RPMES FORM 5
2
REGIONAL PROJECT MONITORING AND EVALUATION SYSTEM (RPMES)
3
SUMMARY OF FINANCIAL AND PHYSICAL ACCOMPLISHMENTS
4
As of September 30, 2026
5
Regional Project Monitoring Committee 02
6
Program/Project TitleImplementing AgencyImplementation ScheduleSectorFund SourceFunding AgencyTotal Program/ Project Cost
(PHP)
Financial Status (in PHP exact figures)Physical AccomplishmentEmployment GeneratedRemarks
7
Start Date
(mm-dd-yyyy)
End Date
(mm-dd-yyyy)
AppropriationsAllotmentObligationsDisbursementsFunding Support (%)Fund Utilization (%)Target OWPA to date (%)Actual OWPA to date (%)Slippage (%)MF
8
A. OFFICIAL DEVELOPMENT ASSISTANCE (ODA)-FUNDED PROGRAMS/ PROJECTS
9
1Philippine Rural Development Project (PRDP) Scale UpDA RFO 2Official Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU 1,454,972,049.88 1,607,551,000.00 1,454,972,049.89 1,437,339,337.15 647,635,905.74 90.51 44.51 -5.05 572 144
10
a) Rehabilitation/Construction of Nanauatan-Lattut Farm-to-Market RoadDA RFO 211-27-2401-19-27EconomicOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU252,919,097.84257,921,000.00252,919,097.84252,919,097.83135,845,633.82 98.06 53.71 66.4754.34-12.13 55 2 The project is delayed due to bad weather, frequent equipment breakdowns, cement shortages, and insufficient manpower. These affected the progress of civil and structural works, particularly Portland Cement Concrete Pavement (PCCP), structural concrete, steel reinforcement, aggregate subbase, and masonry works.

To address the delays, the project management granted official Suspension Orders, issued a formal Site Instruction requiring the contractor to submit a detailed Catch-Up Plan, and conducted coordination meetings to realign project performance.
11
b) Rehabilitation of Poblacion-Labang Farm to Market RoadDA RFO 210-18-2511-19-26EconomicOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU78,147,352.7988,709,000.0078,147,352.7978,147,352.7954,290,399.05 88.09 69.47 79.6674.66-5.00 23 no dataThe project is delayed due to heavy rainfall that made access routes unsafe for workers, equipment, and construction activities. Consequently, the contractor requested work suspensions for three periods: August 14 to 20, 2026 (5.5 calendar days); August 28 to September 3, 2026 (6.5 calendar days); and September 4 to 10, 2026 (5.5 calendar days).

In response, the management granted Suspension Orders, issued a formal Site Instruction requiring the contractor to submit a detailed Catch-Up Plan with revised schedules, supplemental manpower, and additional equipment deployment.
12
c) Rehabilitation of Bugallon Proper-Villa Carmen-San Antonio Farm to Market Road (FMR)DA RFO 201-25-2510-20-26EconomicOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU117,612,650.00144,310,000.00117,612,650.00117,612,650.0080,999,291.79 81.50 68.87 95.8892.94-2.94 91 1 The negative slippage is due to required back jobs on the road shoulder subbase course, insufficient manpower and equipment to perform remaining tasks simultaneously, and unworkable site conditions.

