| D | E | F | G | H | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | AA | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Task Name | Description | Duration | Start | Finish | % Progres | |||||||||||||||
2 | BV (FE) & RV/SV STG BB | 6,3 days | 4/9/26 7:30 | 4/15/26 14:36 | |||||||||||||||||
3 | WATER INTAKE | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
4 | Shutdown | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
5 | Start Work | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
6 | FILTER WATER | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
7 | Shutdown | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
8 | DEMINERALIZED WATER | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
9 | Shutdown | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
10 | INSTRUMENT AIR & PLANT AIR | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
11 | Shutdown | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
12 | COOLING WATER | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
13 | Shutdown | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
14 | BOILER & STEAM SYSTEM | 6,25 days | 4/9/26 7:30 | 4/15/26 13:36 | |||||||||||||||||
15 | Shutdown | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
16 | Start Work | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
17 | F6P-2001BO : Rek No. 0001/TASTG BB/STG/DC400/2026 | Service dan test PSV2251 (PSV SAH) | 1,5 days | 4/9/26 7:30 | 4/10/26 19:31 | ||||||||||||||||
18 | amankan sistem & persiapan material | 140000089023 / 300001941382 | 2 hrs | 4/9/26 7:30 | 4/9/26 9:30 | 100 | |||||||||||||||
19 | pasang scaffold | 2 hrs | 4/9/26 9:30 | 4/9/26 11:30 | 100 | ||||||||||||||||
20 | buka PSV2251 | 2 hrs | 4/9/26 13:30 | 4/9/26 15:30 | 100 | ||||||||||||||||
21 | turunkan PSV2251 | 2 hrs | 4/9/26 15:30 | 4/9/26 17:30 | 100 | ||||||||||||||||
22 | kirim ke m.shop | 1 hr | 4/9/26 19:30 | 4/9/26 20:30 | 100 | ||||||||||||||||
23 | bongkar PSV2251 | 2 hrs | 4/9/26 20:30 | 4/9/26 22:30 | 100 | ||||||||||||||||
24 | machining seat | 4 hrs | 4/9/26 22:30 | 4/10/26 4:30 | 100 | ||||||||||||||||
25 | lapping | 2 hrs | 4/10/26 4:30 | 4/10/26 6:30 | 100 | ||||||||||||||||
26 | assembly | 2 hrs | 4/10/26 6:30 | 4/10/26 8:31 | 100 | ||||||||||||||||
27 | test PSV2251, set pop : 25 kg | 1 hr | 4/10/26 8:31 | 4/10/26 9:31 | 100 | ||||||||||||||||
28 | kirim kelapangan | 1 hr | 4/10/26 9:31 | 4/10/26 10:31 | 100 | ||||||||||||||||
29 | bantu pasang PSV2251 | 2 hrs | 4/10/26 10:31 | 4/10/26 14:31 | 100 | ||||||||||||||||
30 | pasang PSV2251 | 2 hrs | 4/10/26 14:31 | 4/10/26 16:31 | 100 | ||||||||||||||||
31 | pemeriksaan pekerjaan | 1 hr | 4/10/26 16:31 | 4/10/26 19:31 | 100 | ||||||||||||||||
32 | F6P-2001F : Rek No. 0002/TASTG BB/STG/DC400/2026 | Service dan test PSV2001 (PSV Flash Tank) | 1,25 days | 4/10/26 9:31 | 4/11/26 15:32 | ||||||||||||||||
33 | amankan sistem & persiapan material | 140000089010 / 300001941383 | 2 hrs | 4/10/26 9:31 | 4/10/26 13:31 | 100 | |||||||||||||||
34 | pasang scaffold | 2 hrs | 4/10/26 13:31 | 4/10/26 15:31 | 100 | ||||||||||||||||
35 | buka PSV2001 | 2 hrs | 4/10/26 15:31 | 4/10/26 19:31 | 100 | ||||||||||||||||
36 | kirim ke m.shop | 1 hr | 4/10/26 19:31 | 4/10/26 20:31 | 100 | ||||||||||||||||
