S.NoStateBridge IdNH NoLatitudeLongitudeNH
Chainage
(Km)
CustodianType of StructureDescription of DistressCurrent Status
2
Bihar
3
1BiharBRBR-01N030AZ0002200002030AZ25.490263585.3021672.2RCD (NH)
(Biharsharif)
MABridge condition is ok but this is submersible type bridge and vertical clearance is not enough for water way, so a new bridge is under constructionNew bridge under constrution.
4
2BiharBRBR-02N082ZZ0038000067082ZZ24.810488785.278552338NHAI
(Gaya)
ELThis is steel bridge . This is narrow bridge . Only one way traffic movement is possible . And this bridge is not suitable for heavy load . New bridge is required .Reconstruction of bridge required.
5
3BiharBRBR-05N104ZZ0014800007104ZZ26.456788985.152781814.8RCD (NH)
(sitamarhi)
MAsacling observed in deck slab, reinforcement exposed in deck slab , pier is totally damagedMajor Repair Required
6
4BiharBRBR-08N333ZZ0021900053333ZZ25.095066986.536614521.9RCD (NH)
(Lakhisarai)
MIOld arch and narrow bridge with brickwork, bridge is totally distressd, diversion provided for traffic movement. Immdiate replacment of bridge requiredNew bridge under constrution.
7
5BiharBRBR-19N107ZZ0053800034107ZZ25.744334286.563573753.8NHAI
(Begusarai)
MIThis structure is not suitable for heavy load and NH .Old screw pile steel bridge needs immediate replacement.Contract awarded for new construction
8
6BiharBRBR-21N082ZZ0073300136082ZZ25.01071285.420469173.3NHAI
(Gaya)
MIScaling observed in deck slab . Reinforcement exposed in deck slab . Piers are totally distress . Abutment condition is bad .Reconstruction of Bridge Required
9
7BiharBRBR-21N082ZZ0109500211082ZZ25.21530685.6450375109.5NHAI
(Gaya)
MAThis is narrow bridge with carriage way 4.0m width,steel girders and deck slab condition is very poorParallelly new bridge under construction
10
8BiharBRBR-21N082ZZ0110500214082ZZ25.215472385.653704110.5NHAI
(Gaya)
MIBridge is collapsed , temporary diversion is provided.New bridge under construction.
11
9BiharBRBR-25N110ZZ0034300111110ZZ25.209785284.971889834.3RCD (NH)
(Biharsharif)
MIAbutment and pier substructure is damaged, cracks observed in deck surfaceReconstruction of Bridge Required
12
10BiharBRBR-25N110ZZ0038800117110ZZ25.222550385.009667538.8RCD (NH)
(Biharsharif)
MABridge closed. Temporary diversion providedNew bridge under constrution.
13
11BiharBRBR-27N082ZZ0048200084082ZZ24.830366585.3945648.2NHAI
(Gaya)
MAThis is steel bridge. Bridge is closed for heavy vehicle.New bridge under construction.
14
12BiharBRBR-27N082ZZ0066700130082ZZ24.965709785.42404666.7NHAI
(Gaya)
MINew bridge construction under progress due to change of allignment.New bridge construction under progress due to change of allignment.