To prevent further delays, the Regional Project Coordination Office 02, the Municipal Project Management and Implementation Unit (MPMIU), and the contractor's representative conducted a site coordination meeting. A formal notice will be issued through MPMIU Ramon directing the contractor to expedite subproject completion. Additionally, the management will conduct the pre-final inspection and punch listing once the subproject reaches substantial completion at 95 percent physical accomplishment.
13
d) Rehabilitation of Sta. Lucia - Sta. Catalina Farm to Market Road with BridgeDA RFO 211-22-2407-26-26Economic ServicesOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU183,831,191.67204,279,000.00183,831,191.68183,831,191.68175,525,385.79 89.99 95.48 1001000.00 20 1 The project was physically completed on September 3, 2026.
14
e) Rehabilitation of Rizal- Abra Farm to Market RoadDA RFO 211-27-2410-08-25EconomicOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU75,890,644.5377,450,000.0075,890,644.5375,890,644.5273,430,325.51 97.99 96.76 1001000.00 58 no dataThe project was completed on January 26, 2026. A final joint inspection was conducted on January 28, 2026.
15
f) Rehabilitation of Sinsayon-Cabulay Farm to Market RoadDA RFO 211-27-2507-31-27EconomicOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU131,821,270.93 133,827,000.00 131,821,270.93 131,821,270.93 25,981,860.95 98.50 19.71 35.50 40.18 4.68 1170The positive slippage is due to the deployment of sufficient manpower and equipment to work simultaneously on the PCCP, stone masonry, and lined canal works.
16
g) Rehabilitation/Improvement of Union-Barcolan Farm to Market RoadDA RFO 212-26-2511-01-26EconomicOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU76,887,915.00 94,341,000.00 76,887,915.00 76,847,915.00 36,127,741.23 81.50 46.99 83.07 81.47 -1.60 252The project is behind schedule due to insufficient manpower and inclement weather conditions.

In response, joint weekly coordination meetings were conducted involving the contractor’s Resident Engineer, the RPCO, and PLGU/PPMIU staff. The management instructed the contractor to expedite lagging work items and to maintain adequate manpower and equipment to prevent further delays.
17
h) Rehabilitation/Improvement of M.H. Del Pilar - Salvacion Farm-to-Market RoadDA RFO 202-04-2611-2-27EconomicOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU215,332,127.14 262,700,000.00 215,332,127.14 197,739,414.42 23,906,171.60 81.97 11.10 28.64 21.78 -6.86 912The project is delayed due to slow progress in the following works: Grouted Riprap (Item 505), Structure Excavation (Item 103(1)a), Reinforcing Steel (Item 404), and Structural Concrete (Item 405).

In response, weekly coordination meetings were conducted by the RPCO, the MLGU, and the contractor's staff, where management directed the contractor to expedite the delayed works. The MPMIU also issued a first warning letter to the contractor.
18
j) Rehabilitation of Oscariz-Burgos-Purok Ni Bulan-Pabil FMRDA RFO 205-07-2603-30-28EconomicOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU188,367,999.98 199,754,000.00 188,367,999.98 188,367,999.98 25,429,680.00 94.30 13.50 6.22 16.48 10.26 901The positive slippage is due to sufficient manpower and equipment deployed for grouted riprap works. However, the contractor failed to deploy key personnel, such as the Project Manager, Project Engineer, and Materials Engineer II.

To address this, the MPMIU issued a clarificatory letter to the contractor to comply with personnel requirements.

The MPMIU Technical Working Group completed the evaluation of the replacement personnel documents, which are now under review by RPCO 02. To prevent negative slippage, the RPCO 02 and MPMIU will conduct a site coordination meeting with the contractor.
19
k) Upgrading of Agusi Farm-to-Market RoadDA RFO 206-04-2606-29-27Economic ServicesOfficial Development Assistance (ODA) - LOANWORLD BANK, DA, P/MLGU134,161,800.00 144,260,000.00 134,161,800.00 134,161,800.00 16,099,416.00 93.00 12.00 10.96 6.29 -4.67 2135The negative slippage is due to insufficient manpower and equipment, frequent equipment breakdowns, inadequate planning, poor workmanship, and bad weather. The required key personnel, specifically the Project Engineer and Materials Engineer, were also not deployed to the project site.

The management conducted a coordination meeting to address the causes of delay and subsequently issued the necessary Suspension Orders. The contractor committed to mobilize additional manpower and equipment, deploy the required personnel, and submit a detailed Catch-Up Plan.
20
2Second Additional Financing for the Philippine Rural Development Project (AF-2)DA RFO 2Projects under AF-2 completed. No additional funding received under AF-2
21
3Adapting Philippine Agriculture to Climate ChangeDA RFO 2No funds downloaded for project implementation in the region as of the reporting period.
22
4Rebuilding agricultural livelihoods affected by multiple cyclones in Cagayan ProvinceFAONo livelihood projects funded for this quarter.
23
5Water District Development Sector Project (WDDSP) - Design, Supply, Construction, Installation, Testing and Commissioning of Caggay Surface Water Treatment PlantMetro Tuguegarao Water District01-31-23
01-31-23
05-19-25
02-21-26
EconomicOfficial Development Assistance (ODA) - LOANAsian Development Bank (ADB) through Local Water Utilities Administration (LWUA)320,000,000.00 332,216,181.30 332,216,181.30 223,050,271.12 197,188,348.49 100.00 59.36 59.51 58.01 -1.50 302The implementation period and loan validity period expired on June 30, 2025 and December 31, 2025, respectively.

