FDP Form 7 - 20% Component of the IRA Utilization
3
4
UTILIZATION OF THE 20% COMPONENT OF THE INTERNAL REVENUE ALLOTMENT (IRA)
5
AS OF THE 4th QUARTER, CY 2021(as of December 31, 2021)
6
7
8
Province: BOHOL
9
10
Program or ProjectLocationTotal CostDate StartedTarget CompletionProject StatusNo. of Extensions if anyRemarks
(Status of implementation)
11
% of Completion Total Cost incurred to Date
12
13
GENERAL SERVICES
14
15
1Estimated Loan Amortization for Hospital Modernization Program Phase 1 (Land Bank of the Philippines) Devolved Hospitals 14,678,311.12 Dec. 31, 202180.26% 11,781,327.88 Loan Amortization (with interest) for Hospital Modernization (1st phase) due as of December 31, 2021 per schedule
16
2Estimated Loan Amortization for Hospital Modernization Program Phase 2 (MDFO) Devolved Hospitals 5,855,070.00 Dec. 31, 202112.73% 376,534.07 Due as of December 31, 2021 per schedule (Loan Amortization payment for the procurement of generator set , 150 KVA for CNCNC (Loon) and repair/rehab of dormitory, perimeter fence of Catigbian District Hospital under the MDFO Loan- Hospital Modernazation Program assigned to LBP)
17
3Estimated Loan Amortization for Hospital Modernization Program Phase 2 (DBP) Devolved Hospitals 7,950,000.00 Dec. 31, 20210.06% 4,499.84 Due as of December 31, 2021 per schedule (Loan Amortization payment for the improvement of sewage treatment facility with biological and nutrient removal at GMPH Talibon under the MDFO Loan - Hospital Modernization Program assigned to LBP)
18
4Estimated Loan Amortization for Procurement of Heavy Equipment (DBP)GO/PTO 6,540,000.00 Dec. 31, 20210.00%Issuance of Certification on Availability of Funds only. Project procurement and deliveries in-progress. Release of proceeds only to be made upon certain % of completion/accomplishment.
19
5Estimated Loan Amortization for Mrchanization fo Corn/Casava/FisheriesGO/PTO 3,774,000.00 Dec. 31, 20210.00%Procurement still in progress. No amortization due yet as of September 30, 2021
20
6Estimated Loan Amortization for Wter Development Projects (Land Bank of the Philippines)GO/PTO30,000,000.00Dec. 31, 20210.00%Loan application processing in progress.
21
Sub-Total68,797,381.1212,162,361.79
22
23
24
ECONOMIC SERVICES
25
26
27
7 Rehabilitation and Improvement of various Local Roads and Bridges in the Province of Bohol
28
7.1Concreting of San Isidro – Catigbian via Caimbang Road San Isidro, Catigbian10,000,000.00Submitted Aug 16, 2021, Procurement Stage
29
7.2Concreting of Pob. (Catigbian) – Ambuan -Sagasa (Balilihan)Catigbian, Balilihan10,000,000.00Sept. 1, 2021Nov. 29, 2021
Revised End Date:
Dec. 28, 2021
1.28%29 Calendar DaysWYNN Construction On-going,
Variance = -1.14%
30
7.3Concreting of Candumayao (Catigbian)-Bogtongbod (Clarin, BoholCatigbian, Clarin15,000,000.00Aug. 27, 2021Dec. 25, 2021
Revised:
Feb. 16, 2022
45.86%2,153,802.1253 Calendar DaysDBP Construction Corporation On-going,
Variance = +2.19%, First progress billing amounting to P5,015,693.53 was recorded as payable in 2021
31
7.4Concreting of Jct. (LIR) Mahayag – Katipunan Road San Miguel 10,000,000.00 Dec. 31, 2021Submitted Oct.18, 2021, Procurement Stage
32
7.5Concreting of Pob. Inabanga – Lawis RoadInabanga 10,000,000.00 Aug. 31, 2021Nov. 28, 2021
Revised:
Feb. 10, 2022
42.28%74 Calendar Days Inabanga Drilling Construction, Steel Fabrication & Gen. Mdes. On-going,
Variance = +4.46%
33
7.6Concreting of Cambangay (San Miguel) – Soom (Trinidad) RoadSan Miguel, Trinidad 4,000,000.00 Dec. 31, 2021Submitted July 5, 2021, Procurement Stage
34
7.7Concreting of Popoo-Tugas Road, Pres. Carlos P. GarciaPres. Carlos P. Garcia 15,000,000.00 Dec. 31, 2021Submitted March 19, 2021, Procurement Stage
35
7.8Concreting of Ewon Sevilla-Candabong Loboc (Sevilla) SideSevilla 5,000,000.00 Dec. 1, 2021Jan. 29, 2022Pablo S. Labasbas Construction Corporation Juast Started