15
13BiharBRBR-30N104ZZ0052100044104ZZ26.555310785.444762852.1RCD (NH)
(sitamarhi)
MIsacling observed in deck slab, reinforcement exposed in deck slab , pier is totally damaged Immdiate replacment of bridge requiredMajor Repair Required. Reconstruction of bridge required
16
14BiharBRBR-30N104ZZ0054300047104ZZ26.572006185.453832954.3RCD (NH)
(sitamarhi)
MIBridge is closed.Contract awarded for new construction
17
15BiharBRBR-30N104ZZ0073200061104ZZ26.644798985.594086473.2RCD (NH)
(sitamarhi)
MIThis is narrow srew pile bridge components are damagedContract awarded for new construction
18
16BiharBRBR-30N104ZZ0075000064104ZZ26.647361285.609929275RCD (NH)
(sitamarhi)
MABridge is closed.Contract awarded for new construction
19
17BiharBRBR-30N104ZZ0075100065104ZZ26.646840985.611500175.1RCD (NH)
(sitamarhi)
MABridge is closed.Contract awarded for new construction
20
18BiharBRBR-30N104ZZ0076600066104ZZ26.653082385.623111376.6RCD (NH)
(sitamarhi)
MIBridge is closed.Contract awarded for new construction
21
19BiharBRBR-30N104ZZ0081400068104ZZ26.658781185.664639581.4RCD (NH)
(sitamarhi)
MIbridge is closed for heavy loaded vehicles and diversion providedContract awarded for new construction
22
20BiharBRBR-30N104ZZ0088800072104ZZ26.642251885.730252288.8RCD (NH)
(sitamarhi)
MIBridge is closed.Contract awarded for new construction
23
21BiharBRBR-32N105ZZ0054400053105ZZ26.575708686.125929754.4RCD (NH)
(Darbhanga)
MIBridge collapsed.New bridge under constrution.
24
22BiharBRBR-32N105ZZ0054600054105ZZ26.576164486.127174554.6RCD (NH)
(Darbhanga)
MIThis narrow bridge with carriageway 3.7m width, reinfocement exposed in dech surfaceNew bridge under constrution.
25
23BiharBRBR-33N103ZZ0044000045103ZZ25.720722485.661307744RCD (NH)
(Gulzarbagh)
MIScrew pile Bridge, condition of bridge is poorNew bridge is under construction.
26
24BiharBRBR-38N327EZ0135900118327EZ26.148024487.5223304135.9RCD (NH)
(Araria)
MABridge collapsed. Temporary diversion providedDPR completed
27
25BiharBRBR-38N327EZ0142250123327EZ26.143899587.5868116142.25RCD (NH)
(Araria)
MIBridge is totally distress, reinforcement exposed in girder at the bearing point in huge amount and soffit area. Bearings are not working properly. Perapet damaged and pavement condition is bad.DPR completed
28
26BiharBRBR-39N081ZZ0055900018081ZZ25.348678487.692898455.9RCD (NH)
(Bhagalpur)
MIThis is narrow, submersible bridge. Totally choked and pavement condition is very bad.(New bridge is required) This is wrongly inventorised in NH 81 (Reconstruction of Bridge Required)
29
27BiharBRBR-45N030ZZ0031400057030ZZ25.229789383.91176531.4NHAI
(Patna)
MAMajor cracks occurred in all girders. Settlement occurred in embankment.Replacement of bridge required. New construction of bridge has been stoped due to legel issues
30
28BiharBRBR-46N333ZZ0115600136333ZZ24.625177186.3787345115.6RCD (NH)
(Lakhisarai)
MICondition of super and sub structure are good but this structure is present in between two mountains and traffic movement is very heavy. Both approches near abutment are curvilinear and high level. Parapet are damaged and pavement is damaged.DPR Under Progress for New Bridge
31
29BiharBRBR-55N104ZZ0034600028104ZZ26.514229185.308041134.6RCD (NH)
(sitamarhi)
MIBridge is closed. Diversion provided .New bridge under constrution.
32
30BiharBRBR-55N104ZZ0035900029104ZZ26.516459485.319120735.9RCD (NH)
(sitamarhi)
MIBridge is closed.New bridge under constrution.
33
31BiharBRBR-55N104ZZ0041100033104ZZ26.511322685.369227441.1RCD (NH)
(sitamarhi)
MIBridge is closed.New bridge under constrution.
34
32
35
33ChhatisgarhCGCG-09N130AN0008500002130AN22.175172781.31741278.5NH-Division Bilaspur PWDMIReconstruction shall be done; Major distress has been identified.