LWUA has a pending request for the extension of the implementation period until 31 October 2027 and the loan validity until 31 December 2027.
24
6Supporting Innovation in the Philippine Technical and Vocational Education and Training System (SIPTVETS) Project
TESDA RO210/03/202501/09/2026General Public ServicesOthers - LoanAsian Development Bank (ADB)163,047,336.22163,047,336.22163,047,336.22163,047,336.2270,632,106.05 100.00 43.32 89.7245.5-44.22 446The project is delayed due to the late issuance of the Building Permit (contract commenced March 10, 2025; permit issued December 15, 2025). Progress was further delayed during foundation works due to the contractor’s slow pace of work and poor sequencing of construction activities.
25
7Philippine Digital Infrastructure Project (PDIP) National Broadband ProjectDICT RO2
The project is not implemented in the region.
26
8Philippines Health System Resilience Project (HSRP)DOH
The project is not implemented in the region.
27
9Health System Enhancement to Address and Limit
(HEAL) COVID-19
DOH
The project is not implemented in the region.
28
10Disaster Risk Reduction Enhancement at the Local
Level Technical Assistance Program
DILG
The project is not implemented in the region.
29
11Rural Agro-Enterprise Partnership for Inclusive Development and Growth Project (RAPID Growth)DTI
The project is not implemented in the region.
30
B. PUBLIC PRIVATE PARTNERSHIP (PPP) FUNDED PROJECTS
31
1Baggao Water Supply Project MLGU Baggao/ ME
Sicat Construction, Inc.
General Public ServicesPublic-Private Partnership (PPP) According to LGU Baggao, the identification of suitable sites for groundwater extraction is still ongoing. Previously identified sites were deemed infeasible due to the deep groundwater table.
32
C. LOCALLY-FUNDED PROGRAMS AND PROJECTS
33
a. Agricultural Development Programs and Projects
34
1Tumauini River Multi-Purpose Project (TRMP)NIA06-01-1812-31-26EconomicLocally Funded Project -NIA2,777,795,045.162,777,795,045.16807,824,261.61 736,121,530.15 641,094,002.73 29.08 #REF! 29.94 26.35 -3.59 721 22 The negative slippage is due to the liquidation of indirect costs (supervision costs and employee salaries).

For CY 2025, there are three active contracts: one has been completed, one is ongoing, and one is currently suspended due to typhoons and heavy rainfall.
35
2Calapangan Small Reservoir Irrigation Project (CSRIP)NIA05-08-2312-31-26EconomicLocally Funded Project -NIA1,060,000,000.001,060,000,000.00 1,055,558,000.00 1,017,927,409.77 99.58 60.74 57.48 61.24 3.76 232 16 No funds were allocated for CY 2026.

Positive slippage increased by 1.56 percentage points, from 2.20% in the second quarter to 3.76% this quarter, due to the resumption of contract works, institutional development programs, and procurement of equipment.
36
3Balasig Small Reservoir Irrigation Project (BSRIP) FY 2023- 50M
FY 2024- 5M
FY 2025- 0
NIA05-03-2312-31-26EconomicLocally Funded Project -NIA55,000,000.0055,000,000.0055,000,000.0055,000,000.0054,673,244.56 100.00 99.41 1001000.00 00
37
4Lusod Intergrated National Irrigation Project (LINIP)

