20% COMPONENT OF THE IRA UTILIZATION
2
FOR THE 1stQUARTER, CY 2016
3
4
5
Province, City or Municipality:BAGO CITY
6
7
Program or ProjectLocationTotal CostDate StartedTarget Completion DateProject StatusNo. of Extension, if anyRemarks
8
% of CompletionTotal Cost Incurred to Date
9
Social Development 2012
10
Const/Maint/Rep Health Center, Hospital, DCC,& Purchase
11
of Equipment P 5,000,000.00
12
13
Hospital P 1,750,000.00 1,750,000.00
14
15
Jan-16
16
Const of MRF @ Bago City Hospital, Balingasag Balingasag 260,000.00 177,418.00
17
Installation of Electrical Power Supply Line of Balingasag
18
Sewerage Treatment Plant @ BCH, Balingasag 63,015.00 63,015.00
19
Total : 323,015.00 240,433.00
20
21
Balance as of March 31, 2016 1,426,985.00
22
23
Social Development 2014
24
Const/Maint/Rep Health Center, Hospital, DCC,& Purchase
25
of Equipment P 5,000,000.00
26
Balance as of December 31, 2015 29,375.90
27
28
Const/Maint/Rep of LGO Potable WSS P 7,100,000.00
29
Balance as of December 31, 2015 8,853.27
30
31
Rehabilitation of Cultural & Historical Sites P 1,000,000.00
32
Balance as of December 31, 2015 359,000.00
33
34
35
Social Development 2015
36
Const/Maint/Rep Health Center, Hospital, DCC,& Purchase
37
of Equipment P 5,000,000.00
38
Balance as of December 31, 2015 305,000.00
39
40
Const/Maint/Rep of LGO Potable WSS P 8,000,000.00
41
Balance Appropriations December 31, 2015: 1,038,146.00
42
43
January 2016
44
Rep Damage submersible Motor Pump DJA Public Market, DJADon Jorge Araneta 37,000.00 1/12/2016 37,000.00 on going
45
Rep Damage submersible Motor Pump MYTMCCC , PoblacionPoblacion 37,000.00 1/12/2016 37,000.00 on going
46
Rep Damage Pressure Tank City Hall WSS, PoblacionPoblacion 50,000.00 1/12/2016 50,000.00 on going
47
Const 1 unit DW Prk. Province, TabunanTabunan 25,000.00 1/12/2016 24,680.00 on going
48
Rep. Damage Reversible Pump Brgy. BagroyBagroy 37,000.00 1/11/2016 37,000.00 on going
49
Const 1 SW @ Prk Humayan, TabunanTabunan 18,000.00 1/11/2016 17,890.00 on going
50
Redrilling SW Prk. Balinghoy, PoblacionPoblacion 19,000.00 1/11/2016 18,480.00 on going
51
Const 1 DW @ Prk Camingawan, TalocTaloc 29,000.00 1/11/2016 28,000.00 on going
52
Repair 5 AW, CaridadCaridad 75,000.00 1/18/2016 68,470.00 on going
53
Rep AW @ Prk. Mabinuligon, AlianzaAlianza 27,000.00 1/19/2016 24,470.00 on going
54
Installation SW @ Lag-asan Elem School, Lag-asanLag-asan 38,000.00 1/19/2016 36,540.00 on going
55
Rep. 10 units AW, BalingasagBalingasag 169,000.00 1/19/2016 153,700.00 on going
56
Total Allotment: 561,000.00
57
58
February 2016
59
Redrilling 1 SW @ Prk Violetas, BalingasagBalingasag 18,000.00 2/12/2016 16,770.00 on going
60
Installation 1 SW @ Prk. Daisy, CalumanganCalumangan 19,000.00 2/12/2016 18,440.00 on going
61
Rep Senior Citizen Asso. Bldg. WSF, Ma-aoMa-ao 16,000.00 2/12/2016 15,569.00 on going
62
Rep. Submersible Pump Alianza WSS Level III, AlianzaAlianza 75,000.00 2/15/2016 75,000.00 on going
63
Repair 5 SWH, CalumanganCalumangan 33,000.00 2/15/2016 20,850.00 on going
64
Installation 1 DW @ Prk. Matatag II, Ma-aoMa-ao 26,000.00 2/15/2016 8,930.00 on going
65
Const & Repair 5 SW @ Bybay Taloc, TalocTaloc 58,000.00 2/15/2016 40,710.00 on going
66
Installation 2 DW Prk Baras, Ma-aoMa-ao 37,000.00 2/15/2016 16,968.00 on going
67
Ext. WS Pipelines Level III, Prk. Malipayon, AtipuluanAtipuluan 69,000.00 2/15/2016 49,800.00 on going
68
Rep Submersible Pump J. Montilla E/S WSS, BacongBacong 75,000.00 2/24/2016 75,000.00 on going
69
Rep. 4AW various Puroks, NapolesNapoles 42,000.00 2/24/2016 25,380.00 on going
70
Total Allotment: 468,000.00
71
72
Total Allotment: 1,029,000.00
73
74
Balance Appropriation WSS 2015 as of March 31, 2016
9,146.00
75
76
Rehabilitation of Cultural & Historical Sites P 1,000,000.00
1,000,000.00
77
78
79
Social Development 2016
80
Const/Maint/Rep of LGO Potable WSS P 11,000,000.00
81
Balance Appropriation January 2016 11,000,000.00
82
83
February 2016
84
Acquisition 300 SW HP various BarangaysBago City 844,000.00 2/15/2016 795,000.00 on going
85
Ext. Pipeline fr Balintawak WS to Had. Gay, DJADon Jorge Araneta 111,000.00 2/29/2016 70,440.00 on going
86
Total Allotment: 955,000.00 865,440.00
87
March 2016
88
Ext. Pipeline Pk Balatong, IlijanIlijan 59,000.00 3/2/2016 43,115.00 on going
89
Const 1 SW Prk Humay, NapolesNapoles 19,000.00 3/2/2016 11,340.00 on going
90
Repair 5 AW @ various Prk, DJADon Jorge Araneta 51,000.00 3/2/2016 34,070.00 on going
91
Const Bago City Jail WSS Level III, RS Drive, Lag-asanLag-asan 470,000.00 3/2/2016 347,295.00 on going
92
Installation WSS Lag-asan E/S, Lag-asanLag-asan 486,000.00 3/9/2016 357,330.00 on going
93
Rep. AW @ various Prks, AlianzaAlianza 68,000.00 3/9/2016 46,940.00 on going
94
Rep. 10 SW# HP, BacongBacong 52,000.00 3/9/2016 39,850.00 on going
95
Const 1 SW Pk Malunggay, PacolPacol 18,000.00 3/9/2016 9,900.00 on going
96
Repair 4 AW @ Astro Farms E/S, DJADon Jorge Araneta 47,000.00 3/9/2016 31,280.00 on going
97
Const Pks Aquarius, Balulan, & Province WSS, Level III, TabunanTabunan 1,000,000.00 3/9/2016 844,060.00 on going
98
Ext. Pipeline fr. DJA Public Market to Pk Elga, DJADon Jorge Araneta 26,000.00 3/11/2016 17,400.00 on going
99
Const 1 DW @ Had. Hanao Hanao, CaridadCaridad 26,000.00 3/11/2016 17,500.00 on going
100
Const 1 DW @ Astro Farm DCC, DJADon Jorge Araneta 26,000.00 3/11/2016 17,380.00 on going