PackageIRF No.IRF LINK in PrologWork to InspectInspection timeInspection DateIRF Status updated by Turner
(Rejected / Cancelled / Completed)
Tình trạng IRF cập nhật bởi Turner
2
BP0300572
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00572-SIGMA%20Installation%20of%20piping%20for%20Plumbing%20system-Level%204%20%28VO-13%29.pdf%7C109213%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of piping for Plumbing system-Level 4 (VO-13)9:00:00 AM11/15/2019
3
BP0300571
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00571-SIGMA%20Installation%20of%20pipe%2C%20fittings%2C%20flexible%20sprinkler%20joint%20and%20pressure%20test%20for%20fire%20protection%20system%20at%20Level%204%20%28VO-13%29.pdf%7C109212%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of pipe, fittings, flexible sprinkler joint and pressure test for fire protection system at Level 4 (VO-13)8:00:00 AM11/15/2019
4
BP0300570
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00570-SIGMA%20Materials%20inspection%20of%20flexible%20sprinkler%20joint%20for%20fire%20protection%20system%20%28VO-13%29.pdf%7C108884%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials inspection of flexible sprinkler joint for fire protection system (VO-13)8:30:00 AM11/6/2019
5
BP0300569
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00569-SIGMA%20Inspection%20of%20installation%2C%20testing%20and%20commissioning%20pressure%20gauge%20for%20pressure%20vesel%20%28VO-13%29.pdf%7C108885%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation, testing and commissioning pressure gauge for pressure vesel (VO-13)8:00:00 AM11/6/2019
6
BP0300568
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00568-SIGMA%20Inspection%20of%20installation%20and%20testing%20%26%20commissioning%20of%20equipments%20for%20lighting%20system%20at%20the%20Level%203-Exterior%20%28VO-11%29.pdf%7C107098%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation and testing & commissioning of equipments for lighting system at the Level 3-Exterior (VO-11)
10:00:00 AM9/18/2019
7
BP0300567
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00567-SIGMA%20Inspection%20for%20installaton%20of%20drainage%20pipe%20and%20roof%20floor%20drain%20at%20Basement%201%20and%20Level%20Rooftop.pdf%7C107005%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installaton of drainage pipe and roof floor drain at Basement 1 and Level Rooftop8:00:00 AM9/14/2019
8
BP0300566
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00566-SIGMA%20Inspection%20of%20removing%20and%20replacing%20dry%20hydrant%20valve%20for%20fire%20protection%20system%20%28VO-11%29.pdf%7C106321%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of removing and replacing dry hydrant valve for fire protection system (VO-11)9:00:00 AM8/23/2019
9
BP0300565
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00565-SIGMA%20Installation%20of%20fire%20extinguisher%20ball%20for%20fire%20protection%20system%20%28VO-11%29.pdf%7C106320%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of fire extinguisher ball for fire protection system (VO-11)8:30:00 AM8/23/2019
10
BP0300564
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00564-SIGMA%20Installation%20of%20piping%20for%20Plumbing%20system-Level%206%20%28VO-11%29.pdf%7C106318%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of piping for Plumbing system-Level 6 (VO-11)8:00:00 AM8/23/2019
11
BP0300563
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00563-SIGMA%20Inspection%20of%20installation%2C%20testing%20and%20commissioning%20sanitary%2C%20fixtures%20for%20Toilet%20area%20at%20Level%209%2C10%20%28VO-11%29.pdf%7C106082%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation, testing and commissioning sanitary, fixtures for Toilet area at Level 9,10 (VO-11)8:00:00 AM8/20/2019
12
BP0300563
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00563-SIGMA%20Inspection%20of%20removing%20and%20repplacing%20%2C%20testing%20and%20commissioning%20sanitary%20fixtures%20for%20Toilet%20area%20at%20Level%209%2C10%20%28VO-11%29.pdf%7C106317%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of removing and repplacing , testing and commissioning sanitary fixtures for Toilet area at Level 9,10 (VO-11)
8:00:00 AM8/20/2019
13
BP0300559
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00559-SIGMA%20Inspection%20of%20installation%20and%20testing%20%26%20commissioning%20of%20equipments%20for%20lighting%20system%20at%20the%20Level%206.pdf%7C105784%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation and testing & commissioning of equipments for lighting system at the Level 610:00:00 AM8/8/2019
