1 | FDP Form 10a - Bid Results on Civil Works | |||||||||||||||||||||||||
2 | Note: Bid Results are in three (3) separate forms, particularly, for Civil Works (Form 10a -CW), Goods and Services (Form 10b - GS) and Consulting Services | |||||||||||||||||||||||||
3 | (Form 10c - CS). If there is no bidded project, good or service for the quarter, the forms must still be submitted with the said notation and signed accordingly. | |||||||||||||||||||||||||
4 | ||||||||||||||||||||||||||
5 | CIVIL WORKS BID-OUT | |||||||||||||||||||||||||
6 | ||||||||||||||||||||||||||
7 | REGION: | REGION X - NORTHERN MINDANAO | CALENDAR YEAR: | 2024 | ||||||||||||||||||||||
8 | PROVINCE: | MISAMIS ORIENTAL | QUARTER: | 3 | ||||||||||||||||||||||
9 | CITY/MUNICIPALITY: | |||||||||||||||||||||||||
10 | ||||||||||||||||||||||||||
11 | No. | Reference No. | Name of Project | Approved Budget for Contract | Location | Winning Bidder | Name and Address | Bid Amount | Bidding Date | Contract Duration | ||||||||||||||||
12 | ||||||||||||||||||||||||||
13 | 1 | 0397-24 | Construction of Child Development Center Purok 19, Poblacion, Manticao, Misamis Oriental | 3,497,619.48 | Poblacion, Manticao, Misamis Oriental | NONE | N/A | N/A | July 12, 2024 | 76 Calendar Days | ||||||||||||||||
14 | 2 | 1630-24 | Concreting of Brgy. Road Purok 3, Mandahilag, Talisayan, Misamis Oriental | 1,000,000.00 | Mandahilag, Talisayan, Misamis Oriental | NONE | N/A | N/A | July 12, 2024 | 42 Calendar Days | ||||||||||||||||
15 | 3 | 0396-24 | Construction of Child Development Center Brgy. Apas, Initao, Misamis Oriental | 3,219,840.75 | Brgy. Apas, Initao, Misamis Oriental | NONE | N/A | N/A | July 12, 2024 | 147 Calendar Days | ||||||||||||||||
16 | 4 | 1525-24 | Renovation of Hospital Building MOPH-OWWA Alubijid, Alubijid, Misamis Oriental | 15,632,585.47 | Alubijid, Misamis Oriental | CAGALAWAN ENTERPRISES INC. | N/A | 15,630,834.41 | July 12, 2024 | 94 Calendar Days | ||||||||||||||||
17 | 5 | 1629-24 | Construction of OR/DR/CSR Building Phase 1 of MOPH Magsaysay MOPH Magsaysay, Misamis Oriental | 19,991,867.00 | Magsaysay, Misamis Oriental | NONE | N/A | N/A | July 25, 2024 | 181 Calendar Days | ||||||||||||||||
18 | 6 | 0397-24 | Construction of Child Development Center Purok 19, Poblacion, Manticao, Misamis Oriental | 3,497,619.48 | Poblacion, Manticao, Misamis Oriental | CAGALAWAN ENTERPRISES INC. | N/A | 3,494,243.10 | July 25, 2024 | 76 Calendar Days | ||||||||||||||||
19 | 7 | 1630-24 | Concreting of Brgy. Road Purok 3, Mandahilag, Talisayan, Misamis Oriental | 1,000,000.00 | Mandahilag, Talisayan, Misamis Oriental | NONE | N/A | N/A | July 25, 2024 | 42 Calendar Days | ||||||||||||||||
20 | 8 | 0396-24 | Construction of Child Development Center Brgy. Apas, Initao, Misamis Oriental | 3,219,840.75 | Brgy. Apas, Initao, Misamis Oriental | CAGALAWAN ENTERPRISES INC. | N/A | 3,216,835.22 | July 25, 2024 | 147 Calendar Days | ||||||||||||||||