36
7.9Concreting of Cabantian-Cansiwang-Mayuga Road, GuindulmanGuindulman 20,000,000.00 Submitted Sept. 30, 2021, Procurement Stage
37
7.10Concreting of Pob.(Sierra Bullones)-Bugsok Road, Sierra Bullones Sierra Bullones 3,000,000.00 Sept. 24, 2021Nov. 1, 2021
Revised:
Nov. 25, 2021
30.59%449,812.8524 Calendar DaysA & D Construction and Supply, On going Variance= -65.20%
38
7.11Concreting of Jct.(Jagna-Sierra Bullones)-Malbog-Calabacita Road, Sierra Bullones Sierra Bullones 3,000,000.00 Dec. 31, 2021Submitted Aug. 26, 2021, Procurement Stage
39
7.12Concreting of Roxas Park-Abejilan-Togbongon-Tabuan Road, Garcia-HernandezGarcia-Hernandez 4,000,000.00 Dec. 31, 2021Submitted Nov. 29, 2021, Procurement Stage
40
7.13Concreting of Jct. (TER) Bunga Mar-Kinagbaan-Balili Road, JagnaJagna 25,000,000.00 Oct. 12, 2022Mar. 10, 202280.88% 11,143,629.99 Muaña Construction and Dev't Corp. On going Variance = +41.34% Second progress billing amonting to P6,306,716.75 recorded as payable in December 2021
41
7.14Concreting of Tiguis-Calvario (Lila)-Cambanse-Alegria (Loboc) Road, LobocLila,Loboc 15,000,000.00 Dec. 10, 2021Apr. 8, 202211.67%Muaña Construction and Dev't Corp. On going Variance = +1.15%
42
7.15Concreting of Bagumbayan-Inaghuban Road, PilarPilar 15,000,000.00 Aug. 31, 2021Dec. 28, 2021
Revised:
Jan. 13, 2022
99.41%8,877,399.3816 Calendar DaysBNYU Development Construction, On-going,
Variance = +8.41% Second progress billing recorded as payable P4,474,953.07 in 2021
43
7.16Concreting of Pob. (Guindulman)-Casbu-Bato Road, GuindulmanGuindulman 20,000,000.00 Sept. 21, 2021Feb. 27, 202271.81%8,067,198.55GCMG Construction On going Variance =+55.79% Recorded as AP 2nd partial billing amounting to P6,203,531.93
44
7.17Concreting of Guadalupe-Monte Video Road, CarmenCarmen 4,000,000.00 Sept. 6, 2021Oct. 20, 2021
Revised:
Dec. 23, 2021
100.0% 3,590,826.42 64 Calendar DaysC. Jansen Construction & Gen. Mdese. Completed
December 15, 2021
45
7.18Concreting of Bilar-Sevilla Road, BilarBilar,Sevilla 3,000,000.00 Sept. 24, 2021Nov. 2, 2021
Revised:
Jan. 4, 2022
97.82%2,677,605.1963 Calendar DaysC. Jansen Construction & Gen. Mdese. On-going,
Variance = +11.73%
46
7.19Concreting of Can-ipol-Odiong Road, Jagna RoadJagna 4,000,000.00 Dec. 31, 2021Submitted, Procurement Stage
47
7.20Concreting of Guinsularan-Lobogon RoadDuero 3,500,000.00 Dec. 31, 2021Submitted, Procurement Stage
48
7.21Construction of Box Culvert (Cross Drainage)-Pob.Carmen to VallehermosoCarmen 1,500,000.00 Dec. 31, 2021Submitted Aug. 11, 2021, Procurement Stage
49
7.22Concreting of Maribojoc-Pagnito-an-Candavid-Tubuan-Basak(Loon) RoadLoon 10,000,000.00 Dec. 31, 2021Submitted April 4, 2021, Procurement Stage
50
7.23Repair. Rehabilitation and Improvement of Various Local Roads 25,000,000.00 Dec. 31, 2021PR submitted for the Road Rehab. & Const. of Lined Canal Brgy Road, Fatima, Ubay amounting
P 312,787.73
51
52
8Provincial Counterpart for the Implementation of the Philippine Rural Development Program (PRDP)Provincewide 10,000,000.00 Dec. 31, 2021Transferred to PRDP Trust Fund as Provincial Counterpart to PRDP Sub-projects
53
9Procurement of Machineries to support for riceProvincewide 4,250,000.00 Only 7 unit of Mud Boats last Nov., 2021(not yet turn over to recepient)Dec. 31, 202127%· Amount of ABC is P3,065,000.00 - Split award 1,148,400.00 was awarded to Ubay Machineries for 7 mud boats and 1,916,600.00 approved PO/NTP (not yetdelivered) - For rebidding 1,815,000.00 Recirculating batch grain drterand rice husk fuel hot wind stove
54