14
BP0300557
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00557-SIAMA%20Testing%20and%20commissioning%20of%20Plumbing%20system%20and%20sanitary%20fixtures.pdf%7C105690%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Testing and commissioning of Plumbing system and sanitary fixtures9:00:00 AM8/6/2019
15
BP0300556
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00556-SIGMA%20Installation%20of%20pipe%2C%20fittings%2C%20sprinkler%20and%20pressure%20test%20for%20protection%20system%20at%20Level%207.pdf%7C105368%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of pipe, fittings, sprinkler and pressure test for protection system at Level 79:00:00 AM7/27/2019
16
BP0300555
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00555-SIGMA%20Inspection%20of%20installation%20and%20testing%20%26%20commissioning%20for%20Extorior%20lighting%20system%20at%20level%2010%2C11%2C12%2C%20Roof.pdf%7C104960%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation and testing & commissioning for Extorior lighting system at level 10,11,12, Roof6:00:00 PM7/24/2019
17
BP0300554
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00554-SIGMA%20Materials%20for%20electrical%20work-Lighting%2C%20Switch%2C%20socket%20%26%20Accessories%2C%20Thermostat%20%28Phase%209%29.pdf%7C104803%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for electrical work-Lighting, Switch, socket & Accessories, Thermostat (Phase 9)9:30:00 AM7/21/2019
18
BP0300553
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00553-SIGMA%20Installation%20of%20pipe%2C%20fittings%2C%20sprinkler%20and%20pressure%20test%20for%20protection%20system%20at%20Level%202.pdf%7C104768%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of pipe, fittings, sprinkler and pressure test for protection system at Level 210:00:00 AM7/20/2019
19
BP0300552
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00552-SIGMA%20Installation%20of%20pipe%2C%20fittings%2C%20sprinkler%20and%20pressure%20test%20for%20protection%20system%20at%20Level%206.pdf%7C104769%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of pipe, fittings, sprinkler and pressure test for protection system at Level 69:00:00 AM7/20/2019
20
BP0300551
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00551-SIGMA%20Testing%20and%20commissioning%20of%20%20equipments%20for%20irrigation%20system%20at%20Level%201.pdf%7C104528%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Testing and commissioning of equipments for irrigation system at Level 19:00:00 AM7/16/2019
21
BP0300550
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00550-SIGMA%20Installation%20of%20equipments%20for%20irrigation%20system%20at%20Level%201.pdf%7C104472%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of equipments for irrigation system at Level 19:00:00 AM7/13/2019
22
BP0300548
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00548-SIGMA%20Inspection%20of%20testing%20%26%20commissioning%20of%20FCU%20equipment%20for%20HVAC%20system%20at%20Level%206%2C7.pdf%7C104531%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of testing & commissioning of FCU equipment for HVAC system at Level 6,79:00:00 AM7/5/2019
23
BP0300549
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00549-SIGMA%20Inspection%20of%20testing%20%26%20commissioning%20of%20AHU%20equipment%20for%20HVAC%20system%20from%20B2%20to%20Roof%20floor%20%281%29.pdf%7C104529%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of testing & commissioning of AHU equipment for HVAC system from B2 to Roof floor9:00:00 AM7/4/2019
24
BP0300546
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00546%20Materials%20for%20Plumbing%20system-Equipments%20and%20accessories%20for%20irrigation%20system.pdf%7C104189%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for Plumbing system-Equipments and accessories for irrigation system9:00:00 AM7/2/2019
25
BP0300547
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00547-SIGMA%20Inspection%20of%20testing%20%26%20commissioning%20for%20electrical%20system%20%28full%20load-lighting%2C%20socket%2C%20fan%2C%20pumb%2C...%29from%20B2-Roof.pdf%7C104264%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of testing & commissioning for electrical system (full load-lighting, socket, fan, pumb,...)from B2-Roof6:00:00 PM6/29/2019
26
BP0300545
