| D | E | F | G | H | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Task Name | Text1 | Duration | Start | Finish | % Progres | ||||||||||||||
2 | Rotating STG BB II | 8,08 days | 4/9/26 7:30 | 4/17/26 9:30 | ||||||||||||||||
3 | Shutdown | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | ||||||||||||||||
4 | BOILER & STEAM SYSTEM | 8,08 days | 4/9/26 7:30 | 4/17/26 9:30 | ||||||||||||||||
5 | Start Work | 0 hrs | 4/9/26 7:30 | 4/9/26 7:30 | ||||||||||||||||
6 | F6P-2343RMA : COAL MILL 2A | Cek dan service | 5,65 days | 4/9/26 7:30 | 4/14/26 23:00 | |||||||||||||||
7 | Persiapan pengamanan & pendinginan coal mill | 8 hrs | 4/9/26 7:30 | 4/9/26 15:30 | 100 | |||||||||||||||
8 | Buka MH utama & all Hand hole bushing rod. | 2 hrs | 4/9/26 15:30 | 4/9/26 17:30 | 100 | |||||||||||||||
9 | Pembersihan area dalam coal mill | 4 hrs | 4/9/26 17:30 | 4/10/26 11:00 | 100 | |||||||||||||||
10 | Pengecekan parts dalam coal mill (gap stress-unstress, tebal tyre & table dll) | 8 hrs | 4/10/26 11:00 | 4/10/26 19:00 | 100 | |||||||||||||||
11 | Ganti oli grinding roller | 24 hrs | 4/10/26 19:00 | 4/11/26 19:00 | 100 | |||||||||||||||
12 | Ganti oli hidrolik (pembersihan tangki hidrolik) | 12 hrs | 4/11/26 19:00 | 4/12/26 7:00 | 100 | |||||||||||||||
13 | Ganti oli main gear box & cleaning filter LO main gear box | 12 hrs | 4/12/26 7:00 | 4/12/26 19:00 | 100 | |||||||||||||||
14 | Ganti oli gear box classifier | 12 hrs | 4/12/26 19:00 | 4/13/26 7:00 | 100 | |||||||||||||||
15 | Repack all tierod & ganti bushing jika kondisi aus. | 12 hrs | 4/13/26 7:00 | 4/13/26 19:00 | 100 | |||||||||||||||
16 | Setting gap stress/unstress sesuai design manufaktur BPEG | 12 hrs | 4/13/26 19:00 | 4/14/26 7:00 | 100 | |||||||||||||||
17 | Pengecekan akhir dalam coal mill & area scrapper serta tutup semua MH/Hand hole | 8 hrs | 4/14/26 7:00 | 4/14/26 15:00 | ||||||||||||||||
18 | Penetran test all tierod (bila dibutuhkan) | 8 hrs | 4/14/26 15:00 | 4/14/26 23:00 | 100 | |||||||||||||||
19 | F6P-2343RMB : COAL MILL 2B | Cek dan service | 5,58 days | 4/9/26 7:30 | 4/14/26 21:30 | |||||||||||||||
20 | Persiapan pengamanan & pendinginan coal mill | 8 hrs | 4/9/26 7:30 | 4/9/26 15:30 | 100 | |||||||||||||||
21 | Buka MH utama & all Hand hole bushing rod. | 2 hrs | 4/9/26 15:30 | 4/9/26 17:30 | 100 | |||||||||||||||
22 | Pembersihan area dalam coal mill | 4 hrs | 4/9/26 17:30 | 4/9/26 21:30 | 100 | |||||||||||||||
23 | Pengecekan parts dalam coal mill (gap stress-unstress, tebal tyre & table dll) | 8 hrs | 4/9/26 21:30 | 4/10/26 5:30 | 50 | |||||||||||||||
24 | Ganti oli grinding roller | 24 hrs | 4/10/26 5:30 | 4/11/26 5:30 | 100 | |||||||||||||||
25 | Ganti oli hidrolik (pembersihan tangki hidrolik) | 12 hrs | 4/11/26 5:30 | 4/11/26 17:30 | 100 | |||||||||||||||