21 | 9 | 1977-24 | Completion of New PEO Building (Phase IV) Provincial Capitol Compound, Cagayan de Oro City | 1,499,997.51 | Cagayan de Oro City | NONE | N/A | N/A | August 8, 2024 | 55 Calendar Days | ||||||||||||||||
22 | 10 | 1350-24 | Construction of Child Development Center Brgy. Mapua, Balingoan, Misamis Oriental | 3,308,358.04 | Brgy. Mapua, Balingoan, Misamis Oriental | CAGALAWAN ENTERPRISES INC. | N/A | 3,305,651.30 | August 8, 2024 | 70 Calendar Days | ||||||||||||||||
23 | 11 | 1351-24 | Construction of Child Development Center Brgy. Dahilig Balingoan, Misamis Oriental | 3,286,345.07 | Brgy. Dahilig Balingoan, Misamis Oriental | CAGALAWAN ENTERPRISES INC. | N/A | 3,285,010.64 | August 8, 2024 | 65 Calendar Days | ||||||||||||||||
24 | 12 | 1629-24 | Construction of OR/DR/CSR Building Phase 1 of MOPH Magsaysay MOPH Magsaysay, Misamis Oriental | 19,991,867.00 | Magsaysay, Misamis Oriental | REYROSE CONST. SUPPLIER & DEV'T. CORP. | N/A | 19,981,835.46 | August 8, 2024 | 181 Calendar Days | ||||||||||||||||
25 | 13 | 1976-24 | Fabrication & Installation of Window Grills, Construction of CR & Installation of Sliding Door of ICT Room at Gracia E.S, Tagoloan, Misamis Oriental | 603,529.45 | Tagoloan, Misamis Oriental | NONE | N/A | N/A | August 8, 2024 | 26 Calendar Days | ||||||||||||||||
26 | 14 | 2146-24 | Construction of Water System Brgy. Mahayahay, Manticao, Misamis Oriental | 2,334,477.84 | Brgy. Mahayahay, Manticao, Misamis Oriental | NONE | N/A | N/A | August 22, 2024 | 37 Calendar Days | ||||||||||||||||
27 | 15 | 2145-24 | Construction of Perimeter Fence (NBI Office) Poblacion, El Salvador City | 3,757,631.75 | Poblacion, El Salvador City | NONE | N/A | N/A | August 22, 2024 | 91 Calendar Days | ||||||||||||||||
28 | 16 | 2149-24 | Rehabilitation of Water System Brgy. Lapad, laguindingan, Misamis Oriental | 1,497,606.62 | Brgy. Lapad, laguindingan, Misamis Oriental | NONE | N/A | N/A | August 22, 2024 | 56 Calendar Days | ||||||||||||||||
29 | 17 | 2148-24 | Construction of Water System Brgy. Apas, Initao Misamis Oriental | 1,191,077.96 | Brgy. Apas, Initao Misamis Oriental | NONE | N/A | N/A | August 22, 2024 | 35 Calendar Days | ||||||||||||||||
30 | 18 | 1452-24 | Construction of Outpost on the Monitoring of Taskforce Quarry w/in Misamis Oriental, Various Location | 1,604,831.49 | Misamis Oriental | BZAR CONSTRUCTION | N/A | 1,603,557.06 | August 22, 2024 | 80 Calendar days | ||||||||||||||||
31 | 19 | 2166-24 | Completion of Disaster Reponders Building Sta. Cruz, Tagoloan, Misamis Oriental | 1,250,000.00 | Sta. Cruz, Tagoloan, Misamis Oriental | ABAYCER CONST. SUPPLIES & GEN MDSE. | N/A | 1,249,012.25 | August 22, 2024 | 58 Calendar days | ||||||||||||||||
32 | 20 | 2137-24 | Construction of Water Tub Purok 3 Baybay, buko, kinoguitan, Misamis Oriental | 369,493.08 | Purok 3 Baybay, buko, kinoguitan, Misamis Oriental | CAGALAWAN ENTERPRISES INC. | N/A | 368,335.07 | August 22, 2024 | 14 Calendar days | ||||||||||||||||