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00545-SIGMA%20Inspection%20of%20installation%20and%20testing%20%26%20commissioning%20for%20Extorior%20lighting%20system%20at%20Level%2010%2C11%2C12.pdf%7C104147%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation and testing & commissioning for Extorior lighting system at Level 10,11,126:00:00 PM6/29/2019
27
BP0300542
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00542-SIGMA%20Inspection%20for%20installation%20and%20testing%20%26%20commissioning%20of%20lighting%20system%20Level%203M%2C%20socket%20system%20Level%203%20%28VO-10%29.pdf%7C104101%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation and testing & commissioning of lighting system Level 3M, socket system Level 3 (VO-10)
9:30:00 AM6/21/2019
28
BP0300541
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00541-SIGMA%20Inspection%20of%20installation%20and%20testing%20%26%20commissioning%20for%20Extorior%20lighting%20system%20at%20Level%201%2C4%2C10%2C11%2C12.pdf%7C103780%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation and testing & commissioning for Extorior lighting system at Level 1,4,10,11,126:00:00 PM6/20/2019
29
BP0300540
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00540-SIGMA%20Materials%20for%20electrical%20work-Lighting%20%26%20accessories%20%28Phase%208%29.pdf%7C103759%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for electrical work-Lighting & accessories (Phase 8)9:30:00 AM6/20/2019
30
BP0300539
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00539-SIGMA%20Inspection%20of%20testing%20%26%20commissioning%20of%20HVAC%20equipment%20for%20HVAC%20system%2C%20according%20to%20BMS%20for%205%20days.pdf%7C103629%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of testing & commissioning of HVAC equipment for HVAC system, according to BMS for 5 days8:00:00 AM6/17/2019
31
BP0300538
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00538-SIGMA%20Materials%20for%20electrical%20work-Switch%2C%20socket%20%26%20accessories%20%28VO-10%29.pdf%7C103556%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for electrical work-Switch, socket & accessories (VO-10)9:00:00 AM6/13/2019
32
BP0300537
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00537-SIGMA%20Installation%20of%20conduit%2C%20wiring%20and%20cables%20for%20ELE%20%26%20ELV%20system%20at%20Level%207%20%28VO10%29.pdf%7C103441%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of conduit, wiring and cables for ELE & ELV system at Level 7 (VO10)9:30:00 AM6/12/2019
33
BP0300536
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00536-SIGMA%20Materials%20inspection%20of%20flexible%20sprinkler%20joint%20for%20fire%20protection%20system%20%28VO-10%29.pdf%7C103390%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials inspection of flexible sprinkler joint for fire protection system (VO-10)9:00:00 AM6/7/2019
34
BP0300535
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00535-SIGMA%20Installation%20of%20chiller%20water%20pipe%2C%20Ducting%2C%20Valve...%20for%20HVAC%20at%20Level%207.pdf%7C103355%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of chiller water pipe, Ducting, Valve... for HVAC at Level 79:30:00 AM6/5/2019
35
BP0300534
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00534-SIGMA%20Inspection%20of%20installation%20and%20testing%20%26%20commissioning%20for%20Extorior%20lighting%20system%20at%20Level%201%2C2%2C3%2C3M.pdf%7C103347%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation and testing & commissioning for Extorior lighting system at Level 1,2,3,3M9:00:00 AM6/2/2019
36
BP0300533
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00533-SIGMA%20Inspection%20of%20testing%20%26%20commissioning%20of%20FCU%20equipment%20for%20HVAC%20system%20at%20Level%201%2C2%2C3%2C3M.pdf%7C103337%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of testing & commissioning of FCU equipment for HVAC system at Level 1,2,3,3M9:00:00 AM5/31/2019
37
BP0300532
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00532-SIGMA%20Materials%20for%20electrical%20work-Switch%2C%20socket%20%26%20accessories%20%28Phase%203%29.pdf%7C103287%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for electrical work-Switch, socket & accessories (Phase 3)9:00:00 AM5/31/2019
38
BP0300531
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00531-SIGMA%20Materials%20for%20electrical%20work-Wire%20and%20cable%20%28VO-10%29.pdf%7C103336%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for electrical work-Wire and cable (VO-10)9:30:00 AM5/30/2019