26 | Ganti oli main gear box & cleaning filter LO main gear box | 24 hrs | 4/11/26 17:30 | 4/12/26 17:30 | 100 | |||||||||||||||
27 | Ganti oli gear box classifier | 12 hrs | 4/12/26 17:30 | 4/13/26 5:30 | 100 | |||||||||||||||
28 | Repack all tierod & ganti bushing jika kondisi aus. | 12 hrs | 4/13/26 5:30 | 4/13/26 17:30 | 100 | |||||||||||||||
29 | Setting gap stress/unstress sesuai design manufaktur BPEG | 12 hrs | 4/13/26 17:30 | 4/14/26 5:30 | 100 | |||||||||||||||
30 | Pengecekan akhir dalam coal mill & area scrapper serta tutup semua MH/Hand hole | 8 hrs | 4/14/26 5:30 | 4/14/26 13:30 | ||||||||||||||||
31 | Penetran test all tierod (bila dibutuhkan) | 8 hrs | 4/14/26 13:30 | 4/14/26 21:30 | 100 | |||||||||||||||
32 | F6P-2342WFA : COAL FEEDER 2A | Penggantian Belt Coalfeeder 2342WFA | 1,31 days | 4/9/26 7:30 | 4/10/26 15:00 | |||||||||||||||
33 | Persiapan pengamanan (off breaker) | 1 hr | 4/9/26 7:30 | 4/9/26 8:30 | 100 | |||||||||||||||
34 | Posisikan sambungan belt kearah MH | 1 hr | 4/9/26 8:30 | 4/9/26 9:30 | 100 | |||||||||||||||
35 | Buka MH timur & barat | 1 hr | 4/9/26 9:30 | 4/9/26 10:30 | 100 | |||||||||||||||
36 | kendorkan adjuster belt | 0,5 hrs | 4/9/26 10:30 | 4/9/26 11:00 | 100 | |||||||||||||||
37 | Buka sambungan belt | 4 hrs | 4/9/26 11:00 | 4/9/26 17:00 | 100 | |||||||||||||||
38 | Tarik belt bekas keluar dari drive & tail pulley | 1 hr | 4/9/26 17:00 | 4/9/26 18:00 | 100 | |||||||||||||||
39 | check tail & drive pulley coal feeder | 1 hr | 4/9/26 19:00 | 4/9/26 20:00 | 100 | |||||||||||||||
40 | check bearing scrapper (tail & drive / out board) | 1 hr | 4/9/26 20:00 | 4/10/26 8:00 | 100 | |||||||||||||||
41 | Ganti oli housing bearing gear box belt coal feeder & scrapper. | 1 hr | 4/10/26 8:00 | 4/10/26 9:00 | 100 | |||||||||||||||
42 | Pasang belt coal feeder baru | 1 hr | 4/10/26 9:00 | 4/10/26 10:00 | 100 | |||||||||||||||
43 | adjust belt | 1 hr | 4/10/26 10:00 | 4/10/26 11:00 | 100 | |||||||||||||||
44 | kalibrasi belt | 1 hr | 4/10/26 11:00 | 4/10/26 14:00 | 100 | |||||||||||||||
45 | Tutup kembali cover MH barat & timur | 1 hr | 4/10/26 14:00 | 4/10/26 15:00 | 50 | |||||||||||||||
46 | F6P-2342WFB : COAL FEEDER 2B | Cek dan service | 1,96 days | 4/10/26 15:00 | 4/12/26 14:00 | |||||||||||||||
47 | Persiapan pengamanan (off breaker) | Service Coalfeeder 2342WFB | 1 hr | 4/10/26 15:00 | 4/10/26 16:00 | 100 | ||||||||||||||
48 | Buka MH timur & barat | 2 hrs | 4/10/26 16:00 | 4/10/26 18:00 | 100 | |||||||||||||||
49 | Posisikan sambungan belt kearah MH | 2 hrs | 4/10/26 19:00 | 4/11/26 8:00 | 100 | |||||||||||||||
50 | Buka sambungan belt | 2 hrs | 4/11/26 8:00 | 4/11/26 10:00 | 100 | |||||||||||||||
51 | Tarik belt bekas keluar dari drive & tail pulley | 1 hr | 4/11/26 10:00 | 4/11/26 11:00 | 100 | |||||||||||||||