Previously in Minor repair list
Concerned Authority was appraised regarding the distress condition vide letter no. AA/HW/1883/17-18/447 dated- 03.07.2017;
No activity in site currently
36
34ChhatisgarhCGCG-21N130DN0021300001130DN19.64554981.487613421.3NH-Division Jagdalpur PWDMIShall be replaced with a high level bridge (vent height less than 0.5m)
Previously in Major repair list
Damaged portion of superstructure has been repaired and waterway obstructions have also been cleared
37
35ChhatisgarhCGCG-26N221ZZ0117700025221ZZ18.271420381.5260078117.7NH-Division Jagdalpur PWDMIShall be replaced with a high level bridge (vent height less than 1.0m)
Previously in Minor repair list
Widening of existing bridge is under progress
38
36ChhatisgarhCGCG-26N221ZZ0132900031221ZZ18.159338481.5116558132.9NH-Division Jagdalpur PWDMIShall be replaced with a high level bridge (vent height less than 1.0m)
Previously in Minor repair list
Widening of existing bridge is under progress
39
37ChhatisgarhCGCG-26N221ZZ0137900034221ZZ18.122254781.4954596137.9NH-Division Jagdalpur PWDMIShall be replaced with a high level bridge (vent height less than 1.0m)
Previously in Minor repair list
Old bridge demolished; New bridge is under construction at same location
40
38ChhatisgarhCGCG-26N221ZZ0151500037221ZZ18.019189281.4591151.5NH-Division Jagdalpur PWDMIShall be replaced with a high level bridge (vent height less than 1.0m)
Previously in Minor repair list
Highway under construction but no changes in the structure yet
41
39ChhatisgarhCGCG-26N221ZZ0157600039221ZZ17.977486581.4344404157.6NH-Division Jagdalpur PWDMIReconstruction shall be done; Major distress has been identified.
Previously in Minor repair list
Widening of existing bridge is under progress
42
40ChhatisgarhCGCG-26N221ZZ0175400043221ZZ17.845207881.3861516175.4NH-Division Jagdalpur PWDMIMoved to Reconstruction; Previously in Minor repair listOne of the masonry Pier collapsed resulting subsequent collapse of slabs of the adjoining spans
43
41ChhatisgarhCGCG-30N343NH0069600023343NH23.556186983.535840669.6NH-Division Ambikapur PWDMIReconstruction shall be done; Major distress has been identified.
Previously in Minor repair list
No activity in site currently
44
42
45
43GujaratGJGJ-08N168NH0041450036168NH24.492864772.007067441.45CE-NHMIBridge is closedTender process completed for New bridge.
Diversion is provided
46
44GujaratGJGJ-10N927DN0036820064927DN22.270694570.330453436.82CE-NHMIMajor Spalling in span 1 & 2
Bridge is abandoned.
Proposal of new bridge on bypass is under process
Diversion is provided
47
45GujaratGJGJ-11N008DZ0046500230008DZ21.458624770.322820946.5CGM-NHAIELBridge is ClosedThe New bridge is proposed under EPC mode . The said NH is of four lane .Hence the traffic of this distressed bridge is diverted to nearby existing two lane New bridge.
48
46GujaratGJGJ-11N008DZ0056907176008DZ21.38378270.266336556.907CGM-NHAIMABridge is ClosedThe New bridge is proposed under EPC mode . The said NH is of four lane .Hence the traffic of this distressed bridge is diverted to nearby existing two lane New bridge.
49
47GujaratGJGJ-11N008DZ0099850007008DZ21.036719570.289919399.85CGM-NHAIMABridge is ClosedThe New bridge is proposed under EPC mode . The said NH is of four lane .Hence the traffic of this distressed bridge is diverted to nearby existing two lane New bridge.
50
48GujaratGJGJ-11N008DZ0100150005008DZ21.033151970.2905824100.15CGM-NHAIELBridge is ClosedThe New bridge is proposed under EPC mode . The said NH is of four lane .Hence the traffic of this distressed bridge is diverted to nearby existing two lane New bridge.