39
BP0300530
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00530-SIGMA%20Inspection%20for%20installation%20and%20testing%20%26%20commissioning%20of%20DB%2C%20LCP%20panel%2C%20cable%20and%20equipment%20for%20Fire%20protection%20system%20%28VO-09%29.pdf%7C103202%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Material inspection of discharge nozzle for FM200 system (VO-PCCC)2:00:00 PM5/29/2019
40
BP0300529
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00529-SIGMA%20Material%20inspection%20of%20discharge%20nozzle%20for%20FM200%20system%20%28VO-PCCC%29.pdf%7C103203%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation and testing & commissioning of DB, LCP panel, cable and equipment for Fire protection system (VO-09)
8:00:00 AM5/29/2019
41
BP0300528
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00528-SIGMA%20Materials%20inspection%20of%20Balancing%20valve%20for%20HVAC%20system%20Level%207%20%28VO%29.pdf%7C103168%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials inspection of Balancing valve for HVAC system Level 7 (VO)9:30:00 AM5/28/2019
42
BP0300527
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00527-SIGMA%20Inspection%20for%20installation%20of%20overflow%20drain%20equipment%20for%20the%20planter%20at%20Level%201.pdf%7C103167%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation of overflow drain equipment for the planter at Level 19:30:00 AM5/28/2019
43
BP0300526
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00526-SIGMA%20Inspection%20of%20installation%20equipments%20for%20Toilet%20area%20at%20Basement%201.pdf%7C103166%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation equipments for Toilet area at Basement 19:00:00 AM5/28/2019
44
BP0300524
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00524-SIGMA%20Material%20inspection%20of%20Panel%2C%20Exit%20lighting%2C%20detector%2C%20firealarm%20module%2C%20control%20panel%2C%20cable%20and%20wiring%20for%20Electrical%20system%20%28VO-PCCC%29.pdf%7C102039%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Material inspection of Panel, Exit lighting, detector, firealarm module, control panel, cable and wiring for Electrical system (VO-PCCC)
9:00:00 AM5/23/2019
45
BP0300523
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00523-SIGMA%20Materials%20for%20electrical%20work-PVC%20conduit%20%26%20fitting%20%28VO%2009%20PCCC%20and%20Level%207%29.pdf%7C102038%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for electrical work-PVC conduit & fitting (VO 09 PCCC and Level 7)10:00:00 AM5/23/2019
46
BP0300521
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00521-SIGMA%20Inspection%20for%20installation%2C%20testing%20and%20commissioning%20of%20equipments%20for%20BMS%20system%20from%20Basement%20B2%20to%20Level%2012.pdf%7C102033%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation, testing and commissioning of equipments for BMS system from Basement B2 to Level 12
2:00:00 PM5/18/2019
47
BP0300520
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00520-SIGMA%20Inspection%20for%20installation%2C%20testing%20and%20commissioning%20of%20equipments%20for%20TEL%2CLAN%2CCATV%20system%20from%20Basement%20B2%20to%20Level%2012.pdf%7C102032%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation, testing and commissioning of equipments for TEL,LAN,CATV system from Basement B2 to Level 12
9:30:00 AM5/18/2019
48
BP0300518
Inspection of installation of Fan for HVAC system at level 3M,4,6,7,8,9,10,11,12 (V0-PCCC)
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00518-SIGMA%20Inspection%20of%20installation%20of%20Fan%20for%20HVAC%20system%20at%20level%203M%2C4%2C6%2C7%2C8%2C9%2C10%2C11%2C12%20%28V0-PCCC%29.pdf%7C102031%7C0&Com=SIGENG&Con=NGONGU0&Ai=
9:00:00 AM5/15/2019
49
BP0300517
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00517%20Inspection%20for%20installation%20of%20regulation%20%26%20firefighting%20from%20Basement%20B2%20to%20Level%2012.pdf%7C101865%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation of regulation & firefighting from Basement B2 to Level 129:00:00 AM5/15/2019Completed
50
BP0300516
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00516-SIGMA%20Inspection%20for%20installation%20of%20discharge%20nozzle%20for%20FM200%20system%20at%20electrical%20riser%20at%20Basement%20B1.pdf%7C101864%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation of discharge nozzle for FM200 system at electrical riser at Basement B18:30:00 AM5/15/2019Completed