37 | bongkar PSV2001 | 2 hrs | 4/10/26 20:31 | 4/10/26 22:31 | 100 | ||||||||||||||||
38 | machining seat | 4 hrs | 4/10/26 22:31 | 4/11/26 4:31 | 100 | ||||||||||||||||
39 | lapping | 2 hrs | 4/11/26 4:31 | 4/11/26 6:31 | 100 | ||||||||||||||||
40 | assembly | 2 hrs | 4/11/26 6:31 | 4/11/26 8:32 | 100 | ||||||||||||||||
41 | test PSV2001, set pop : 8,4 kg | 1 hr | 4/11/26 8:32 | 4/11/26 9:32 | 100 | ||||||||||||||||
42 | kirim kelapangan | 1 hr | 4/11/26 9:32 | 4/11/26 10:32 | 100 | ||||||||||||||||
43 | pasang PSV2001 | 2 hrs | 4/11/26 10:32 | 4/11/26 14:32 | 100 | ||||||||||||||||
44 | pemeriksaan pekerjaan | 1 hr | 4/11/26 14:32 | 4/11/26 15:32 | 100 | ||||||||||||||||
45 | F6P-PV4008 : Rek No. 0003/TASTG BB/STG/DC400/2026 | Service dan test PSV4008 A & B (PSV Line ke P2B) | 3,34 days | 4/9/26 7:30 | 4/12/26 15:33 | ||||||||||||||||
46 | amankan sistem & persiapan material | 140000088991 / 300001941384 | 2 hrs | 4/9/26 7:30 | 4/9/26 9:30 | 100 | |||||||||||||||
47 | buka PSV4008 A | 2 hrs | 4/9/26 9:30 | 4/9/26 11:30 | 100 | ||||||||||||||||
48 | buka PSV4008 B | 2 hrs | 4/9/26 13:30 | 4/9/26 15:30 | 100 | ||||||||||||||||
49 | turunkan PSV4008 A | 2 hrs | 4/9/26 15:30 | 4/9/26 17:30 | 100 | ||||||||||||||||
50 | turunkan PSV4008 B | 2 hrs | 4/9/26 19:30 | 4/9/26 21:30 | 100 | ||||||||||||||||
51 | kirim ke m.shop | 1 hr | 4/9/26 21:30 | 4/9/26 22:30 | 100 | ||||||||||||||||
52 | bongkar PSV4008 A | 3 hrs | 4/9/26 22:30 | 4/10/26 3:30 | 100 | ||||||||||||||||
53 | machining seat | 6 hrs | 4/10/26 3:30 | 4/10/26 9:31 | 100 | ||||||||||||||||
54 | lapping | 3 hrs | 4/10/26 9:31 | 4/10/26 14:31 | 100 | ||||||||||||||||
55 | assembly | 3 hrs | 4/10/26 14:31 | 4/10/26 19:31 | 100 | ||||||||||||||||
56 | test PSV4008 A, set pop : 52 kg | 1 hr | 4/10/26 19:31 | 4/10/26 20:31 | 100 | ||||||||||||||||
57 | bongkar PSV4008 B | 3 hrs | 4/10/26 20:31 | 4/11/26 1:31 | 100 | ||||||||||||||||
58 | machining seat | 6 hrs | 4/11/26 1:31 | 4/11/26 7:32 | 70 | ||||||||||||||||
59 | lapping | 3 hrs | 4/11/26 7:32 | 4/11/26 10:32 | 75 | ||||||||||||||||
60 | assembly | 3 hrs | 4/11/26 10:32 | 4/11/26 15:32 | 75 | ||||||||||||||||
61 | test PSV4008 B, set pop : 52 kg | 1 hr | 4/11/26 15:32 | 4/11/26 16:32 | |||||||||||||||||
62 | kirim kelapangan | 1 hr | 4/11/26 16:32 | 4/11/26 19:32 | 50 | ||||||||||||||||
63 | angkat PSV4008 A & B | 3 hrs | 4/11/26 19:32 | 4/11/26 22:32 | 100 | ||||||||||||||||
64 | pasang PSV4008 A, step 1 : 924,2024, step 2 : 1041,561, step 3 : 1100,241 lb | 6 hrs | 4/11/26 22:32 | 4/12/26 6:32 | 100 | ||||||||||||||||
65 | pasang PSV4008 B, step 1 : 924,2024, step 2 : 1041,561, step 3 : 1100,241 lb | 6 hrs | 4/12/26 6:32 | 4/12/26 14:33 | 100 | ||||||||||||||||
66 | pemeriksaan pekerjaan | 1 hr | 4/12/26 14:33 | 4/12/26 15:33 | 100 | ||||||||||||||||
67 | F6P-2111F : Rek No. 0006/TA/STG BB/STG/DC400/2026 | service & test PSV-2211 dilapangan (PSV Soot Blower NF) | 1,96 days | 4/11/26 9:32 | 4/13/26 8:34 | ||||||||||||||||
68 | amankan sistem & persiapan material | 1400000899098 / 300001949595 | 2 hrs | 4/11/26 9:32 | 4/11/26 13:32 | 100 | |||||||||||||||
69 | pasang scaffold | 2 hrs | 4/11/26 13:32 | 4/11/26 15:32 | 100 | ||||||||||||||||
70 | bongkar PSV-2211 dilapangan | 2 hrs | 4/11/26 15:32 | 4/11/26 19:32 | 100 | ||||||||||||||||
