ABCDEFGHIJKLMNOPQRSTUVWXYZ
1
EXCAVATION JOB COSTING
2
3
REPORT CONTROL
4
Job Cost Record
EXC2601-2026-08-001-R00Revision0Record StatusActiveForecast Date08/31/2026
5
6
Reporting Period
08/01/2026 - 08/31/2026
Project Manager
Example PM
Superintendent
Example Superintendent
7
8
9
10
11
PROJECT AND CONTRACT INFORMATION
12
Project NameExample Excavation Project
Project Number
EXC-2601CustomerExample Customer
13
14
Contract / Subcontract
C-2601 / SC-310000
Project Address
300 Example Site Road
15
16
17
18
Work Area / Trench / Phase
Building Pad A / T-001 / Phase 1
19
20
21
22
23
24
FINANCIAL SUMMARY
25
Revised Contract
Current Budget
Actual Cost
Committed Cost
Est. Cost at Completion
Forecast Gross Profit
26
$1,250,000.00-----
27
28
29
30
Forecast Gross Margin
Unapproved Change Exposure
Shoring Exposure
Dewatering Exposure
Trucking Exposure
Accounts Receivable
31
-$900.00---$1,000.00
32
33
34
35
36
37
38
COST AND PRODUCTION SUMMARY
39
Labor and Equipment
Labor, crew productivity, and payroll-sensitive data are summarized in the detailed labor report and restricted internal review.
40
41
42
43
Excavation Production, Shoring, and Dewatering
Track bank, loose, compacted, trench, shoring, and dewatering quantities and costs by work area and phase.
44
45
46
47
Materials, Trucking, and Subcontractors
Track purchase orders, supplier invoices, truck routes, tickets, disposal, borrow, and subcontractor commitments.
48
49
50
51
52
53
54
FORECAST, RISK, AND CHANGE ORDERS
55
Forecast at Completion
Forecast current budget, actual and committed cost, cost to complete, EAC, gross profit, and margin.
56
57
58
59
Change Orders, Billing, and Revenue
Track approved and pending changes, billing, retainage, collections, earned revenue, overbilling, and underbilling.
60
61
62
63
Risks, Opportunities, and Corrective Actions
Record cost risks, opportunities, corrective actions, owners, due dates, and exposure.
64
65
66
67
68
FINAL REVIEW AND APPROVAL
69
Final Estimate-to-Actual Review
Compare final estimated quantities, hours, costs, and revenue with actual results.
70
71
72
73
Lessons Learned and Approval
Capture lessons learned and feedback for estimating, production, equipment, trucking, shoring, dewatering, purchasing, restoration, project management, and accounting.
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100