33 | 21 | 2136-24 | Construction of Water System Brgy. Aluna, Initao, Misamis Oriental | 535,148.70 | Brgy. Aluna, Initao, Misamis Oriental | ABAYCER CONST. SUPPLIES & GEN MDSE. | N/A | 534,929.34 | August 22, 2024 | 20 Calendar days | ||||||||||||||||
34 | 22 | 2138-24 | Construction of Reservoir Brgy. Camanga, Manticao, Misamis Oriental | 299,273.11 | Brgy. Camanga, Manticao, Misamis Oriental | CAGALAWAN ENTERPRISES INC. | N/A | 298,339.71 | August 22, 2024 | 13 Calendar days | ||||||||||||||||
35 | 23 | 2147-24 | Improvement of Water System Brgy. Nabataan, Binuangan, Misamis Oriental | 824,914.50 | Brgy. Nabataan, Binuangan, Misamis Oriental | CAGALAWAN ENTERPRISES INC. | N/A | 823,841.46 | August 22, 2024 | 13 Calendar days | ||||||||||||||||
36 | 24 | 1977-24 | Completion of New PEO Building (Phase IV) Provincial Capitol Compound, Cagayan de Oro City | 1,499,997.51 | Cagayan de Oro City | BZAR CONSTRUCTION | N/A | 1,499,046.00 | August 22, 2024 | 55 Calendar Days | ||||||||||||||||
37 | 25 | 2229-24 | Construction of Child Development Center Zone 2 , Sitio Tagculot, Nangcaon, Opol Misamis Oriental | 3,497,084.35 | Sitio Tagapulot, Nangcaon, Opol Misamis Oriental | NONE | N/A | N/A | August 29, 2024 | 64 Calendar days | ||||||||||||||||
38 | 26 | 2228-24 | Construction of Child Development Center Purok 8, Cogon, Gitagum Misamis Oriental | 3,230,339.07 | Purok 8, Cogon, Gitagum Misamis Oriental | NONE | N/A | N/A | August 29, 2024 | 77 Calendar Days | ||||||||||||||||
39 | 27 | 2225-24 | Construction of Child Development Center Brgy. Bal-ason, Gingoog City, Misamis Oriental | 3,237,811.29 | Brgy. Bal-ason, Gingoog City, Misamis Oriental | NONE | N/A | N/A | August 29, 2024 | 65 Calendar Days | ||||||||||||||||
40 | 28 | 2224-24 | Construction of Child Development Center Brgy. Umagos, Lagonglong , Misamis Oriental | 3,138,814.76 | Brgy. Umagos, Lagonglong , Misamis Oriental | NONE | N/A | N/A | August 29, 2024 | 64 Calendar Days | ||||||||||||||||
41 | 29 | 2263-24 | Construction of Child Development Center Purok 4 Brgy. Bonifacio Aquino Magsaysay, Misamis Oriental | 3,132,206.30 | Brgy. Bonifacio Aquino Magsaysay, Misamis Oriental | NONE | N/A | N/A | September 5, 2024 | 64 Calendar days | ||||||||||||||||
42 | 30 | 2260-24 | Construction of Child Development Center Brgy. Sumalag , Kinoguitan Misamis Oriental | 3,138,104.27 | Brgy. Sumalag , Kinoguitan Misamis Oriental | NONE | N/A | N/A | September 5, 2024 | 63 Calendar days | ||||||||||||||||
43 | 31 | 2261-24 | Construction of Child Development Center Brgy. Kauswagan, Lagonglong Misamis Oriental | 3,309,674.09 | Brgy. Kauswagan, Lagonglong Misamis Oriental | NONE | N/A | N/A | September 5, 2024 | 71 Calendar days | ||||||||||||||||