71 | lapping, 2"J'4 | 24 hrs | 4/11/26 19:32 | 4/13/26 3:33 | 100 | ||||||||||||||||
72 | assembly, set pop : 40 kg | 4 hrs | 4/13/26 3:33 | 4/13/26 7:34 | 100 | ||||||||||||||||
73 | pemeriksaan pekerjaan | 1 hr | 4/13/26 7:34 | 4/13/26 8:34 | 100 | ||||||||||||||||
74 | F6P-2111F : Rek No. 0006/TA/STG BB/STG/DC400/2026 | service & test PSV-2111 dilapangan (PSV SD Selatan NF) | 1,96 days | 4/11/26 16:32 | 4/13/26 15:34 | ||||||||||||||||
75 | amankan sistem & persiapan material | 1400000899098 / 300001949596 | 2 hrs | 4/11/26 16:32 | 4/11/26 20:32 | 100 | |||||||||||||||
76 | pasang scaffold | 2 hrs | 4/11/26 20:32 | 4/11/26 22:32 | 100 | ||||||||||||||||
77 | bongkar PSV-2111 dilapangan | 2 hrs | 4/11/26 22:32 | 4/12/26 2:32 | 100 | ||||||||||||||||
78 | lapping | 24 hrs | 4/12/26 2:32 | 4/13/26 8:34 | 100 | ||||||||||||||||
79 | assembly, set pop : 76,5 kg | 4 hrs | 4/13/26 8:34 | 4/13/26 14:34 | 100 | ||||||||||||||||
80 | pemeriksaan pekerjaan | 1 hr | 4/13/26 14:34 | 4/13/26 15:34 | 100 | ||||||||||||||||
81 | F6P-2111F : Rek No. 0006/TA/STG BB/STG/DC400/2026 | service & test PSV-2112 dilapangan (PSV SD Utara NF) | 1,96 days | 4/13/26 14:34 | 4/15/26 13:36 | ||||||||||||||||
82 | amankan sistem & persiapan material | 1400000899098 / 300001949597 | 2 hrs | 4/13/26 14:34 | 4/13/26 16:34 | 100 | |||||||||||||||
83 | pasang scaffold | 2 hrs | 4/13/26 16:34 | 4/13/26 20:34 | 100 | ||||||||||||||||
84 | bongkar PSV-2112 dilapangan | 2 hrs | 4/13/26 20:34 | 4/13/26 22:34 | 100 | ||||||||||||||||
85 | lapping | 24 hrs | 4/13/26 22:34 | 4/15/26 6:35 | 100 | ||||||||||||||||
86 | assembly, set pop : 78,8 kg | 4 hrs | 4/15/26 6:35 | 4/15/26 10:36 | 100 | ||||||||||||||||
87 | pemeriksaan pekerjaan | 1 hr | 4/15/26 10:36 | 4/15/26 13:36 | 100 | ||||||||||||||||
88 | F6P-2111F : Rek No. 0006/TA/STG BB/STG/DC400/2026 | service & test PSV-2131 dilapangan (NF) | 1,96 days | 4/13/26 7:34 | 4/15/26 6:35 | ||||||||||||||||
89 | amankan sistem & persiapan material | 1400000899098 / 300001949598 | 2 hrs | 4/13/26 7:34 | 4/13/26 9:34 | 100 | |||||||||||||||
90 | pasang scaffold | 2 hrs | 4/13/26 9:34 | 4/13/26 13:34 | 100 | ||||||||||||||||
91 | bongkar PSV-2131 dilapangan | 2 hrs | 4/13/26 13:34 | 4/13/26 15:34 | 100 | ||||||||||||||||
92 | lapping | 24 hrs | 4/13/26 15:34 | 4/15/26 1:35 | 100 | ||||||||||||||||
93 | assembly, set pop : 67,3 kg | 4 hrs | 4/15/26 1:35 | 4/15/26 5:35 | 100 | ||||||||||||||||
94 | pemeriksaan pekerjaan | 1 hr | 4/15/26 5:35 | 4/15/26 6:35 | 100 | ||||||||||||||||
95 | F6P-2343RMA : Rek No. 0008/TA/STG BB/STG/DC400/2026 | service & test gate valve pyrite hopper coalmill 2A & 2B | 3,63 days | 4/9/26 7:30 | 4/12/26 22:33 | ||||||||||||||||
96 | amankan sistem & persiapan material | 140000089183 / 300001951533 | 2 hrs | 4/9/26 7:30 | 4/9/26 9:30 | 100 | |||||||||||||||
97 | pasang scaffold | 2 hrs | 4/9/26 9:30 | 4/9/26 11:30 | 100 | ||||||||||||||||
98 | buka gate pryrite hopper coailmill 2A | 3 hrs | 4/9/26 13:30 | 4/9/26 16:30 | 100 | ||||||||||||||||
99 | buka gate pryrite hopper coailmill 2B | 3 hrs | 4/9/26 16:30 | 4/9/26 21:30 | 100 | ||||||||||||||||
100 | turunkan gate pryrite hopper coailmil 2A | 2 hrs | 4/9/26 21:30 | 4/9/26 23:30 | 100 |