CHIEF ENGINEER PROJECTS-1 -SDRF PROGRESS REPORT
2
As on 23-09-2021
3
Physical progress86.81%
4
Financial Progress67.27%
5
SL NoName of Division Works SanctionedAS issuedTS issuedTendered Agreement executedWorks CompletedPhysical Progress (%)Expenditure (in lakh)Financial Progress (%)
6
NumberAmount in LakhsNumberAmount in LakhsNumberAmount in LakhsNumberAmount in LakhsNumberAmount in LakhsNumberAmount in Lakhs
7
1Irrigation Division Chittur3433981.223433899.983433877.8653403842.4653283182.082672549.1977.842231.9856.06
8
2Malampuzha Division1782111.391782111.391782102.891781992.51781769.2591651756.0892.701716.781.31
9
3Kuttiyadi Irrigation Project Division 1391943.121391910.51391910.31391910.31391617.791061311797.8694.241650.0984.92
10
4
Kanhirapuzha Irrigation Project Division
105884.34105883.42105882.83105882.83105729.7810270397.14728.1782.34
11
5
Pazhassi Irrigation Project Division No.2,
931715.99931715.99931715.99931715.99931715.99781457.2883.87818.4447.69
12
6Karapuzha Irrigation Project Division1454.411454.411454.411454.411446.661445.89100.0045.8984.34
13
TOTAL87210690.4787210575.6987210544.28586910398.4958579061.560067578309.386.817191.2767.27