0EA199.0$1,592
8
2SURFACE MOUNTED FIXTURE6.0EA250.0$1,500
9
3LED LIGHT STRIP9.0EA450.0$4,050
10
4WALL WASHER DOWNLIGHT1.0EA450.0$450
11
5INSTALL NEW PENDANT LIGHT FIXTURE FURNISHED BY OWNERS1.0EA96.0$96
12
13
POWER
14
6JUNCTION BOX5.0EA360.0$1,800
15
7EXHAUST FAN ONLY1.0EA450.0$450
16
8SWITCH11.0EA136.0$1,496
17
9JAMB SWITCH1.0EA145.0$145
18
10DUPLEX OUTLET14.0EA96.0$1,344
19
11HARD WIRE DIRECTOR2.0EA166.0$332
20
12FLOOR MOUNTED OUTLET2.0EA85.0$170
21
13GFI: GROUND FAULT INTRUPTION5.0EA96.0$480
22
14CONTRACTORS PROPOSAL TO INCLUDE UPGRADING THE ELECTRICAL SERVICE TO 200 AMPS1.0EA500.0$500
23
15WIRE1.0ls2850.0$2,850
24
25
Subtotal (Electrical)$17,255
26
SUBTOTAL$17,255.00
27
OVERHEAD & PROFIT35%$6,039.25
28
GENERAL REQUIREMENTS20%$3,451.00
29
TAX6%$1,035.30
30
TOTAL SUGGESTED BID$27,780.55
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101