Rotating STG BB II8,08 days4/9/26 7:304/17/26 9:30
3
Shutdown0 days4/9/26 7:304/9/26 7:30
4
BOILER & STEAM SYSTEM8,08 days4/9/26 7:304/17/26 9:30
5
Start Work0 hrs4/9/26 7:304/9/26 7:30
6
F6P-2343RMA : COAL MILL 2ACek dan service5,65 days4/9/26 7:304/14/26 23:00
7
Persiapan pengamanan & pendinginan coal mill8 hrs4/9/26 7:304/9/26 15:30100
8
Buka MH utama & all Hand hole bushing rod.2 hrs4/9/26 15:304/9/26 17:30100
9
Pembersihan area dalam coal mill4 hrs4/9/26 17:304/10/26 11:00100
10
Pengecekan parts dalam coal mill (gap stress-unstress, tebal tyre & table dll)8 hrs4/10/26 11:004/10/26 19:00100
11
Ganti oli grinding roller24 hrs4/10/26 19:004/11/26 19:00100
12
Ganti oli hidrolik (pembersihan tangki hidrolik)12 hrs4/11/26 19:004/12/26 7:00100
13
Ganti oli main gear box & cleaning filter LO main gear box12 hrs4/12/26 7:004/12/26 19:00100
14
Ganti oli gear box classifier12 hrs4/12/26 19:004/13/26 7:00100
15
Repack all tierod & ganti bushing jika kondisi aus.12 hrs4/13/26 7:004/13/26 19:00100
16
Setting gap stress/unstress sesuai design manufaktur BPEG12 hrs4/13/26 19:004/14/26 7:00100
17
Pengecekan akhir dalam coal mill & area scrapper serta tutup semua MH/Hand hole8 hrs4/14/26 7:004/14/26 15:00
18
Penetran test all tierod (bila dibutuhkan)8 hrs4/14/26 15:004/14/26 23:00100
19
F6P-2343RMB : COAL MILL 2BCek dan service5,58 days4/9/26 7:304/14/26 21:30
20
Persiapan pengamanan & pendinginan coal mill8 hrs4/9/26 7:304/9/26 15:30100
21
Buka MH utama & all Hand hole bushing rod.2 hrs4/9/26 15:304/9/26 17:30100
22
Pembersihan area dalam coal mill4 hrs4/9/26 17:304/9/26 21:30100
23
Pengecekan parts dalam coal mill (gap stress-unstress, tebal tyre & table dll)8 hrs4/9/26 21:304/10/26 5:3050
24
Ganti oli grinding roller24 hrs4/10/26 5:304/11/26 5:30100
25
Ganti oli hidrolik (pembersihan tangki hidrolik)12 hrs4/11/26 5:304/11/26 17:30100
26
Ganti oli main gear box & cleaning filter LO main gear box24 hrs4/11/26 17:304/12/26 17:30100
27
Ganti oli gear box classifier12 hrs4/12/26 17:304/13/26 5:30100
28
Repack all tierod & ganti bushing jika kondisi aus.12 hrs4/13/26 5:304/13/26 17:30100
29
Setting gap stress/unstress sesuai design manufaktur BPEG12 hrs4/13/26 17:304/14/26 5:30100
30
Pengecekan akhir dalam coal mill & area scrapper serta tutup semua MH/Hand hole8 hrs4/14/26 5:304/14/26 13:30
31
Penetran test all tierod (bila dibutuhkan)8 hrs4/14/26 13:304/14/26 21:30100
32
F6P-2342WFA : COAL FEEDER 2APenggantian Belt Coalfeeder 2342WFA1,31 days4/9/26 7:304/10/26 15:00
33
Persiapan pengamanan (off breaker)1 hr4/9/26 7:304/9/26 8:30100
34
Posisikan sambungan belt kearah MH1 hr4/9/26 8:304/9/26 9:30100
35
Buka MH timur & barat1 hr4/9/26 9:304/9/26 10:30100
36
kendorkan adjuster belt0,5 hrs4/9/26 10:304/9/26 11:00100
37
Buka sambungan belt4 hrs4/9/26 11:004/9/26 17:00100
38
Tarik belt bekas keluar dari drive & tail pulley1 hr4/9/26 17:004/9/26 18:00100
39
check tail & drive pulley coal feeder1 hr4/9/26 19:004/9/26 20:00100
40
check bearing scrapper (tail & drive / out board)1 hr4/9/26 20:004/10/26 8:00100
41
Ganti oli housing bearing gear box belt coal feeder & scrapper.1 hr4/10/26 8:004/10/26 9:00100
42
Pasang belt coal feeder baru1 hr4/10/26 9:004/10/26 10:00100
43
adjust belt1 hr4/10/26 10:004/10/26 11:00100
44
kalibrasi belt1 hr4/10/26 11:004/10/26 14:00100
45
Tutup kembali cover MH barat & timur1 hr4/10/26 14:004/10/26 15:0050
46
F6P-2342WFB : COAL FEEDER 2BCek dan service1,96 days4/10/26 15:004/12/26 14:00
47
Persiapan pengamanan (off breaker)Service Coalfeeder 2342WFB1 hr4/10/26 15:004/10/26 16:00100
48
Buka MH timur & barat2 hrs4/10/26 16:004/10/26 18:00100
49
Posisikan sambungan belt kearah MH2 hrs4/10/26 19:004/11/26 8:00100
50
Buka sambungan belt2 hrs4/11/26 8:004/11/26 10:00100
51
Tarik belt bekas keluar dari drive & tail pulley1 hr4/11/26 10:004/11/26 11:00100
52
Ganti tail & drive pulley coal feeder4 hrs4/11/26 11:004/11/26 17:00100
53
Ganti bearing scrapper (tail & drive / out board)2 hrs4/11/26 17:004/11/26 20:00100