FY 2023- 50M
FY 2024- 100M
FY 2025- 200M
FY 2026- 100M
NIA04-07-2312-31-26EconomicLocally Funded Project -NIA450,000,000.00450,000,000.00447,779,000.00 442,985,287.54 321,280,343.41 99.51 71.75 86.00 85.71 -0.29 210 5
38
b. Infrastructure Development Programs/ Projects
39
1CEZA Port Development
40
a) Retroffing and Rehabilitation Works at Port IreneCEZA09-01-2009-30-26
12-31-26
EconomicCorporate FundCEZA400,000,000.00 400,000,000.00 400,000,000.00 395,313,171.02 395,313,171.02 100.00 98.83 100.00 98.91 -1.09 no data no data
41
b) Construction of Data Center / Upgrade of Telecomunication FacilityCEZA12-1-202410-30-26EconomicGAACEZA 150,000,000.00 150,000,000.00 150,000,000.00 98,214,411.56 98,214,411.56 100.00 65.48 65.96 99.00 33.04 8 -
42
c) Repair, Rehabilitation and Maintenance of the Breakwater at Cagayan Economic Zone
43
c.1) Repair, Rehabilitation and Maintenance of the Breakwater at Cagayan Economic Zone - Phase ICEZA6-1-202507-30-26EconomicGAACEZA 156,492,000.00 156,492,000.00 156,492,000.00 156,338,780.95 156,338,780.95 100.00 99.90 96.36 100.00 3.64 no data no dataThe project was completed on June 30, 2026, ahead of time.
44
c.2) Repair, Rehabilitation and Maintenance of the Breakwater at Cagayan Economic Zone - Phase IICEZA07-01-2606-30-27EconomicGAACEZA678,986,907.20678,986,907.20678,986,907.20 181,062,560.68 181,062,560.68 100.00 26.67 22.13 24.06 1.93 17 -
45
d) Dredging and Reclamation at
Port Irene
46
d.1) Dredging and Reclamation Project, Phase IICEZA09-01-2409-30-2026
12-31-26
EconomicGAACEZA228,844,000.00 228,844,000.00 228,844,000.00 220,064,239.08 220,064,239.08 100.00 96.16 99.00 96.36 -2.64 17 2
47
d.2) Dredging and Reclamation at Port Irene (Phase III & IV)CEZA9-1-202511-30-2026
12-31-26
EconomicGAACEZA 743,508,000.00 743,508,000.00 743,508,000.00 181,062,560.68 181,062,560.68 100.00 24.35 22.50 24.36 1.86 17 1
48
2Amulung Bridge and ApproachesDPWH03-12-2406-13-25General Public ServicesLocally Funded ProjectDPWH RO2140,904,816.34 151,000,000.00 151,000,000.00 140,904,816.34 21,135,722.45 100.00 14.00 10090.84-9.16 33 5 The project is delayed pending the approval of Variation Order No. 01.
49
3Bambang By-Pass Road, Nueva Vizcaya (FY 2025)DPWH02-27-2509-24-25General Public ServicesLocally Funded ProjectDPWH RO293,333,935.49 100,000,000.00 100,000,000.00 93,331,896.08 70,056,944.41 100.00 70.06 100.00 100.00 0.00 no data no dataThe project was completed on August 28, 2026.
50
4Tuguegarao-Enrile Bridge and Approaches
51
Construction of Bypass and
Diversion Roads Tuguegarao-
Enrile Diversion Road
(Including Tuguegarao-Enrile
Bridge and Approaches),
Phase 1
DPWH RO2
09-20-202311-23-2024General Public ServicesLocally Funded ProjectDPWH R02

186,874,492.51200,000,000.00200,000,000.00 186,766,374.69 138,863,808.84 100.00 69.43 100.00 100.00 0.00 no datano dataCompleted as of July 15, 2025.
52
Phase 3
DPWH RO2
04-11-202404-10-2025General Public ServicesLocally Funded ProjectDPWH R02