51
BP0300515
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00515-SIGMA%20Inspection%20of%20installation%20for%20emergency%20valve%20box%20of%20Drencher%20sytsem%20at%20Basement%201%2C2.pdf%7C101863%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation for emergency valve box of Drencher sytsem at Basement 1,28:00:00 AM5/15/2019Completed
52
BP0300514
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00514-SIGMA%20Inspection%20of%20T%26C%20for%20FCU%20equipment%20for%20HVAC%20system%20at%20Level%209%2C10%2C11%2C12.pdf%7C101830%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of T&C for FCU equipment for HVAC system at Level 9,10,11,129:00:00 AM5/14/2019Completed
53
BP0300513
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00513-SIGMA%20Installation%20of%20water%20supply%20system%20for%20Cooling%20tower%20and%20Planter%20area%20at%20level%20Roof%5B1%5D.pdf%7C101829%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of water supply system for Cooling tower and Planter area at level Roof8:30:00 AM5/14/2019Completed
54
BP0300513
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00513-SIGMA%20Installation%20of%20water%20supply%20system%20for%20Cooling%20tower%20and%20Planter%20area%20at%20level%20Roof%5B1%5D.pdf%7C101829%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of water supply system for Cooling tower and Planter area at level Roof8:30:00 AM5/14/2019Completed
55
BP0300512
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00512-SIGMA%20Inspection%20for%20installation%20and%20Testing%20and%20commissioning%20of%20Switch%2C%20socket%20for%20ELE%20system%20at%20Level%203%2C4.pdf%7C101828%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation and Testing and commissioning of Switch, socket for ELE system at Level 3,49:00:00 AM5/14/2019
56
BP0300522
Materials inspection of Fan and air duct for HVAC system (VO-PCCC)
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00522-SIGMA%20Materials%20inspection%20of%20Fan%20and%20air%20duct%20for%20HVAC%20system%20%28VO-PCCC%29.pdf%7C102034%7C0&Com=SIGENG&Con=NGONGU0&Ai=
9:00:00 AM5/10/2019
57
BP0300511
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00511-SIGMA%20Inspection%20of%20installation%20and%20testing%20%26%20commissioning%20for%20Exterior%20lighting%20system%20at%20Level%201.pdf%7C101746%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation and testing & commissioning for Exterior lighting system at Level 19:00:00 AM5/10/2019
58
BP0300510
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00510-SIGMA%20Inspection%20for%20installation%20and%20testing%20and%20commissioning%20of%20Switch%2C%20Socket%20for%20ELE%20system%20at%20Level%209.pdf%7C101704%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for Plumbing system-Accessories for Toilet (VO-10)9:30:00 AM5/9/2019Completed
59
BP0300509
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00509-SIGMA%20Inspection%20of%20installation%20for%20equipments%20for%20Toilet%20area%20from%20Level%201%20to%20Level%207.pdf%7C101705%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of jacketing for piping, valve and accessories for chiller system-Basement B29:30:00 AM5/9/2019Completed
60
BP0300508
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00508-SIGMA%20Materials%20for%20Plumbing%20system-Accessories%20for%20Toilet%20%28VO-10%29.pdf%7C101660%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for Plumbing system-Accessories for Toilet (VO-10)10:30:00 AM5/8/2019Completed
61
BP0300507
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00507-SIGMA%20Installation%20of%20jacketing%20for%20piping%2C%20valve%20and%20accessories%20for%20chiller%20system-Basement%20B2.pdf%7C101661%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of jacketing for piping, valve and accessories for chiller system-Basement B29:00:00 AM5/8/2019Completed
62
BP0300506
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00506-SIGMA%20Installation%20of%20piping%20for%20Plumbing%20system-Level%201%20%28V0-10%29.pdf%7C101610%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of piping for Plumbing system-Level 1 (V0-10)10:30:00 AM5/7/2019Completed
63
BP0300505
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00505-SIGMA%20Materials%20for%20Plumbing%20system-Floor%20drain%20equipment%20%28VO-10%29.pdf%7C101609%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for Plumbing system-Floor drain equipment (VO-10)9:00:00 AM5/7/2019Completed