51
49GujaratGJGJ-12N008AN0164500463008ANDoesn't Exsist164.5CE-NHMIMajor Cracks in Stone Masonry Pier 1 & 2. Major Spalling on deck slab All spanNew Bridge is Under Construction
Diversion is provided
52
50GujaratGJGJ-12N015ZZ0394530132015ZZ23.492435270.9451681394.53CGM-NHAIMI-New Bridge is constructed
53
51GujaratGJGJ-16N228ZZ0266370248228ZZ21.512915872.8209007266.37CE-NHMIStone Masonry Pier P1 & P2 Damaged & Rusting of Steel GirderNew Bridge is under Construction
54
52GujaratGJGJ-17N008Ez0339700028008EzDoesn't Exsist339.7CGM-NHAIEL-New Span is constructed
55
53GujaratGJGJ-22N753BZ0148550092753BZ148.55CE-NHMIOld Bridge is abandonedNew Bridge is Constructed
56
54GujaratGJGJ-24N015ZZ0456300114015ZZ23.805759971.3837221456.3CGM-NHAIMI-New Bridge is constructed
57
55GujaratGJGJ-24N015ZZ0456700116015ZZ23.805522571.3855434456.7CGM-NHAIMI-New Bridge is constructed
58
56GujaratGJGJ-38N008EZ0208900064008EZ20.817143370.8305412208.9CGM-NHAIMAJoints Open In brick masonry Abutment 1,2 & P-1 and P-2 Major spalling on deck slab all spanThe New bridge is proposed under Hybrid Annuity Scheme.
59
57
60
58Himachal
Pradesh
HPHP-40N020ZZ0079085435020ZZ32.132876276.296778779.085PWDMIDisintegration, scaling, and stains, moisture etc. are present in Arch.
Stone masonry abutment and pier are disintegrated.
Current status for the distressed bridges has been requested to the Chief Engineer (NH) HPPWD ,Shimla, vide letter no. CASTA 15004 /MORTH/MBIU (PKG-1)/2018-2019/ 4506 dated 04-06-2018. Awaiting their reply
61
59Himachal
Pradesh
HPHP-54N020ZZ0045380206020ZZ32.236830376.047860945.38PWDMIDeclared as damaged bridge by N.H.H.P.P.W.D. Deck is disintegrated and cracked.Current status for the distressed bridges has been requested to the Chief Engineer (NH) HPPWD ,Shimla, vide letter no. CASTA 15004 /MORTH/MBIU (PKG-1)/2018-2019/ 4506 dated 04-06-2018. Awaiting their reply
62
60Himachal
Pradesh
HPHP-54N020ZZ0045380206020ZZDuplicate id's45.38PWDMI( Earlier also this bridge is reported )
Declared as damaged bridge by N.H.H.P.P.W.D. Deck is disintegrated and cracked.
Current status for the distressed bridges has been requested to the Chief Engineer (NH) HPPWD ,Shimla, vide letter no. CASTA 15004 /MORTH/MBIU (PKG-1)/2018-2019/ 4506 dated 04-06-2018. Awaiting their reply
63
61
64
62HaryanaHRHR-03N073ZZ0120417108073ZZ30.291130376.9931511120.417NHAIMIDisintegration, scaling, spalling and stains are found at many locations in Deck. Abutments and piers are in poor condition. Disintegrated at many locations. Stains moisture, leaching, etc. are present. Abutments are damaged at top. Lots of vegetation is present.Current status for the distressed bridges has been requested to the Regional Officer, NHAI vide letter no. CASTA 15004 /MORTH/MBIU (PKG-1)/2017-2018/ 4495 dated 02-06-2018. Awaiting their reply.
65
63HaryanaHRHR-05N709AZ0128575051709AZ29.663222176.7958627128.575NHAIMISteel is excessively exposed and corroded at bottom and sides of slab.
Disintegration, scaling, spalling and leaching is present on Deck.
Abutments and piers are integrated, cracked and partially damaged. Moisture, leaching, vegetation growth, etc. are present.