237,863,500.76280,000,000.00280,000,000.00 237,833,200.52 177,264,240.60 100.00 63.31 100.00 96.18 -3.82 0.000.00The project is delayed due to unfavorable weather conditions. Contract Time Extension No. 4 is currently in process; if approved, the revised expiry date will be September 9, 2026.
53
Flood Control Projects
54
5Abulug Flood Control Projects
55
Construction of Canayun Flood Control Structure along Abulug-Apayao River, Barangay Canayun, Abulug, CagayanDPWH Cagayan 2nd DEO02-21-2510-19-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,350,935.37100,000,000.0096,500,000.0096,350,935.37 96,350,935.37 96.50 99.85 100 100.00 0.00 no data no dataCompleted as of July 25, 2025.
56
Construction of Dugo Flood Control along Abulug River, Package 2, Barangay Dugo, Abulug, CagayanDPWH Cagayan 2nd DEO03-07-2511-2-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,349,581.49100,000,000.0096,500,000.0096,349,581.49 86,716,921.64 96.50 89.86 100 100.00 0.00 no data no dataCompleted as of June 1, 2026.
57
Construction of Dugo Flood Control Structure along Abulug River, Barangay Dugo, Abulug, CagayanDPWH Cagayan 2nd DEO03-07-2511-2-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,349,144.71100,000,000.0096,500,000.0096,349,144.71 86,715,434.46 96.50 89.86 100 100.00 0.00 no data no dataCompleted as of June 1, 2026.
58
Construction of Libertad Flood Control along Abulug-Apayao River, Package 2, Barangay Libertad, Abulug, CagayanDPWH Cagayan 2nd DEO02-27-2510-25-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,349,531.70100,000,000.0096,500,000.0096,349,531.70 86,714,578.53 96.50 89.86 100 100.00 0.00 no data no dataCompleted as of July 15, 2025.
59
Construction of Libertad Flood Control Structure along Abulug-Apayao River, Package 1, Barangay Libertad, Abulug, CagayanDPWH Cagayan 2nd DEO02-21-2510-19-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,349,818.22100,000,000.0096,500,000.0096,349,818.22 96,349,818.22 96.50 99.84 100 100.00 0.00 no data no dataCompleted as of July 15, 2025.
60
Construction of Santo Tomas Flood Control along Abulug-Apayao River, Package 2, Barangay Sto. Tomas, Abulug, CagayanDPWH Cagayan 2nd DEO02-21-2510-19-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

95,535,102.35100,000,000.0096,500,000.0095,535,102.35 77,383,432.91 96.50 80.19 100 100.00 0.00 no data no dataCompleted as of November 28, 2025.
61
Construction of Bank Protection Structure along Guiddam River, Guiddam, Abulug,CagayanDPWH Cagayan 2nd DEO04-11-259-27-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

16,688,705.7517,652,000.0017,034,180.0016,688,705.75 15,186,723.95 96.50 89.15 100 100.00 0.00 no data no dataCompleted as of July 15, 2025.
62
Construction of Canayun Flood Control along Abulug-Apayao River, Package 2, Barangay Canayun, Abulug, CagayanDPWH Cagayan 2nd DEO02-21-2510-19-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,395,395.99100,000,000.0096,500,000.0096,395,395.9977,136,039.10 96.50 79.93100 100.00 0.00 no data no dataCompleted as of May 15, 2026.
63
Construction of Abulug River Revetment 9 along Abulug River, Dugo, Abulug, CagayanDPWH Cagayan 2nd DEO06-11-252-6-26General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,299,249.05100,000,000.0096,500,000.0096,299,249.05 86,669,324.15 96.50 89.81 100 100.00 0.00 no data no dataCompleted as of January 31, 2026.
64
6Construction of Alannay Flood Control Structure along Zinundungan River, Lasam, CagayanDPWH Cagayan 2nd DEO03-07-259-16-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

48,935,000.0150,000,000.0049,000,000.0048,935,000.01 21,657,949.42 98.00 44.20 100 100.00 0.00 no data no dataCompleted as of May 15, 2026.
65
7Construction of Flood Control Structure along Cagayan River, Package 2, Barangay Aggunetan, Lasam, CagayanDPWH Cagayan 2nd DEO02-21-2510-19-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

96,264,699.87100,000,000.0096,500,000.0096,264,699.87 86,638,229.88 96.50 89.78 100 100.00 0.00 no data no dataCompleted as of March 31, 2026.
66
8Construction of Sicatna River Control along Chico River, Package 1, Barangay Sicatna, Piat, CagayanDPWH Cagayan 2nd DEO02-21-259-28-25General Public ServicesLocally Funded Project - Flood Mitigation Facility