44 | 32 | 2262-24 | Construction of Child Development Center Brgy. Pook, Talisayan, Misamis Oriental | 3,192,160.08 | Brgy. Pook, Talisayan, Misamis Oriental | NONE | N/A | N/A | September 5, 2024 | 80 Calendar days | ||||||||||||||||
45 | 33 | 2227-24 | Construction of Child Development Center Brgy. Samay, Gingoog City, Misamis Oriental | 3,321,531.09 | Brgy. Samay, Gingoog City, Misamis Oriental | NONE | N/A | N/A | September 5, 2024 | 175 Calendar days | ||||||||||||||||
46 | 34 | 2257-24 | Construction of Child Development Center Brgy. Ulaliman, El Salvador City, Misamis Oriental | 3,408,064.74 | Brgy. Ulaliman, El Salvador City, Misamis Oriental | NONE | N/A | N/A | September 5, 2024 | 76 Calendar days | ||||||||||||||||
47 | 35 | 2259-24 | Construction of Child Development Center Brgy.Poblacion, Binuangan, Misamis Oriental | 3,498,856.11 | Brgy.Poblacion, Binuangan, Misamis Oriental | NONE | N/A | N/A | September 5, 2024 | 82 Calendar days | ||||||||||||||||
48 | 36 | 2258-24 | Construction of Child Development Center Poblacion 6, Balingasag, Misamis Oriental | 3,198,889.46 | Poblacion 6, Balingasag, Misamis Oriental | NONE | N/A | N/A | September 5, 2024 | 80 Calendar days | ||||||||||||||||
49 | 37 | 2146-24 | Construction of Water System Brgy. Mahayahay, Manticao, Misamis Oriental | 2,334,477.84 | Brgy. Mahayahay, Manticao, Misamis Oriental | CAGALAWAN ENTERPRISES INC. | N/A | 2,332,780.75 | September 5, 2024 | 37 Calendar Days | ||||||||||||||||
50 | 38 | 2145-24 | Construction of Perimeter Fence (NBI Office) Poblacion, El Salvador City | 3,757,631.75 | Poblacion, El Salvador City | CAGALAWAN ENTERPRISES INC. | N/A | 3,756,253.95 | September 5, 2024 | 91 Calendar Days | ||||||||||||||||
51 | 39 | 2149-24 | Rehabilitation of Water System Brgy. Lapad, laguindingan, Misamis Oriental | 1,497,606.62 | Brgy. Lapad, laguindingan, Misamis Oriental | CAGALAWAN ENTERPRISES INC. | N/A | 1,496,537.31 | September 5, 2024 | 56 Calendar Days | ||||||||||||||||
52 | 40 | 2148-24 | Construction of Water System Brgy. Apas, Initao Misamis Oriental | 1,191,077.96 | Brgy. Apas, Initao Misamis Oriental | ABAYCER CONST. & GEN MDSE. | N/A | 1,190,663.26 | September 5, 2024 | 35 Calendar Days | ||||||||||||||||
53 | 41 | 2156-24 | Establishment of One (1) Unit Multi-Purpose Drying Pavement (MPDP), Brgy Macopa,Talisayan, Misamis Oriental | 494,661.97 | Brgy Macopa,Talisayan, Misamis Oriental | CAGALAWAN ENTERPRISES INC. | N/A | 493,684.91 | September 5, 2024 | 28 Calendar Days | ||||||||||||||||
54 | 42 | 2157-24 | Establishment of One (1) Unit Multi-Purpose Drying Pavement (MPDP) Purok-4 Brgy I.S. Cruz, Jasaan, Misamis Oriental | 498,551.02 | Brgy I.S. Cruz, Jasaan, Misamis Oriental | CAGALAWAN ENTERPRISES INC. | N/A | 497,448.11 | September 5, 2024 | 28 Calendar Days | ||||||||||||||||
55 | 43 | 2229-24 | Construction of Child Development Center Zone 2 , Sitio Tagculot, Nangcaon, Opol Misamis Oriental | 3,497,084.35 | Sitio Tagapulot, Nangcaon, Opol Misamis Oriental | TRI-FOLD | N/A | 3,495,394.22 | September 12, 2024 | 64 Calendar Days | ||||||||||||||||