64
BP0300503
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00503-SIGMA%20Inspection%20for%20installation%20and%20testing%20%26%20commissioning%20of%20equipment%20for%20CCTV%20system%20from%20Basement%20B2%20to%20Level%2012.pdf%7C101566%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation and testing & commissioning of equipment for CCTV system from Basement B2 to Level 12
9:30:00 AM4/26/2019
65
BP0300502
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00502-SIGMA%20Inspection%20for%20installation%20of%20overflow%20drain%20equipment%20for%20the%20planter%20from%20Level%205%20to%20level%20Tum.pdf%7C101283%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation of overflow drain equipment for the planter from Level 5 to level Tum9:30:00 AM4/25/2019Completed
66
BP0300501
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00501-SIGMA%20Materials%20for%20electrical%20work-Lighting%20%26%20Accessories%20%28Phase%207%29.pdf%7C101235%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for electrical work-Lighting & Accessories (Phase 7)9:30:00 AM4/24/2019
67
BP0300500
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00500-SIGMA%20Installation%20of%20jacketing%20for%20piping%2C%20valve%20and%20accessories%20for%20Heatpump%20system.pdf%7C101236%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of jacketing for piping, valve and accessories for Heatpump system3:00:00 PM4/24/2019Completed
68
BP0300499
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00499-SIGMA%20Inspection%20of%20installation%20and%20testing%20%26%20commissioning%20of%20equipments%20for%20lighting%20system%20at%20the%20level%206%2C7.pdf%7C101233%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation and testing & commissioning of equipments for lighting system at the level 6,710:00:00 AM4/24/2019
69
BP0300498
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00498-SIGMA%20Inspection%20of%20installation%20and%20testing%20%26%20commissioning%20of%20equipments%20for%20lighting%20system%20at%20the%20leve%204%2C5.pdf%7C101234%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation and testing & commissioning of equipments for lighting system at the leve 4,59:00:00 AM4/24/2019
70
BP0300497
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00497-SIGMA%20Inspection%20for%20installation%20and%20Testing%20and%20commissioning%20of%20Switch%2C%20socket%20for%20ELE%2C%20LAN%2C%20TEL%20system%20at%20Level%2010.pdf%7C101182%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation and Testing and commissioning of Switch, socket for ELE, LAN, TEL system at Level 102:00:00 PM4/23/2019
71
BP0300496
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00496-SIGMA%20Inspection%20for%20installation%20and%20Testing%20and%20commissioning%20of%20Switch%2C%20socket%20for%20ELE%2C%20LAN%2C%20TEL%20system%20at%20Level%2011%2C12.pdf%7C101181%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation and Testing and commissioning of Switch, socket for ELE, LAN, TEL system at Level 11,12
10:00:00 AM4/23/2019
72
BP0300495
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00495-SIGMA%20Inspection%20for%20installation%20and%20Testing%20and%20commissioning%20of%20socket%20and%20isolator%20for%20ELE%2C%20ELV%20system%20at%20Basement%20B1%2CB2.pdf%7C101180%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation and Testing and commissioning of socket and isolator for ELE, ELV system at Basement B1,B2
9:30:00 AM4/23/2019
73
BP0300494
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00494-SIGMA%20Inspection%20for%20installation%20for%20ABC%20fire%20extinguisher%20at%20Basement%20B1%2C2.pdf%7C101178%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation for ABC fire extinguisher at Basement B1,210:30:00 AM4/23/2019Completed
74
BP0300493
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00493-SIGMA%20Inspection%20for%20installation%20for%20CO2%2C%20ABC%20fire%20extinguisher%20from%20Level%201%20to%20Level%2012.pdf%7C101179%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation for CO2, ABC fire extinguisher from Level 1 to Level 129:30:00 AM4/23/2019Completed
75
BP0300491
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00491-SIGMA%20Inpection%20of%20testing%20%26%20commissioning%20for%20Exterior%20lighting%20system%20for%20Planter%20from%20Level%202%20to%20roof%20floor.pdf%7C101127%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inpection of testing & commissioning for Exterior lighting system for Planter from Level 2 to roof floor9:00:00 AM4/20/2019
