Lullabot Wideband Delphi Estimation Sheet
 Share
The version of the browser you are using is no longer supported. Please upgrade to a supported browser.Dismiss

 
View only
 
 
ABC
1
How to use this estimation spreadsheet
2
3
1.Clone this spreadsheet and save it somewhere you'll find it again. You may need to re-lock some of the worksheets that are locked here.
4
2.Fill out column A in the Master Estimate sheet. What you enter there will magically show up on the developer 1 and developer 2 sheets, for them to reference when they make their own estimates.
5
3.Rename the Developer 1 and Developer 2 sheets if you'd like, perhaps to the actual developer's names.
6
4.Adjust column headings E-I to match your process - default values are: research, design, development, theming, QA.
7
5.Have the developers make their estimates in their own sheets, breaking estimates across columns E-I. Developers should also specify their uncertainty.
8
6.The Comparison sheet will show estimates from both developers, including the difference between their high estimates. You may wish to filter column C to spot high values that need discussion.
9
7.Once you've reached agreement about the estimates you've produced, copy the agreed-upon estimates to the master estimate sheet. When complete, you can check out the subtotals sheet to account for PM or other fixed costs.
10
11
Note: Cells with a grey background are computed—don't touch 'em.
12