5010Establishment of Fish Cages in various strategic areas of the provinceProvincewide 15,200,000.00 95 units but only 7 Fish Cages initially constructed; 5 for Talibon, 2 for B-Unido last Nov- Dec, 2021Dec. 31, 20217% 2,258,482.00 ·  Bidder Brightstone initially claim the 15% Mobilization last Sept. 30, 2021 in the amount of P2,258,482.00 -7 fish cages not yet turn-over and expected - Damaged due to typhoon Odette
55
11Procurement of Ice Making Machine and Cold Storage FacilitiesProvincewide 5,000,000.00 Dec. 31, 2021NOA- Supplier last dec. 10, 2021
56
12Establishment of Fish Feed Pellet Line Facility (Including Start up Capital)Provincewide 12,000,000.00 Dec. 31, 2021 -Building design for reviews approval by PEO - Revised Proposal, WFP and PPMP
57
13Procurement of Machineries and Establishment of Structuresfor ART CacaoProvincewide 5,200,000.00 Dec. 31, 2021Approved PO/NTP last November 5, 2021 in the amount of P3,107,500.00 (ALPS Marketing) not yet delivered -Building design for reviews approval by PEO (2,081,000.00)
58
14Procurement of Farm Equipment to promote agri-Productivity (Establishment of Food Dehydrator Facility for Fruits and Vegetables)Provincewide 8,800,000.00 Dec. 31, 2021Approved PO/NTP as of January 31, 2022
59
15Plant Nursery Enhancement Projects - Machineries and EquipmentProvincewide 2,592,992.40 Dec. 31, 2021Split award -P902,000.00 is awarded by ALPS Marketing -Approved PO/NTPlast Nov. 16, 2021 P728,800.00 (3 MSG Enterprises) for delivery - P907,000.00 for canvass as of July 2021
60
16Establishment of the Bohol Innovation HubProvincewide 20,000,000.00 Dec. 31, 2021
61
17Establishment of Two (2) Units Azolla Green HousesProvincewide 1,000,000.00 Dec. 31, 2021Approved Work and Financial Plan Bidder: JECK Construction, On going construction
62
18Procurement of needed Equipment for Meat ProcessingProvincewide 1,000,000.00 Dec. 31, 2021Approved Work and Financial Plan Approved NTP/PO Supplier: 3MSG, Delivered
63
19Multipurpose Hall/Training Center for Children's ChoirProvincewide 3,000,000.00 Dec. 31, 2021Program of Work (POW) preparation still in progress
64
20Water Desalination Project in Island BarangayProvincewide 6,500,000.00 Aug. 23, 2021Dec. 20, 202152.20% 1,064,460.74 NXTLVL Water Technology Inc. On-going,
Variance = -28.61%
65
21Water works Program for Bohol LGU'sProvincewide
66
21.1Mabini Spring Development(Source 1)Mabini, Bohol 30,000,000.00 Sept. 3, 2021Dec. 31, 202121.76% 4,498,656.83 On going construction of the project Contractor: GCMJ Construction
67
21.2Dimiao Spring DevelopmentDimiao, Bohol 10,000,000.00 Aug. 24, 2021Dec. 31, 202150.20% 1,339,318.55 On going construction of the project Contractor: Phikonstrak Development Corporation
68
22Establishment of Agri-Fishery Retail Terminal/Market includingEquipment (Tagbilaran City, Panglao, Talibon)Tagbilran City, Panglao, Talibon 15,000,000.00 Dec. 31, 2021POW preparation still in progress. Total amount budgeted to be used in the Agri-Fishery Retail Terminal/Market in the Old Tagbilaran Airport only for the Access to Recreation and Trade convergence initiative.
69
70
71
Sub-Total384,542,992.4046,121,192.62
72
73
SOCIAL SERVICES
74
75
76
23Rehabilatation of Multi-purpose Building for Persons with DisabilitiesTagbilaran City2,000,000.00Dec. 31, 2021Prepared and submitted documents necessary for procurement
77
24Food Assistance to Affected Families of COVID-19Provincewide28,605,707.28Dec. 31, 2021320,000.00Governor's Office is in charge in the implementation of the program,P28,285,707.28 already obligated and recorded as accounts payable in 2021
78
79
Sub-Total30,605,707.28320,000.00
80
81
TOTAL483,946,080.80 58,603,554.41
82
83
84
85
We hereby certify that we have reviewed the contents and hereby attest to the veracity and correctness of the data or information contained in this document.
86
87
88
89
JOSETH J. CELOCIA
JOHN TITUS J. VISTAL
ARTHUR C. YAP
90
Provincial AccountantProvincial Planning and Development CoordinatorGovernor