Current status for the distressed bridges has been requested to the Regional Officer, NHAI vide letter no. CASTA 15004 /MORTH/MBIU (PKG-1)/2017-2018/ 4495 dated 02-06-2018. Awaiting their reply.
66
64HaryanaHRHR-11N352Az0073830109352Az29.21712876.56498273.83NHAIMISteel is exposed and corroded at bottom and sides of deck. Heavy disintegration, honeycombing, scaling, spalling and leaching is present on deck. Pier cap is severely disintegrated and honey combed. Steel is excessively exposed.Current status for the distressed bridges has been requested to the Regional Officer, NHAI vide letter no. CASTA 15004 /MORTH/MBIU (PKG-1)/2017-2018/ 4495 dated 02-06-2018. Awaiting their reply.
67
65HaryanaHRHR-19N148BZ0059676030148BZ28.564185776.252962859.676PWDMISteel of deck is excessively exposed and corroded at many locations.Brick masonry of abutments and pier is disintegrated. Honeycombing, leaching, and stains are present on cap.Current status for the distressed bridges has been requested to the Chief Engineer (NH), Haryana PWD vide letter no. CASTA 15004 /MORTH/MBIU (PKG-1)/2017-2018/ 4505 dated 04-06-2018. Awaiting their reply .
68
66HaryanaHRHR-19N148BZ0066740034148BZ28.614962276.230302466.74PWDMISteel of deck is excessively exposed and corroded at many locations.Brick masonry of abutments and pier is disintegrated. Honeycombing, leaching, and stains are present on cap.Current status for the distressed bridges has been requested to the Chief Engineer (NH), Haryana PWD vide letter no. CASTA 15004 /MORTH/MBIU (PKG-1)/2017-2018/ 4505 dated 04-06-2018. Awaiting their reply .
69
67HaryanaHRHR-21N148BZ0078930036148BZDoesn't Exsist78.93PWDMISteel of deck is excessively exposed and corroded at many locations.Brick masonry of abutments is disintegrated. Honeycombing, leaching, and stains are present on cap.Current status for the distressed bridges has been requested to the Chief Engineer (NH), Haryana PWD vide letter no. CASTA 15004 /MORTH/MBIU (PKG-1)/2017-2018/ 4505 dated 04-06-2018. Awaiting their reply .
70
68HaryanaHRHR-79N334BN0038900087334BN28.896034376.927745838.9NHAIMISteel is excessively exposed and corroded at bottom and sides of main girders, cross girders and slab.Disintegration, leaching, stains, and minor damages are present on brick masonry piers and abutments.Current status for the distressed bridges has been requested to the Regional Officer, NHAI vide letter no. CASTA 15004 /MORTH/MBIU (PKG-1)/2017-2018/ 4495 dated 02-06-2018. Awaiting their reply.