52 | Ganti tail & drive pulley coal feeder | 4 hrs | 4/11/26 11:00 | 4/11/26 17:00 | 100 | |||||||||||||||
53 | Ganti bearing scrapper (tail & drive / out board) | 2 hrs | 4/11/26 17:00 | 4/11/26 20:00 | 100 | |||||||||||||||
54 | Ganti oli housing bearing gear box belt coal feeder & scrapper. | 1 hr | 4/11/26 20:00 | 4/12/26 8:00 | 100 | |||||||||||||||
55 | Pasang belt coal feeder baru | 2 hrs | 4/12/26 8:00 | 4/12/26 10:00 | 100 | |||||||||||||||
56 | Tutup kembali cover MH barat & timur | 2 hrs | 4/12/26 10:00 | 4/12/26 14:00 | ||||||||||||||||
57 | F6P-2418GBA : MILL SEAL AIR FAN (MSAF) 2A | Cek dan service | 4,35 days | 4/9/26 7:30 | 4/13/26 16:00 | |||||||||||||||
58 | Persiapan pengamanan (Matikan breaker,tutup damper dll) | 1 hr | 4/9/26 7:30 | 4/9/26 8:30 | 100 | |||||||||||||||
59 | Buka cover coupling motor-fan. | 1 hr | 4/9/26 8:30 | 4/9/26 9:30 | 100 | |||||||||||||||
60 | Buka spacer coupling fan-motor. | 2 hrs | 4/9/26 9:30 | 4/9/26 11:30 | 100 | |||||||||||||||
61 | Cek alligment sebelum over haul & ukur jarak DBSE (hub to hub) | 2 hrs | 4/9/26 13:30 | 4/9/26 15:30 | 100 | |||||||||||||||
62 | Buka hub coupling dengan tracker (bila perlu dipanasi) | 8 hrs | 4/9/26 15:30 | 4/9/26 23:30 | 100 | |||||||||||||||
63 | Buka housing bearing & bearing in board dengan bantuan chain block. | 8,5 hrs | 4/9/26 23:30 | 4/10/26 8:00 | 100 | |||||||||||||||
64 | Buka housing bearing & bearing out board dengan bantuan chain block. | 8 hrs | 4/10/26 8:00 | 4/10/26 16:00 | 100 | |||||||||||||||
65 | Bersihkan shaft area bearing in & out board. | 4 hrs | 4/10/26 16:00 | 4/10/26 20:00 | 100 | |||||||||||||||
66 | Buka MH immpeller untuk pengecekan & cleaning. | 8 hrs | 4/10/26 20:00 | 4/11/26 4:00 | 100 | |||||||||||||||
67 | Cleaning immpeller. | 8 hrs | 4/11/26 4:00 | 4/11/26 12:00 | 100 | |||||||||||||||
68 | Pasang bearing baru (6312) in & out board dengan heater bearing | 8,5 hrs | 4/11/26 12:00 | 4/11/26 20:30 | ||||||||||||||||
69 | Pasang kembali housing bearing in board | 8 hrs | 4/11/26 20:30 | 4/12/26 4:30 | ||||||||||||||||
70 | Pasang kembali housing bearing out board | 8 hrs | 4/12/26 4:30 | 4/12/26 12:30 | ||||||||||||||||
71 | Pasang hub coupling dengan dipanasi. | 8 hrs | 4/12/26 12:30 | 4/12/26 20:30 | ||||||||||||||||
72 | Alligment motor-pompa serta ukur djarak hub to hub (DBSE) | 2 hrs | 4/13/26 7:30 | 4/13/26 9:30 | ||||||||||||||||
73 | Pasang spacer pompa diikat sesuai ukuan torsi & tutup cover pelindung coupling. | 6,5 hrs | 4/13/26 9:30 | 4/13/26 16:00 | ||||||||||||||||
74 | F6P-2418GBB : MILL SEAL AIR FAN (MSAF) 2B | Service bearing | 6,33 days | 4/9/26 7:30 | 4/15/26 15:30 | |||||||||||||||
75 | Persiapan pengamanan (Matikan breaker,tutup damper dll) | 1 hr | 4/9/26 7:30 | 4/9/26 8:30 | 100 | |||||||||||||||
76 | Buka cover coupling motor-fan. | 1 hr | 4/11/26 13:30 | 4/11/26 14:30 | ||||||||||||||||