54
Ganti oli housing bearing gear box belt coal feeder & scrapper.1 hr4/11/26 20:004/12/26 8:00100
55
Pasang belt coal feeder baru2 hrs4/12/26 8:004/12/26 10:00100
56
Tutup kembali cover MH barat & timur2 hrs4/12/26 10:004/12/26 14:00
57
F6P-2418GBA : MILL SEAL AIR FAN (MSAF) 2ACek dan service4,35 days4/9/26 7:304/13/26 16:00
58
Persiapan pengamanan (Matikan breaker,tutup damper dll)1 hr4/9/26 7:304/9/26 8:30100
59
Buka cover coupling motor-fan.1 hr4/9/26 8:304/9/26 9:30100
60
Buka spacer coupling fan-motor.2 hrs4/9/26 9:304/9/26 11:30100
61
Cek alligment sebelum over haul & ukur jarak DBSE (hub to hub)2 hrs4/9/26 13:304/9/26 15:30100
62
Buka hub coupling dengan tracker (bila perlu dipanasi)8 hrs4/9/26 15:304/9/26 23:30100
63
Buka housing bearing & bearing in board dengan bantuan chain block.8,5 hrs4/9/26 23:304/10/26 8:00100
64
Buka housing bearing & bearing out board dengan bantuan chain block.8 hrs4/10/26 8:004/10/26 16:00100
65
Bersihkan shaft area bearing in & out board.4 hrs4/10/26 16:004/10/26 20:00100
66
Buka MH immpeller untuk pengecekan & cleaning.8 hrs4/10/26 20:004/11/26 4:00100
67
Cleaning immpeller.8 hrs4/11/26 4:004/11/26 12:00100
68
Pasang bearing baru (6312) in & out board dengan heater bearing8,5 hrs4/11/26 12:004/11/26 20:30
69
Pasang kembali housing bearing in board8 hrs4/11/26 20:304/12/26 4:30
70
Pasang kembali housing bearing out board8 hrs4/12/26 4:304/12/26 12:30
71
Pasang hub coupling dengan dipanasi.8 hrs4/12/26 12:304/12/26 20:30
72
Alligment motor-pompa serta ukur djarak hub to hub (DBSE)2 hrs4/13/26 7:304/13/26 9:30
73
Pasang spacer pompa diikat sesuai ukuan torsi & tutup cover pelindung coupling.6,5 hrs4/13/26 9:304/13/26 16:00
74
F6P-2418GBB : MILL SEAL AIR FAN (MSAF) 2BService bearing6,33 days4/9/26 7:304/15/26 15:30
75
Persiapan pengamanan (Matikan breaker,tutup damper dll)1 hr4/9/26 7:304/9/26 8:30100
76
Buka cover coupling motor-fan.1 hr4/11/26 13:304/11/26 14:30
77
Buka spacer coupling fan-motor.2 hrs4/11/26 14:304/11/26 16:30
78
Cek alligment sebelum over haul & ukur jarak DBSE (hub to hub)2 hrs4/11/26 16:304/11/26 19:30
79
Buka hub coupling dengan tracker (bila perlu dipanasi)8 hrs4/11/26 19:304/12/26 3:30
80
Buka housing bearing & bearing in board dengan bantuan chain block.8 hrs4/12/26 3:304/12/26 11:30
81
Buka housing bearing & bearing out board dengan bantuan chain block.8 hrs4/12/26 11:304/12/26 19:30
82
Bersihkan shaft area bearing in & out board.4 hrs4/12/26 19:304/12/26 23:30
83
Buka MH immpeller untuk pengecekan & cleaning.8 hrs4/12/26 23:304/13/26 7:30100
84
Cleaning immpeller.8 hrs4/13/26 7:304/13/26 15:30100
85
Pasang bearing baru (6312) in & out board dengan heater bearing8 hrs4/13/26 15:304/13/26 23:30
86
Pasang kembali housing bearing in board8 hrs4/13/26 23:304/14/26 7:30
87
Pasang kembali housing bearing out board8 hrs4/14/26 7:304/14/26 15:30
88
Pasang hub coupling dengan dipanasi.8 hrs4/14/26 15:304/14/26 23:30
89
Alligment motor-pompa serta ukur djarak hub to hub (DBSE)2 hrs4/15/26 7:304/15/26 9:30
90
Pasang spacer pompa diikat sesuai ukuan torsi & tutup cover pelindung coupling.6 hrs4/15/26 9:304/15/26 15:30
91
F6P-2701GB : IGNITER AIR FAN (IAF) 1Cek dan service5,42 days4/9/26 7:304/14/26 17:30
92
Persiapan pengamanan (Matikan breaker,tutup damper dll)1 hr4/9/26 7:304/9/26 8:30100
93
Buka cover coupling motor-fan.1 hr4/9/26 8:304/9/26 9:30100
94
Buka spacer coupling fan-motor.2 hrs4/9/26 9:304/9/26 11:30100
95
Cek alligment sebelum over haul & ukur jarak DBSE (hub to hub)2 hrs4/9/26 13:304/9/26 15:30100
96
Buka expantion in let & expantion out let8 hrs4/9/26 15:304/9/26 23:30100
97
Buka cover top blower & Hub coupling fan site12 hrs4/9/26 23:304/10/26 11:30100
98
Buka baut pondasi housing bearing keduanya.4 hrs4/10/26 11:304/10/26 15:30100
99
Angkat rotor dengan ke dua housing bearing & letakkan pada stagger/tools yang telah disediakan.8 hrs4/10/26 15:304/10/26 23:30100
100
Buka housing bearing & bearing 62108 hrs4/10/26 23:304/11/26 7:30100