56 | 44 | 2228-24 | Construction of Child Development Center Purok 8, Cogon, Gitagum Misamis Oriental | 3,230,339.07 | Purok 8, Cogon, Gitagum Misamis Oriental | BZAR CONSTRUCTION | N/A | 3,229,458.40 | September 12, 2024 | 77 Calendar Days | ||||||||||||||||
57 | 45 | 2225-24 | Construction of Child Development Center Brgy. Bal-ason, Gingoog City, Misamis Oriental | 3,237,811.29 | Brgy. Bal-ason, Gingoog City, Misamis Oriental | ABDUL CONSTRUCTION | N/A | 3,234,996.09 | September 12, 2024 | 65 Calendar Days | ||||||||||||||||
58 | 46 | 2224-24 | Construction of Child Development Center Brgy. Umagos, Lagonglong , Misamis Oriental | 3,138,814.76 | Brgy. Umagos, Lagonglong , Misamis Oriental | EQUALYZ TRADING | N/A | 3,137,456.45 | September 12, 2024 | 64 Calendar Days | ||||||||||||||||
59 | 47 | 2234-24 | Rehabilitation of Gym, Misamis Oriental Integrated Sports Complex, Cagayan de oro City | 7,198,351.79 | Cagayan de oro City | NONE | N/A | N/A | September 19, 2024 | 64 Calendar Days | ||||||||||||||||
60 | 48 | 2263-24 | Construction of Child Development Center Purok 4 Brgy. Bonifacio Aquino Magsaysay, Misamis Oriental | 3,132,206.30 | Brgy. Bonifacio Aquino Magsaysay, Misamis Oriental | REYROSE | N/A | 3,130,242.98 | September 19, 2024 | 64 Calendar days | ||||||||||||||||
61 | 49 | 2260-24 | Construction of Child Development Center Brgy. Sumalag , Kinoguitan Misamis Oriental | 3,138,104.27 | Brgy. Sumalag , Kinoguitan Misamis Oriental | ULTIR CONST. & DEV'T. CORP. | N/A | 3,136,309.09 | September 19, 2024 | 63 Calendar days | ||||||||||||||||
62 | 50 | 2261-24 | Construction of Child Development Center Brgy. Kauswagan, Lagonglong Misamis Oriental | 3,309,674.09 | Brgy. Kauswagan, Lagonglong Misamis Oriental | EQUALYZ TRADING | N/A | 3,308,103.88 | September 19, 2024 | 71 Calendar days | ||||||||||||||||
63 | 51 | 2262-24 | Construction of Child Development Center Brgy. Pook, Talisayan, Misamis Oriental | 3,192,160.08 | Brgy. Pook, Talisayan, Misamis Oriental | EQUALYZ TRADING | N/A | 3,190,664.38 | September 19, 2024 | 80 Calendar days | ||||||||||||||||
64 | 52 | 2227-24 | Construction of Child Development Center Brgy. Samay, Gingoog City, Misamis Oriental | 3,321,531.09 | Brgy. Samay, Gingoog City, Misamis Oriental | ABDUL CONSTRUCTION | N/A | 3,319,530.70 | September 19, 2024 | 175 Calendar days | ||||||||||||||||
65 | 53 | 2257-24 | Construction of Child Development Center Brgy. Ulaliman, El Salvador City, Misamis Oriental | 3,408,064.74 | Brgy. Ulaliman, El Salvador City, Misamis Oriental | CAGALAWAN ENTERPRISES INC. | N/A | 3,406,872.92 | September 19, 2024 | 76 Calendar days | ||||||||||||||||
66 | 54 | 2259-24 | Construction of Child Development Center Brgy.Poblacion, Binuangan, Misamis Oriental | 3,498,856.11 | Brgy.Poblacion, Binuangan, Misamis Oriental | ULTIR CONST. & DEV'T. CORP. | N/A | 3,496,654.90 | September 19, 2024 | 82 Calendar days | ||||||||||||||||