DPWH-CSDEO

72,274,996.9675,000,000.0072,375,000.0072,274,996.96 59,551,588.43 96.50 82.28 100 100.00 0.00 no data no dataCompleted as of March 31, 2026.
67
9Construction of Tuguegarao Circumferential Dike Road, Tuguegarao City, Cagayan - Package 4 (FY2024)DPWH RO203-12-246-23-25General Public ServicesLFPDPWH RO2183,025,826.31200,000,000.00200,000,000.00183,025,826.31 173,876,124.46 100.00 86.94 100 100.00 0.00 no data no dataCompleted as of September 02, 2025.
68
Phase 3(FY 2025)DPWH RO203-17-259-23-25General Public ServicesLFPDPWH RO277,098,486.6180,000,000.0080,000,000.0077,098,486.6111,564,772.99 100.00 14.46100 96.40 -3.60 no data no dataThe project is subject to liquidated damages.
69
10Health Facilities Enhancement Program (HFEP, FY 2022-2026)
70
a) HFEP 2022 LGU/ CVCHD20222026SocialLocally Funded ProjectDOH-CVCHD5,000,000.005,000,000.005,000,000.005,000,000.003,476,751.73 100.00 69.54 80.00 80.00 0.00 no data no dataOnly one project (Sto Tomas Super Health Center) is under implementation.
71
b) HFEP 2023LGU/ CVCHD20232026SocialLocally Funded ProjectDOH-CVCHD56,000,000.0056,000,000.0056,000,000.0056,000,000.0010,200,000.00 100.00 18.21 75.8975.890.00 no data no dataOf the 110 projects reported, 107 were already completed, two (Nagtipunan and Quirino Provincial Medical Center) are ongoing, while the funding for one project (Diura BHS) was reverted to the National Treasury.
72
c) HFEP 2024LGU/ CVCHD20242026SocialLocally Funded ProjectDOH-CVCHD58,166,843.1358,500,000.0058,440,000.0058,335,000.0028,642,500.00 99.90 49.01 66.4866.480.00 no data no dataOf the 44 projects reported, 19 were completed and 25 are ongoing.
73
c) HFEP 2025LGU/ CVCHD20252026SocialLocally Funded ProjectDOH-CVCHD9,894,845.7113,000,000.0012,740,000.009,894,821.440.00 98.00 - 1001000.00 no data no dataAs of this reporting period, all 3 projects reported under the HFEP 2025 were already completed with 1 project (Completion/ Upgrading of Itbayat Rural health Unit) scheduled for final inspection.
74
11DOT-DPWH Convergence Program (2024-2025)DPWH2-15-202312-05-2024EconomicLocally Funded ProjectDPWH RO2 401,141,500.58 370,000,000.00 362,635,000.00 354,635,924.42 170,315,979.34 98.01 46.97 64.86 54.97 -9.89 69 1
75
12Construction/ Improvement of Access Roads Leading to Trades, Industries and Economic Zones (Roads Leveraging Linkages for Industry and Trade Infrastructure Program - ROLL-IT)DPWH02-15-202302-06-2025EconomicLocally Funded ProjectDPWH RO2 249,624,806.56 238,370,000.00 234,142,600.00 230,024,935.96 87,728,002.09 98.23 37.47 91.29 82.32 -8.97 121 9
76
13Alicia-Angadanan-San Guillermo-Cauayan City-Naguilian Alternate Route, San Guillermo

