ABCDEFGHIJKLMNOPQRSTUVWXYZAAABACADAEAFAGAHAI
1
GENERAL SUMMARY
2
3
PROJECT:THREE BRIDGES GOLF RESORT. (COMFORT STATION 2)DATE:6/18/2025
4
ADDRESS:SALEM, UT.
5
SCOPE:EVERYTHING
TOTAL BASE BID:
$ 1,375,646
6
7
DIVISION #DESCRIPTIONTOTAL COST
8
DIV-01GENERAL REQUIREMENTS ADDED BY CLIENT / CONTRACTOR $ -
9
DIV-03CONCRETE $ 76,117.01
10
DIV-05METALS $ 138,290.79
11
DIV-07THERMAL AND MOISTURE PROTECTION $ 69,008.39
12
DIV-08OPENINGS $ 11,710.00
13
DIV-09FINISHES $ 191,053.68
14
DIV-10SPECIALITIES $ 707.40
15
DIV-11EQUIPMENTS $ 4,246.00
16
DIV-12FURNISHING $ 25,544.01
17
DIV-22PLUMBING $ 29,039.14
18
DIV-23HEATING, VENTILATING, & AIR CONDITIONING (HVAC) $ 26,623.72
19
DIV-26ELECTRICAL $ 22,279.46
20
DIV. 31EARTHWORKS $ 284,018.68
21
DIV. 32EXTERIOR IMPROVEMENTS $ 70,951.14
22
DIV. 33UTILITIES $ 89,810.68
23
24
SUB-TOTAL $ 1,039,400.09
25
26
OVERHEAD & PROFIT
25% $ 259,850.02
27
INSURANCE0% $ -
28
TAX7.35% $ 76,395.91
29
BID BOND0.0% $ -
30
CONTIGENCIES0% $ -
31
TOTAL BASE BID $ 1,375,646.02
32
33
BREAKDOWN OF ITEMS
34
ITEM #DWG #CSI #/SUB DETAILDESCRIPTIONQTY.WASTEQTY. W/ WASTEUNIT UNIT LABOR UNIT MATERIAL TOTAL LABOR TOTAL MATERIAL UNIT COST TOTAL COSTTRADE COST
35
DIV-01GENERAL REQUIREMENTS
36
1Submittal Procedures10%1LS $ - $ - $ - $ -
37
2Temporary Facilities and Controls10%1LS $ - $ - $ - $ -
38
3Closeout Procedures 10%1LS $ - $ - $ - $ -
39
4Payment Procedures10%1LS $ - $ - $ - $ -
40
5Contract Modification Procedures10%1LS $ - $ - $ - $ -
41
6Maintenance & Traffic Protection 10%1LS $ - $ - $ - $ -
42
7Allowance for Site Staff (Guard, Manager Etc.)10%1LS $ - $ - $ - $ -
43
8Allowance for Permits10%1LS $ - $ - $ - $ -
44
9Allowance for Rental Equipment10%1LS $ - $ - $ - $ -
45
10Allowance for Cleaning & Protection10%1LS $ - $ - $ - $ -
46
11Misc. Allowances10%1LS $ - $ - $ - $ -
47
48
SUB-TOTAL $ -
49
50
DIV-03CONCRETE
51
52
COMFORT STATION 2
53
54
CONCRETE SLAB
55
56
12S2S14'' Concrete Slab On Grade 335%34CY $ 227.95 $ 257.05 $ 7,810.91 $ 8,808.05 $ 485.00 $ 16,619
57
13S2S1#4 Bars 12'' O.C. E.W35675%3746LBS $ 1.50 $ 1.70 $ 5,633.34 $ 6,352.49 $ 3.20 $ 11,986
58
14S2S14" Gravel Fill335%34CY $ 35.96 $ 26.04 $ 1,232.20 $ 892.28 $ 62.00 $ 2,124