76
BP0300490
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00490-SIGMA%20Materials%20for%20electrical%20work-Wire%20and%20cable%20%28VO-08%29.pdf%7C101126%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for electrical work-Wire and cable (VO-08)9:30:00 AM4/17/2019
77
BP0300489
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00489-SIGMA%20Inspection%20of%20installation%20for%20equipments%20for%20Toilet%20area%20from%20Level%208%20to%20Level%2012.pdf%7C100931%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation for equipments for Toilet area from Level 8 to Level 129:30:00 AM4/13/2019Completed
78
BP0300488
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00488-SIGMA%20Inspection%20of%20installation%20and%20testing%20%26%20commissioning%20of%20equipments%20for%20PA%20system%20from%20Level%201%20to%20Level%2012.pdf%7C100932%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation and testing & commissioning of equipments for PA system from Level 1 to Level 129:00:00 AM4/13/2019
79
BP0300492
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00492-SIGMA%20Inspection%20for%20installation%20of%20grease%20trap%20tank%20at%20Level%2012.pdf%7C101125%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation of grease trap tank at Level 122:30:00 PM4/12/2019Completed
80
BP0300487
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00487-SIGMA%20Materials%20for%20HVAC-Fan%20coil%20unit%20for%20HVAC%20system-Level%2013.pdf%7C100732%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for HVAC-Fan coil unit for HVAC system-Level 1310:30:00 AM4/10/2019Completed
81
BP0300486
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00486-SIGMA%20Materials%20for%20HVAC-Air%20grill%20for%20HVAC%20system.pdf%7C100731%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for HVAC-Air grill for HVAC system10:30:00 AM4/10/2019Completed
82
BP0300485
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00485-SIGMA%20Materials%20for%20HVAC%20system-Ventilation%20fan%20%28VO-08%29.pdf%7C100730%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for HVAC system-Ventilation fan (VO-08)9:30:00 AM4/10/2019Completed
83
BP0300484
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00484-SIGMA%20Materials%20for%20electrical%20work-Signal%20cable%20%28VO-08%29.pdf%7C100729%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for electrical work-Signal cable (VO-08)9:30:00 AM4/10/2019
84
BP0300483
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00483-SIGMA%20Testing%20and%20commissioning%20of%20Fan%20for%20HVAC%20system%20at%20the%20Basement%20B1%2CB2%2C%20Roof.pdf%7C100728%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Testing and commissioning of Fan for HVAC system at the Basement B1,B2, Roof2:00:00 PM4/9/2019Not completed
85
BP0300482
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00482-SIGMA%20Testing%20and%20commissioning%20of%20equipments%20for%20irrigation%20system%20from%20Level%205%20to%20level%2012.pdf%7C100727%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Testing and commissioning of equipments for irrigation system from Level 5 to level 1210:00:00 AM4/9/2019Completed
86
BP0300481
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00481-SIGMA%20Installation%20of%20equipments%20for%20irrigation%20system%20from%20level%205%20to%20level%20Tum.pdf%7C100726%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of equipments for irrigation system from level 5 to level Tum9:00:00 AM4/9/2019Completed
87
BP0300480
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00480-SIGMA%20Inspection%20of%20installation%20and%20testing%20%26%20commissioning%20of%20equipments%20for%20lighting%20system%20at%20the%20level%203%2C3M%2C4.pdf%7C100658%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation and testing & commissioning of equipments for lighting system at the level 3,3M,49:00:00 AM4/7/2019
88
BP0300479
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00479-SIGMA%20Materials%20for%20electrical%20work-DB%20Panel%20%28Lot%203%29.pdf%7C100657%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for electrical work-DB Panel (Lot 3)10:00:00 AM4/2/2019
89
BP0300477
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00477-SIGMA%20Installation%20of%20Sprinkler%20for%20fire%20protection%20system%20at%20Basement%20B1.pdf%7C100367%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of Sprinkler for fire protection system at Basement B110:00:00 AM3/28/2019Completed