Package 1, Isabela (P00801533LZ)
DPWH RO2
03-31-2511-26-25General Public ServicesLocally Funded ProjectDPWH RO2115,523,684.02 122,900,000.00 122,900,000.00 115,523,684.02 46,229,704.82 100.00 37.62 100.00 80.69 -19.31 no data no dataThe project has been suspended since May 5, 2026, due to an obstruction at the project site (ISELCO post).
77
14Aritao-Quirino Road
78
Aritao-Quirino Road
- Package 1, Quirino Aglipay, Quirino (P00914998LZ-CW1)
DPWH RO2
03-17-259-20-25General Public ServicesLFPDPWH RO272,304,702.69 75,000,000.00 75,000,000.00 72,304,702.69 43,968,468.31 100.00 58.62 100.00 100.00 0.00 no data no dataThe project was completed on November 29, 2025.
79
Aritao-Quirino Road, Nueva Vizcaya (Phase II)
DPWH RO2
03-17-259-23-25General Public ServicesLocally Funded ProjectDPWH RO276,019,992.24 78,881,000.00 78,881,000.00 76,019,992.24 43,753,656.52 100.00 55.47 100.00 100.00 0.00 no data no dataThe project was completed on August 14, 2026.
80
Cagayan Bridge Projects for Economic Development
81
16Tuguegarao - Solana Bridge and Approaches
82
Package 2, FY 2024DPWH04-11-2404-10-25
03-25-26
General Public ServicesLocally Funded ProjectDPWH RO2269,862,556.29280,000,000.00280,000,000.00269,862,556.29 143,760,067.04 100.00 51.34 100 100.00 0.00 no datano dataCompleted as of May 30, 2026.
83
Tuguegarao - Solana Bridge and Approaches, Package 1, 2025DPWH04-10-2503-05-26
06-19-26
General Public ServicesLocally Funded ProjectDPWH RO2141,706,353.54 150,000,000.00 150,000,000.00 141,706,353.54 57,155,081.14 100.00 38.10 100.00 67.97 -32.03 no datano dataThe project is delayed due to high water elevation coming from upstream. Contract Time Extension No. 13 (due to unfavorable weather conditions) is currently in process; if approved, the revised expiry date will be October 2, 2026. Additionally, Variation Order No. 1 is in process.
84
Package 2, FY 2025DPWH04-10-2503-05-26
06-19-26
General Public ServicesLocally Funded ProjectDPWH RO2141,706,325.34 150,000,000.00 150,000,000.00 141,706,325.34 21,255,948.80 100.00 14.17 100.00 62.09 -37.91 no datano dataThe project is delayed due to high water elevation coming from upstream. Contract Time Extension No. 13 (due to unfavorable weather conditions) is currently in process; if approved, the revised expiry date will be October 2, 2026. Additionally, Variation Order No. 1 is in process.
85
Construction of By-Pass and Diversion Roads - Tuguegarao-Solana Diversion Road (Tuguegarao- Solana Bridge) (Sta. 849.513 - Sta. 2+515.463) (26B00004) DPWH08-03-2605-04-27General Public ServicesLocally Funded ProjectDPWH RO288,761,191.6592,500,000.0092,500,000.0088,761,191.65 - 100.00 - 18.93 0.51 -18.42 no datano dataThe project is delayed due to Road Right-of-Way (RROW) issues. Negotiations with the Project-Affected Person (PAP) are currently ongoing.
86
Construction of Bypass and Diversion Roads - Tuguegarao-Solana Diversion Road (Tuguegarao- Solana Bridge) (Sta. 0+849.513 - Sta. 2+515.463) (26B00007)DPWH08-03-2603-07-27General Public ServicesLocally Funded ProjectDPWH RO246,783,622.4449,000,000.0049,000,000.0046,783,622.44 - 100.00 - 21.75 0.73 -21.02 no datano dataThe project is delayed due to RROW issues. Negotiations with the PAP are currently ongoing.
87
17Pinacanauan Bridge 2
88
Package 2, FY 2023
DPWH RO2
05-25-2311-18-24General Public ServicesLocally Funded ProjectDPWH RO2285,919,061.33300,000,000.00300,000,000.00285,919,061.33 214,872,200.26 100.00 71.62 100 78.28 -21.72 no datano dataThe contract was terminated effective July 13, 2026.
89
Package 2, FY 2024
DPWH RO2
04-11-202404-10-2025General Public ServicesLocally Funded ProjectDPWH RO2264,489,713.09280,000,000.00280,000,000.00264,489,713.09 70,205,648.58 100.00 25.07 100 63.54 -36.46 no datano dataThe project has been suspended since March 16, 2026, awaiting the completion of prerequisite phases.
90
FY 2025
DPWH RO2
04-10-202503-04-2026General Public ServicesLocally Funded ProjectDPWH RO2139,598,578.83150,000,000.00150,000,000.00 139,538,120.02 80,586,738.37 100.00 53.72 100.00 78.48 -21.52 no datano dataThe project is delayed due to unfavorable weather conditions. Contract Time Extension No. 8 is currently in process; if approved, the revised expiry date will be October 13, 2026.
91
Package 2, FY 2025
DPWH RO2
12-05-202504-24-2027General Public Services
Locally Funded Project -
DPWH RO3264,010,208.54300,000,000.00300,000,000.00 264,010,208.54 - 100.00 - 58.21 - -58.21 no datano dataThe project has been suspended since February 12, 2026, pending the completion of prerequisite phases and resolution of RROW issues at Approach B (Capatan side).
92
18Alcala Bridge
93
Construction of Bypass and
Diversion Roads – Alcala-
Santo Niño-Lasam Road,
Package 1 (FY2023)
DPWH RO2
09-21-202305-27-2024 03-03-26General Public ServicesLocally Funded ProjectDPWH RO266,811,501.2775,000,000.0075,000,000.00 66,783,471.73 59,822,424.71 100.00 79.76 100.00 96.85 -3.15 no data no dataThe project is currently suspended due to plan revisions involving the redesign of structural members at Pier 1. This redesign is necessary to accommodate the relocation of a bored pile due to an obstruction caused by an unretrieved steel casing from a collapsed borehole.
94
Package 2, FY 2023
DPWH RO2
09-27-202310-03-2024General Public ServicesLocally Funded ProjectDPWH RO2113,267,468.05120,000,000.00120,000,000.00113,267,468.05 36,602,119.06 100.00 30.50 100.00 47.17 -52.83 no data no dataWork is temporarily stopped. The contractor submitted a request for Work Suspension Order (WSO) due to the AMLC's freeze order on its bank accounts. The request is under review/evaluation.
95
Package 1, FY 2024
DPWH RO2
03-12-202411-19-2025General Public ServicesLocally Funded ProjectDPWH-RO2

