| A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Construction Budget vs Actual Template | |||||||||||||||||||||||||
2 | Fill in blue cells at kickoff. Update Actual Cost as work is completed. Variance calculates automatically. Positive variance = favorable. | |||||||||||||||||||||||||
3 | Project Name | Project No. | Contractor | |||||||||||||||||||||||
4 | Contract Value | Date | Project Manager | |||||||||||||||||||||||
5 | ||||||||||||||||||||||||||
6 | Cost Code | Description | Phase / Category | Estimated ($) | Actual ($) | Variance ($) | Variance (%) | Date Incurred | Invoice Status | Notes | ||||||||||||||||
7 | LABOR | |||||||||||||||||||||||||
8 | L-101 | Project Manager | Management | $38,000.00 | $36,500.00 | $1,500.00 | 3.9% | 2026-01-31 | Paid | On track -- PM hours within plan. | ||||||||||||||||
9 | L-102 | Foreman | Supervision | $52,000.00 | $53,800.00 | ($1,800.00) | -3.5% | 2026-02-28 | Paid | Ran ~35 hrs over due to scope clarifications at rough-in. | ||||||||||||||||
10 | L-103 | Journeyman Electrician | Rough-In | $44,000.00 | $44,000.00 | - | - | 2026-02-28 | Paid | |||||||||||||||||
11 | L-104 | Apprentice (2 workers) | Rough-In | $28,000.00 | $27,200.00 | $800.00 | 2.9% | 2026-02-28 | Paid | |||||||||||||||||
12 | L-105 | Overtime Premium | Various | $5,000.00 | $6,400.00 | ($1,400.00) | -28.0% | 2026-03-15 | Paid | Compressed schedule in weeks 6-8 drove OT. | ||||||||||||||||
13 | Labor Subtotal | $167,000.00 | $167,900.00 | ($900.00) | -0.5% | |||||||||||||||||||||
14 | ||||||||||||||||||||||||||
15 | MATERIALS | |||||||||||||||||||||||||
16 | M-201 | Electrical Panel (200A main) | Procurement | $8,500.00 | $8,750.00 | ($250.00) | -2.9% | 2026-01-20 | Paid | Supplier price increase after bid lock. | ||||||||||||||||
17 | M-202 | Wire and Cable | Rough-In | $12,000.00 | $11,640.00 | $360.00 | 3.0% | 2026-01-31 | Paid | |||||||||||||||||
18 | M-203 | Conduit and Fittings | Rough-In | $5,400.00 | $5,900.00 | ($500.00) | -9.3% | 2026-02-10 | Paid | Additional hangers required per GC RFI-007. | ||||||||||||||||
19 | M-204 | Devices and Covers | Trim-Out | $3,200.00 | $3,200.00 | - | - | 2026-02-15 | Paid | |||||||||||||||||
20 | M-205 | Lighting Fixtures | Trim-Out | $9,800.00 | $9,420.00 | $380.00 | 3.9% | 2026-02-28 | Paid | Owner substitution saved $380. | ||||||||||||||||
21 | M-206 | Fire Alarm Devices | Rough-In | $4,200.00 | - | $4,200.00 | 100.0% | Not Yet Billed | Scope TBD pending GC coordination. | |||||||||||||||||
22 | Materials Subtotal | $43,100.00 | $38,910.00 | $4,190.00 | 9.7% | |||||||||||||||||||||
23 | ||||||||||||||||||||||||||
24 | EQUIPMENT AND TOOLS | |||||||||||||||||||||||||
25 | E-301 | Scissor Lift Rental (4 weeks) | Various | $3,200.00 | $3,200.00 | - | - | 2026-02-01 | Paid | |||||||||||||||||
26 | E-302 | Cable Puller and Tugger | Rough-In | $800.00 | $800.00 | - | - | 2026-01-31 | Paid | |||||||||||||||||
27 | E-303 | Conduit Bender Rental | Rough-In | $400.00 | $480.00 | ($80.00) | -20.0% | 2026-02-12 | Paid | Extended 2 extra days. | ||||||||||||||||
28 | E-304 | Small Tools Allowance | Various | $1,200.00 | $1,050.00 | $150.00 | 12.5% | 2026-03-01 | Paid | |||||||||||||||||
29 | Equipment and Tools Subtotal | $5,600.00 | $5,530.00 | $70.00 | 1.3% | |||||||||||||||||||||
30 | ||||||||||||||||||||||||||
31 | SUBCONTRACTED WORK | |||||||||||||||||||||||||
32 | S-401 | Low-Voltage Cabling Subcontractor | Various | $6,500.00 | $6,500.00 | - | - | 2026-02-20 | Paid | |||||||||||||||||