77 | Buka spacer coupling fan-motor. | 2 hrs | 4/11/26 14:30 | 4/11/26 16:30 | ||||||||||||||||
78 | Cek alligment sebelum over haul & ukur jarak DBSE (hub to hub) | 2 hrs | 4/11/26 16:30 | 4/11/26 19:30 | ||||||||||||||||
79 | Buka hub coupling dengan tracker (bila perlu dipanasi) | 8 hrs | 4/11/26 19:30 | 4/12/26 3:30 | ||||||||||||||||
80 | Buka housing bearing & bearing in board dengan bantuan chain block. | 8 hrs | 4/12/26 3:30 | 4/12/26 11:30 | ||||||||||||||||
81 | Buka housing bearing & bearing out board dengan bantuan chain block. | 8 hrs | 4/12/26 11:30 | 4/12/26 19:30 | ||||||||||||||||
82 | Bersihkan shaft area bearing in & out board. | 4 hrs | 4/12/26 19:30 | 4/12/26 23:30 | ||||||||||||||||
83 | Buka MH immpeller untuk pengecekan & cleaning. | 8 hrs | 4/12/26 23:30 | 4/13/26 7:30 | 100 | |||||||||||||||
84 | Cleaning immpeller. | 8 hrs | 4/13/26 7:30 | 4/13/26 15:30 | 100 | |||||||||||||||
85 | Pasang bearing baru (6312) in & out board dengan heater bearing | 8 hrs | 4/13/26 15:30 | 4/13/26 23:30 | ||||||||||||||||
86 | Pasang kembali housing bearing in board | 8 hrs | 4/13/26 23:30 | 4/14/26 7:30 | ||||||||||||||||
87 | Pasang kembali housing bearing out board | 8 hrs | 4/14/26 7:30 | 4/14/26 15:30 | ||||||||||||||||
88 | Pasang hub coupling dengan dipanasi. | 8 hrs | 4/14/26 15:30 | 4/14/26 23:30 | ||||||||||||||||
89 | Alligment motor-pompa serta ukur djarak hub to hub (DBSE) | 2 hrs | 4/15/26 7:30 | 4/15/26 9:30 | ||||||||||||||||
90 | Pasang spacer pompa diikat sesuai ukuan torsi & tutup cover pelindung coupling. | 6 hrs | 4/15/26 9:30 | 4/15/26 15:30 | ||||||||||||||||
91 | F6P-2701GB : IGNITER AIR FAN (IAF) 1 | Cek dan service | 5,42 days | 4/9/26 7:30 | 4/14/26 17:30 | |||||||||||||||
92 | Persiapan pengamanan (Matikan breaker,tutup damper dll) | 1 hr | 4/9/26 7:30 | 4/9/26 8:30 | 100 | |||||||||||||||
93 | Buka cover coupling motor-fan. | 1 hr | 4/9/26 8:30 | 4/9/26 9:30 | 100 | |||||||||||||||
94 | Buka spacer coupling fan-motor. | 2 hrs | 4/9/26 9:30 | 4/9/26 11:30 | 100 | |||||||||||||||
95 | Cek alligment sebelum over haul & ukur jarak DBSE (hub to hub) | 2 hrs | 4/9/26 13:30 | 4/9/26 15:30 | 100 | |||||||||||||||
96 | Buka expantion in let & expantion out let | 8 hrs | 4/9/26 15:30 | 4/9/26 23:30 | 100 | |||||||||||||||
97 | Buka cover top blower & Hub coupling fan site | 12 hrs | 4/9/26 23:30 | 4/10/26 11:30 | 100 | |||||||||||||||
98 | Buka baut pondasi housing bearing keduanya. | 4 hrs | 4/10/26 11:30 | 4/10/26 15:30 | 100 | |||||||||||||||
99 | Angkat rotor dengan ke dua housing bearing & letakkan pada stagger/tools yang telah disediakan. | 8 hrs | 4/10/26 15:30 | 4/10/26 23:30 | 100 | |||||||||||||||
100 | Buka housing bearing & bearing 6210 | 8 hrs | 4/10/26 23:30 | 4/11/26 7:30 | 100 |