59
15S2S112" Structural Fill995%104CY $ 32.48 $ 23.52 $ 3,372.60 $ 2,442.22 $ 56.00 $ 5,815
60
16S2S110 MIL Vapor Barrier26705%2804SF $ 1.53 $ 1.02 $ 4,289.47 $ 2,859.64 $ 2.55 $ 7,149
61
62
CONTINUOUS FOOTING
63
64
17S2S1FC2.0 - (2'-0"x1'-0") Continuous Footing 185%19CY $ 227.95 $ 257.05 $ 4,295.14 $ 4,843.45 $ 485.00 $ 9,139
65
18S2S13 #4 Cont. Bars4855%510LBS $ 1.50 $ 1.70 $ 766.68 $ 864.56 $ 3.20 $ 1,631
66
67
PAD FOOTING
68
69
19S2S1F1 - (4'-0"x4'-0"x1'-0") Pad Footing85%9CY $ 227.95 $ 257.05 $ 1,985.70 $ 2,239.19 $ 485.00 $ 4,225
70
20S2S14#4 Bars Each Way 2995%314LBS $ 1.50 $ 1.70 $ 472.60 $ 532.93 $ 3.20 $ 1,006
71
72
CONCRETE FOUNDATION WALL
73
74
21S2S1CFW-1 - 1'-3" Thick Concrete Foundation Wall - 2'-0"H185%19CY $ 227.95 $ 257.05 $ 4,407.98 $ 4,970.70 $ 485.00 $ 9,379
75
22S2S1#4 Horz. Bars @ 12'' O.C. E.W2665%279LBS $ 1.50 $ 1.70 $ 419.64 $ 473.21 $ 3.20 $ 893
76
23S2S1#4 Vert. Bars @ 18'' O.C. E.W1775%186LBS $ 1.50 $ 1.70 $ 279.76 $ 315.48 $ 3.20 $ 595
77
78
24S2S1CFW-1 - 1'-3" Thick Concrete Foundation Wall - 2'-0"H (Type B)75%7CY $ 227.95 $ 257.05 $ 1,614.27 $ 1,820.34 $ 485.00 $ 3,435
79
25S2S12#4 Horz. Bars @ 12'' O.C. E.W1955%204LBS $ 1.50 $ 1.70 $ 307.36 $ 346.59 $ 3.20 $ 654
80
26S2S12#4 Vert. Bars @ 18'' O.C. E.W735%77LBS $ 1.50 $ 1.70 $ 115.26 $ 129.97 $ 3.20 $ 245
81
82
27S2S1CFW-1 - 1'-3" Thick Concrete Foundation Wall - 10"H15%1CY $ 227.95 $ 257.05 $ 196.18 $ 221.22 $ 485.00 $ 417
83
28S2S1#4 Horz. Bars @ 12'' O.C. E.W125%12LBS $ 1.50 $ 1.70 $ 18.68 $ 21.06 $ 3.20 $ 40
84
29S2S1#4 Vert. Bars @ 18'' O.C. E.W85%8LBS $ 1.50 $ 1.70 $ 12.45 $ 14.04 $ 3.20 $ 26
85
86
30S2S18" Thick Concrete Foundation Wall - 1'-2"H15%1CY $ 227.95 $ 257.05 $ 275.83 $ 311.04 $ 485.00 $ 587
87
88
THICKEN EDGE SLAB
89
90
31S2S1Thicken Edge Slab (0.25 SF) 0.35%0.3CY $ 227.95 $ 257.05 $ 71.67 $ 80.82 $ 485.00 $ 152
91
92
SUB-TOTAL $ 37,577.70 $ 38,539.31 $ 76,117
93
94
DIV-05METALS
95
96
COMFORT STATION 2
97
98
STEEL COLUMN
99
32S1.01S1.01SC-1 - Pipe 5STD - 9'-0"H80%8EA $ 249.60 $ 320.00 $ 1,996.80 $ 2,560.00 $ 569.60 $ 4,557
100
33S1.01S1.01SC-1 - Pipe 5STD - 13'-6"H60%6EA $ 269.10 $ 345.00 $ 1,614.60 $ 2,070.00 $ 614.10 $ 3,685