33 | S-402 | Fire Suppression Tie-In | Rough-In | $2,800.00 | $2,800.00 | - | - | 2026-02-25 | Paid | |||||||||||||||||
34 | S-403 | Commissioning and Testing | Commissioning | $3,500.00 | - | $3,500.00 | 100.0% | Pending | Scheduled for project closeout week. | |||||||||||||||||
35 | Subcontracted Work Subtotal | $12,800.00 | $9,300.00 | $3,500.00 | 27.3% | |||||||||||||||||||||
36 | ||||||||||||||||||||||||||
37 | PERMITS, FEES, AND OVERHEAD | |||||||||||||||||||||||||
38 | O-501 | Electrical Permit | Pre-Construction | $1,200.00 | $1,200.00 | - | - | 2026-01-10 | Paid | |||||||||||||||||
39 | O-502 | Inspection Fees | Pre-Construction | $400.00 | $400.00 | - | - | 2026-01-15 | Paid | |||||||||||||||||
40 | O-503 | Insurance (project rider) | Pre-Construction | $1,800.00 | $1,800.00 | - | - | 2026-01-10 | Paid | |||||||||||||||||
41 | O-504 | General Overhead (5%) | Various | $3,000.00 | $3,000.00 | - | - | 2026-01-10 | Paid | |||||||||||||||||
42 | Permits, Fees, and Overhead Subtotal | $6,400.00 | $6,400.00 | - | - | |||||||||||||||||||||
43 | ||||||||||||||||||||||||||
44 | CHANGE ORDERS | |||||||||||||||||||||||||
45 | CO-001 | Add circuits to server room | Rough-In | $4,800.00 | $4,800.00 | - | - | 2026-03-05 | Paid | Approved CO per GC RFI-###. | ||||||||||||||||
46 | CO-002 | EV charger rough-in (3 stalls) | Rough-In | $2,200.00 | - | $2,200.00 | 100.0% | Pending | Owner-approved; install scheduled week 12. | |||||||||||||||||
47 | CO-003 | Emergency generator transfer switch | Rough-In | $6,500.00 | - | $6,500.00 | 100.0% | Disputed | Under negotiation -- await written approval. | |||||||||||||||||
48 | Change Orders Subtotal | $13,500.00 | $4,800.00 | $8,700.00 | 64.4% | |||||||||||||||||||||
49 | ||||||||||||||||||||||||||
50 | PROJECT TOTAL | $248,400.00 | $232,840.00 | $15,560.00 | 6.3% | |||||||||||||||||||||
51 | ||||||||||||||||||||||||||
52 | ||||||||||||||||||||||||||
53 | ||||||||||||||||||||||||||
54 | ||||||||||||||||||||||||||
55 | ||||||||||||||||||||||||||
56 | ||||||||||||||||||||||||||
57 | ||||||||||||||||||||||||||
58 | ||||||||||||||||||||||||||
59 | ||||||||||||||||||||||||||
60 | ||||||||||||||||||||||||||
61 | ||||||||||||||||||||||||||
62 | ||||||||||||||||||||||||||
63 | ||||||||||||||||||||||||||
64 | ||||||||||||||||||||||||||
65 | ||||||||||||||||||||||||||
66 | ||||||||||||||||||||||||||
67 | ||||||||||||||||||||||||||
68 | ||||||||||||||||||||||||||
69 | ||||||||||||||||||||||||||
70 | ||||||||||||||||||||||||||
71 | ||||||||||||||||||||||||||
72 | ||||||||||||||||||||||||||
73 | ||||||||||||||||||||||||||
74 | ||||||||||||||||||||||||||
75 | ||||||||||||||||||||||||||
76 | ||||||||||||||||||||||||||
77 | ||||||||||||||||||||||||||
78 | ||||||||||||||||||||||||||
79 | ||||||||||||||||||||||||||
80 | ||||||||||||||||||||||||||
81 | ||||||||||||||||||||||||||
82 | ||||||||||||||||||||||||||
83 | ||||||||||||||||||||||||||
84 | ||||||||||||||||||||||||||
85 | ||||||||||||||||||||||||||
86 | ||||||||||||||||||||||||||
87 | ||||||||||||||||||||||||||
88 | ||||||||||||||||||||||||||
89 | ||||||||||||||||||||||||||
90 | ||||||||||||||||||||||||||
91 | ||||||||||||||||||||||||||
92 | ||||||||||||||||||||||||||
93 | ||||||||||||||||||||||||||
94 | ||||||||||||||||||||||||||
95 | ||||||||||||||||||||||||||
96 | ||||||||||||||||||||||||||
97 | ||||||||||||||||||||||||||
98 | ||||||||||||||||||||||||||
99 | ||||||||||||||||||||||||||
100 | ||||||||||||||||||||||||||