192,891,064.09200,000,000.00200,000,000.00192,891,064.09 45,228,359.73 100.00 22.61 100.00 39.72 -60.28 no data no dataThe project has been suspended since June 1, 2026, due to plan revisions necessitated by an unforeseen obstruction (wooden log) at Pier 3. Additionally, the project is affected by the redesign of Pier 1 under Contract ID No. 23B00066.
96
Package 2, FY 2024
DPWH RO2
02-14-202509-28-2025General Public ServicesLocally Funded ProjectDPWH RO228,850,109.3730,000,000.0030,000,000.0028,850,109.37 4,327,516.41 100.00 14.43 100.00 4.88 -95.12 no data no dataThe project has been suspended since March 3, 2025, pending the completion of its prerequisite phases.
97
Construction of Bypass and
Diversion Roads – Alcala-
Santo Niño-Lasam Road,
Package 1 (25B00041)
DPWH RO2
04-03-2502-07-26General Public ServicesLocally Funded ProjectDPWH RO270,203,914.50 75,000,000.00 75,000,000.00 70,203,914.50 10,530,587.18 100.00 14.04 100.00 0.15 -99.85 no data no dataThe project has been suspended since April 18, 2025, pending the completion of other prerequisite phases.
98
Daang Maharlika Improvement: Bridges
99
19Replacement of Permanent Weak Bridge - Minanga Br. (B01129LZ) along Maharlika Highway Tumauini, Isabela (FY2025)
DPWH RO2
03-07-2506-27-26General Public ServicesLocally Funded ProjectDPWH RO2241,150,001.36 250,000,000.00 250,000,000.00 241,150,001.36 36,172,500.20 100.00 14.47 99.86 23.96 -75.90 no data no dataThe project is delayed due to frequent drilling equipment breakdowns and unfavorable weather conditions.
100
20Widening of Permanent Bridges - Malalam Br. (B01121LZ) Along Maharlika Highway Ilagan City, Isabela (FY2025)
DPWH RO2
03-17-2505-10-26General Public ServicesLocally Funded ProjectDPWH RO2253,509,603.37 271,409,000.00 271,409,000.00 253,509,603.37 190,977,722.04 100.00 70.37 100.00 100.00 0.00 no data no dataThe project was completed on August 30, 2026