SR #CSI SECTDESCRIPTIONQUANTITYWASTAGE
(10%)
QTY WITH
WASTAGE
UNIT OF
MEASURMENT
UNIT COSTTOTAL ITEM
COST
TOTAL TRADE
COST
6
7
DIV.02SITE WORKS $ -
8
9
1Install 24"x24" Catch Basin w/Parkway Grate 1 0% 1 ea $ -
10
2Install 12"x12" Catch Basin w/ADA Grate 1 0% 1 ea $ -
11
3Install 8"x8" Catch Basin w/Parkway Grate 9 0% 9 ea $ -
12
4Install 18"x18" Catch Basin w/Parkway Grate 1 0% 1 ea $ -
13
5New Site Light Post 1 0% 1 ea $ -
14
64" PCC Sidewalk 13,463 10% 14,809 sf $ -
15
76" PCC Sidewalk 2,916 10% 3,208 sf $ -
16
84" AC / 8" AB Pavement 16,952 10% 18,647 sf $ -
17
96" Curb 661 10% 727 lf $ -
18
106" Curb and Gutter 175 10% 193 lf $ -
19
11Remove and replace 6" Curb and Gutter 265 10% 292 lf $ -
20
12Saw cut existing Pavement 397 10% 437 lf $ -
21
22
23
SUB TOTAL
$ - $ -
24
OVERHEAD & PROFIT (25%)
25% $ - $ -
25
TOTAL BID
$ - $ -
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100