FDP Form 7 - 20% Development Fund Utilization
3
4
UTILIZATION OF THE 20% OF THE NATIONAL TAX ALLOTMENT
5
6
REGION:
REGION V - BICOL REGION
CALENDAR YEAR:2023
7
PROVINCE:CAMARINES SURQUARTER:3
8
CITY/MUNICIPALITY:BUHI
9
10
Program or ProjectLocationTotal CostDate StartedTarget Completion DateProject StatusNo. of Extensions, if anyRemarks
11
% of CompletionTotal Cost Incurred to Date
12
SOCIAL DEVELOPMENT
13
2016 & 2017 Fund:
14
Improvement of Pamuntugan ParkSan Buenaventura, Buhi, Camarines Sur 1,384,284.55 01-Dec-2227-Jan-23100% 1,383,778.10 -100% Completed
15
16
17
18
2017 & 2018 Fund:
19
Enhancement of Local Eco-Tourism Development ProjectMagindara, Salvacion, Buhi, Camarines Sur 5,500,000.00 17-Mar-2205-Jan-23100% 5,497,000.00 -100% Completed
20
21
22
23
2018 Fund:
24
Site Development of Rural Health Unit Building (Phase II)Infront of Office on Agricultural Services (OAS), San Buena, Buhi, Camarines Sur 1,000,000.00 13-Jan-20-70% 694,487.51 -Suspended due to lot boundary negotiation; The remaining work is 18.93 LM. Concrete Fence & Steel.
25
26
27
28
29
30
2019 Fund:
31
Repair / Rehab. Of Water SystemTambo - Burocbusoc, Buhi, Camarines Sur 828,082.00 --- 563,826.00 -Suspended
32
33
34
Construction of Public ToiletPublic Terminal, San Buenaventura, Buhi, Camarines Sur 1,056,660.00 20-Mar-2330-Jun-23100% 1,041,646.00 -100% Completed
35
36
37
38
Page 1 of 5 Pages
39
40
FDP Form 7 - 20% Development Fund Utilization
41
42
UTILIZATION OF THE 20% OF THE NATIONAL TAX ALLOTMENT
43
44
REGION:
REGION V - BICOL REGION
CALENDAR YEAR:2023
45
PROVINCE:CAMARINES SURQUARTER:3
46
CITY/MUNICIPALITY:BUHI
47
48
Program or ProjectLocationDate StartedTarget Completion DateProject StatusNo. of Extensions, if anyRemarks
49
% of CompletionTotal Cost Incurred to Date
50
Construction of Public ToiletInfront of Rizal Park, San Buenaventura, Buhi, Camarines Sur 765,530.00 20-Mar-2323-Jun-23100% 748,613.80 -100% Completed
51
52
53
54
55
2020 Fund:
56
Installation of Level 2 Potable Water Supply SystemTambo - Burocbusoc, Buhi, Camarines Sur 150,000.00 --- 114,680.00 - Suspended
57
58
59
60
Repair / Rehab. of Igbac Water SystemIgbac, Buhi, Camarines Sur 900,000.00 08-Mar-22-- 798,643.60 - Suspended
61
62
63
64
2022 Fund:
65
Construction of Multi - Purpose Technical Building (Phase II)Old Municipio Building, Sta. Elena, Buhi, Camarines Sur 3,000,000.00 --- 449,638.76 -On-going
66
67
68
69
Rehabilitation of Damaged Roofing and Roof FramingBuhi Public Market, Sta. Elena, Buhi, Camarines Sur 2,000,000.00 --- 299,807.85 -On-going
70
71
72
Rehabilitation of Municipal Food Terminal - Centralized Fish Landing & DistributionSta. Elena, Buhi, Camarines Sur 585,230.00 --- 410,661.00 - On-going
73
74
75
76
Page 2 of 5 Pages
77
78
FDP Form 7 - 20% Development Fund Utilization
79
80
UTILIZATION OF THE 20% OF THE NATIONAL TAX ALLOTMENT
81
82
REGION:
REGION V - BICOL REGION
CALENDAR YEAR:2023
83
PROVINCE:CAMARINES SURQUARTER:3
84
CITY/MUNICIPALITY:BUHI
85
86
Program or ProjectLocationDate StartedTarget Completion DateProject StatusNo. of Extensions, if anyRemarks
87
% of CompletionTotal Cost Incurred to Date
88
2023 Fund:
89
Installation of Streetlights Along Provincial RoadSalvacion to Burocbusoc, Buhi, Camarines Sur 5,000,000.00 24-Apr-2326-Sep-23- 4,856,045.00 -100% Completed
90
91
92
Rehabilitation of Evacuation CenterSan Buenaventura, Buhi, Camarines Sur 2,000,000.00 22-May-2316-Aug-23100% 1,298,700.00 -100% Completed
93
94
95
Completion of Municipal Food Terminal - Centralized Fish Landing & DistributionSta. Elena, Buhi, Camarines Sur 3,000,000.00 --- 449,700.00 - On-going