90
BP0300476
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00476-SIGMA%20Inspection%20for%20installation%20of%20equipment%20for%20fire%20protection%20system%20at%20Level%203%2C5%20%28Adjustment%20of%20sprinkler%20position%20on%20the%20wood%20ceiling%20at%20level%203%20and%20change%20of%20position%20for%20horsereel%20cabinet%20at%20level%205%29-VO08.pdf%7C100366%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for installation of equipment for fire protection system at Level 3,5 (Adjustment of sprinkler position on the wood ceiling at level 3 and change of position for horsereel cabinet at level 5)-VO08
9:30:00 AM3/28/2019Completed
91
BP0300475
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00475-SIGMA%20Inspection%20of%20installation%20and%20testing%20%26%20commissioning%20of%20equipments%20for%20lighting%20system%20at%20level%208.pdf%7C100365%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation and testing & commissioning of equipments for lighting system at level 89:00:00 AM3/28/2019
92
BP0300474
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00474-SIGMA%20Inspection%20for%20testing%20and%20commissioning%20of%20water%20treatment%20system%20at%20pump%20room-Basement%20B2.pdf%7C100348%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for testing and commissioning of water treatment system at pump room-Basement B210:30:00 AM3/27/2019Completed
93
BP0300473
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00473-SIGMA%20Inspection%20for%20testing%20and%20commissioning%20of%20pump%20for%20plumbing%20system-Basement%20B2.pdf%7C100349%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection for testing and commissioning of pump for plumbing system-Basement B29:30:00 AM3/27/2019
94
BP0300543
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00543-SIGMA%20Installation%20of%20air%20grill%20for%20HVAC%20system%20at%20the%20level%206%2C7%2C8.pdf%7C104114%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of air grill for HVAC system at the level 6,7,89:30:00 AM3/26/2019
95
BP0300472
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00472-SIGMA%20Installation%20of%20air%20grill%20for%20HVAC%20system%20at%20the%20level%201%2C2%2C3%2C3M%2C4%2C5%2C6%2C7%2C8.pdf%7C100656%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of air grill for HVAC system at the level 1,2,3,3M,4,5,6,7,89:30:00 AM3/26/2019
96
BP0300471
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00471-SIGMA%20Installation%20of%20air%20grill%20for%20HVAC%20system%20at%20the%20level%2011.pdf%7C100655%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Installation of air grill for HVAC system at the level 119:00:00 AM3/26/2019
97
BP0300470
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00470-SIGMA%20Materials%20for%20HVAC%20system-Inox%20sheet%20thickness%200%2C4mm%20for%20weather%20protection%20cladding%20for%20chiller%20and%20Heatpump%20system%20at%20Basement%20B2%20and%20roof%20floor.pdf%7C100236%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for HVAC system-Inox sheet thickness 0,4mm for weather protection cladding for chiller and Heatpump system at Basement B2 and roof floor
9:00:00 AM3/20/2019
98
BP0300469
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00469-SIGMA%20Inspection%20of%20installation%20and%20testing%20%26%20commissioning%20of%20equipments%20for%20lighting%20system%20at%20Level%2011%2C12.pdf%7C100237%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Inspection of installation and testing & commissioning of equipments for lighting system at Level 11,129:00:00 AM3/19/2019
99
BP0300468
Inspection for testing and commissioning for firepump, piping and valve, equipment and accessories for fire protection sytsem from B2 to roof floor
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00468-SIGMA%20Inspection%20for%20testing%20and%20commissioning%20for%20firepump%2C%20piping%20and%20valve%2C%20equipment%20and%20accessories%20for%20fire%20protection%20sytsem%20from%20B2%20to%20roof%20floor.pdf%7C100023%7C0&Com=SIGENG&Con=NGONGU0&Ai=
9:00:00 AM3/15/2019
100
BP0300467
https://converge.tcco.com/PrologConverge/WebClient/download.aspx?Typ=6&Act=2&Ref=12157%7CIRF%20BP03-00467-SIGMA%20Materials%20for%20electrical%20work-Lighting%20%26%20Accessories%20%28Phase%206%29.pdf%7C99905%7C0&Com=SIGENG&Con=NGONGU0&Ai=
Materials for electrical work-Lighting & Accessories (Phase 6)9:30:00 AM3/12/2019