67 | 55 | 2258-24 | Construction of Child Development Center Poblacion 6, Balingasag, Misamis Oriental | 3,198,889.46 | Poblacion 6, Balingasag, Misamis Oriental | ULTIR CONST. & DEV'T. CORP. | N/A | 3,195,983.67 | September 19, 2024 | 80 Calendar days | ||||||||||||||||
68 | 56 | 2421-24 | Replacement of Concrete Pavement of Various Provincial Roads (see Attaches List of Provincial Roads ) Misamis Oriental | 29,605,200.00 | Misamis Oriental | NONE | N/A | N/A | September 26, 2024 | 145 Calendar Days | ||||||||||||||||
69 | 57 | 2453-24 | Costruction /Improvement/Rehabilitation/ Renovation of Capitol Building and its Premises, Capitol Grounds, Cagayan de Oro City, Misamis Oriental | 4,999,828.88 | Cagayan de Oro City, Misamis Oriental | NONE | N/A | N/A | September 26, 2024 | 113 Calendar Days | ||||||||||||||||
70 | 58 | 1629-24 | Construction of OR/DR/CSR Building Phase 1 of MOPH Magsaysay MOPH Magsaysay, Misamis Oriental | 19,991,867.00 | Magsaysay, Misamis Oriental | NONE | N/A | N/A | September 26, 2024 | 181 Calendar Days | ||||||||||||||||
71 | 59 | 1976-24 | Fabrication & Installation of Window Grills, Construction of CR & Installation of Sliding Door of ICT Room at Gracia E.S, Tagoloan, Misamis Oriental | 603,529.45 | Tagoloan, Misamis Oriental | EJ'S ENGINEERING SERVICES & CONST. SUPPLIES | N/A | 603,000.00 | September 26, 2024 | 26 Calendar Days | ||||||||||||||||
72 | 60 | 2524-24 | Completion of Water System in Zone 8 Brgy. Poblacion, Opol, Misamis oriental | 499,869.35 | Brgy. Poblacion, Opol, Misamis oriental | CAGALAWAN ENTERPRISES INC. | N/A | 498,802.50 | September 26, 2024 | 33 Calendar Days | ||||||||||||||||
73 | ||||||||||||||||||||||||||
74 | ||||||||||||||||||||||||||
75 | ||||||||||||||||||||||||||
76 | ||||||||||||||||||||||||||
77 | ||||||||||||||||||||||||||
78 | ||||||||||||||||||||||||||
79 | We hereby certify that we have reviewed the contents and hereby attest to the veracity and correctness of the data or information contained in this document. | |||||||||||||||||||||||||
80 | ||||||||||||||||||||||||||
81 | ||||||||||||||||||||||||||
82 | ||||||||||||||||||||||||||
83 | ||||||||||||||||||||||||||
84 | SGD | SGD | ||||||||||||||||||||||||
85 | JACQUILINE M. NOBLE | FILEMON R. AGUILAR JR. | ||||||||||||||||||||||||
86 | BAC Secretariat Head | BAC Chairperson | ||||||||||||||||||||||||
87 | ||||||||||||||||||||||||||
88 | ||||||||||||||||||||||||||
89 | ||||||||||||||||||||||||||
90 | ||||||||||||||||||||||||||
91 | ||||||||||||||||||||||||||
92 | ||||||||||||||||||||||||||
93 | ||||||||||||||||||||||||||
94 | ||||||||||||||||||||||||||
95 | ||||||||||||||||||||||||||
96 | ||||||||||||||||||||||||||
97 | ||||||||||||||||||||||||||
98 | ||||||||||||||||||||||||||
99 | ||||||||||||||||||||||||||
100 | ||||||||||||||||||||||||||