71
69
72
70JharkhandJHJH-02N033zz0040040001033zz23.967595285.37371640.04NHAIMIArch distressedRepairs not undertaken
73
71JharkhandJHJH-03N075zz0195900004075zz24.209811983.9365524195.9RCDMIDemolishedNew bridge under construction
74
72JharkhandJHJH-05N033zz0279720013033zz22.645668686.4238523279.72NHAIMIDemolishedNew bridge under construction
75
73JharkhandJHJH-13N099ZZ0027850005099ZZ24.333458984.799034527.85RCDMIDemolishedNew bridge under construction
76
74JharkhandJHJH-13N099ZZ0028200004099ZZDoesn't Exsist28.2RCDMIDemolishedNew bridge under construction
77
75JharkhandJHJH-13N099ZZ0035500006099ZZ24.275704384.818260735.5RCDMIMinor repairesNew bridge under construction
78
76JharkhandJHJH-13N099ZZ0038010007099ZZ24.265206784.82962438.01RCDMIMinor repairesNew bridge under construction
79
77JharkhandJHJH-13N099ZZ0056320010099ZZ24.132973184.849407956.32RCDMIDemolishedNew bridge contructed & opened
80
78JharkhandJHJH-13N099ZZ0075200014099ZZ23.984819584.843515875.2RCDMIMinor repairesNew bridge under construction
81
79JharkhandJHJH-14N075ZZ0211800123075ZZ24.166488183.8101261211.8RCDMIDistressed super & substructureRepairs not undertaken
82
80JharkhandJHJH-14N075zz0232350004075zz24.226230483.6146358232.35RCDMINow AbandonedNew bridge contructed & opened beside this
83
81JharkhandJHJH-14N343NH0010400003343NH24.079938183.83395710.4RCDMIMid part of superstructure distressedNew bridge under construction
84
82JharkhandJHJH-14N343NH0011550004343NH24.070527883.830961311.55RCDMIDemolishedNew bridge under construction
85
83JharkhandJHJH-14N343NH0019480005343NH24.012546783.800990419.48RCDMIMid part of structure distressedNew bridge under construction
86
84JharkhandJHJH-14N343NH0027450008343NH23.955228883.762636127.45RCDMADemolishedNew bridge under construction
87
85JharkhandJHJH-14N343NH0045050014343NH23.825732883.703244445.05RCDMIDemolishedNew bridge under construction
88
86JharkhandJHJH-17N133NH0012100001133NH25.194230887.365245512.1RCDMINow AbandonedRepairs not undertaken
89
87JharkhandJHJH-17N133NH0056700017133NH24.868544287.233184456.7RCDMANow AbandonedNew bridge constructed & opned
90
88JharkhandJHJH-17N133NH0081700125133NH24.673108587.167281981.7RCDMASuperstructure distressedfew repairs undertaken
91
89JharkhandJHJH-18N133AZ0009150006133AZ24.817275987.80073859.15RCDMIDistress in superstructureRepairs not undertaken
92
90JharkhandJHJH-19N075zz0080250011075zz23.689080884.697913480.25RCDMINow AbandonedNew bridge contructed & opened
93
91JharkhandJHJH-19N075zz0107450003075zz23.770722784.469109107.45RCDMINow CollapsedTraffic on diversion
94
92JharkhandJHJH-19N075zz0109350002075zz23.777450184.4542899109.35RCDMIDistress in stone masonry pierfew repairs undertaken
95
93JharkhandJHJH-22N043NH0055400014043NH22.897217786.068072555.4JARDCL/
RCD
ELNow AbandonedNew bridge under construction
96
94
97
95KarnatakaKAKA-03N004zz0324880005004zz12.982648177.6354318324.88NHAIMIObservations are; Masonry Structure. Loosened pointings and mortar joints in sub structure. Cracks in Masonry stone slab and Damaged Footpath Slabs. May not fit to present higher loadings as per IRC standard.Awaiting information from the respective Division.
98
96KarnatakaKAKA-06N234zz0248436005234zz13.603037376.5678874248.436CE-NHMIObservations are; Masonry Slab. Loosened pointings and disintegration of mortar joints in substructure. Damaged Masonry Parapet. Constraint in Carriageway width and may not fit to present higher loadings as per IRC standard.New bridge is under Construction at the existing chainage
99
97KarnatakaKAKA-06N234zz0283390017234zz13.700951976.8553901283.39CE-NHMIObservations are; Arch Bridge. Loss of plaster and cracks in deck. Major cavitation, spalling, loosened pointings / joints in substructure. Constraint in Carriageway width and may not fit to present higher loadings as per IRC standard.Proposed for New Bridge Construction by the respective Division.
100
98KarnatakaKAKA-10N209zz0338282040209zz12.140744777.0860162338.282CE-NHMAObservations are; Through Truss Bridge. Damage to expansion joint and leakages on slab. Expansion joint are buried with biutuminous concrete and damaged. Constraint in Carriageway width and may not fit to present higher loadings as per IRC standard.Awaiting information from the respective Division.