2 | Symbiosis Reforestation and Agroforestry RFP Questionnaire | |||||||||||||||||||||||||||||
3 | This spreadhseet provides a list of all questions asked in the Symbiosis RFP, along with the data type(s) requested, data selection options (where relevant), and additional guidance (where provided). This is a read only document, you may want to save or download a local copy. Updated as of December 11, 2024. | |||||||||||||||||||||||||||||
4 | Note: This is a spreadsheet version of the quesionnaire for reference, all responses should be submitted via the RFP platform | |||||||||||||||||||||||||||||
5 | ||||||||||||||||||||||||||||||
6 | Question ID | Required / Optional | Question | Data Type | Data Selection Options | Additional Guidance | Character Limit | |||||||||||||||||||||||
7 | 1 | Required | What is the name of your project? | open ended text | n/a | N/A | 100 | |||||||||||||||||||||||
8 | 2 | Required | Provide a brief description of your project. | open ended text | n/a | Please include the primary goals and desired impact of the project, social and ecological context, summary of planned activities, key stakeholders involved, and expected carbon and beyond carbon impact. | 2000 | |||||||||||||||||||||||
9 | 3 | Required | In what country is your project located? | drop-down | List of countries | Symbiosis is currently only considering projects from countries listed as Level 1-3 on the US State Department's Do Not Travel List. Level 4 countries are not eligible at this time. | N/A | |||||||||||||||||||||||
10 | 4 | Required | In what jurisdiction is your project located? | drop-down search | List of jurisdictions based on country selected - will use Mapbox API as it's translatable | N/A | ||||||||||||||||||||||||
11 | 5 | Required | In what ecoregion or ecosystem is your project located? | open ended text | 200 | |||||||||||||||||||||||||
12 | 6 | Required | What registry and methodology are you using to issue credits for this project? | drop-down | Verra’s VM0047 Verra’s VM0047 with ABACUS label Gold Standard AR American Carbon Registry, AR of Degraded Lands Climate Action Reserve Isometric, Reforestation Ecosystem Restoration Standard, M001 Plan Vivo’s P001 Cercarbono Other | Symbiosis requires projects to use a methodology from a registry that is either approved or submitted for review by ICVCM's CCP Assessment Framework (which are listed here). The registry must have been approved by the ICVCM ahead of contracting. | N/A | |||||||||||||||||||||||
13 | 7 | Required | What are your planned activities (intervention type) for the project? Select all that apply. | multi-select | 1. Active reforestation / restoration 2. Passive reforestation / restoration (assisted natural regeneration) 3. Afforestation 4. Agroforestry 5. Silvopasture | - Active reforestation/restoration is defined as activities that involve direct site preparation and tree planting. - Passive reforestation/restoration is defined as activities that enhance and/or accelerate the recovery of natural and managed forest regeneration. - If your project involves intermediate activities between these two (e.g., applied nucleation), please check both. - Afforestation is defined as the artificial establishment of forests or tree plantations on lands which previously did not supported natural forest ecosystems--defined as woody vegetation with a height of at least 5 meters and a canopy density of at least 20-25% at 30 meters existing until 50 years ago. - Agroforestry and Silvopasture interventions are defined as the establishment (either via passive or active reforestation approaches) of trees and shrubs in combination with crops, livestock, or both within a farm system. These interventioons can include dispersed or intercropped trees (land-sharing), or on-farm agricultural intensification on specific areas to enable reforestation in others (land-sparing). Note that Symbiosis is not accepting afforestation projects. | N/A | |||||||||||||||||||||||
14 | 8 | Required | What description best fits your project's goals and main activities? | drop-down | 1. Restoration-oriented project: primarily ecological restoration with goal of long term conservation 2. Mixed-use project: ecological restoration and small scale working forest (timber or agroforestry) 3. Mixed-use project: equal mix of restoration and large scale commercial plantation forestry with credits generated from both the restoration and the plantation portions of the project. 4. Production-oriented project: small scale working forest or agroforestry 5. Industrial-oriented project: large commercial scale forestry project | - We define small-scale working forests as properties approximately under 1,000 ha in regions where mill capacity and timber supply chains are non-existent or limited, but where the project is expected to support the development of these supply chains. In this cases, projects must result in mature working forests composed of mostly native species (> 80%), with appropriate species diversity and eveness indices, and managed under uneven-aged silvicutural practices. - We define large scale commercial plantation or forestry project as properties under corporate ownership or properties with corporate timber contracts of approximately > 500 ha that are intensively managed, even-aged, and/or composed of only one or two species. | N/A | |||||||||||||||||||||||
15 | 9 | Required | Have you started implementation of project activities? If yes, please provide a brief overview of the project's implementation progress. | drop-down and open ended | 1. Yes the project has started implementation 2. No the project has not started implementation | Implementation includes landowner outreach or enrollment, site preparation, seed or seedling procurement, tree planting, or other restoration activities. | 500 | |||||||||||||||||||||||
16 | 10 | Required | What is the stage of the project? | drop-down | 1. Project has a registered PDD and at least one issuance complete 2. Project has a registered and validated PDD but has not yet issued credits 3. Project has a registered PDD but has not yet issued credits 4. Project has a draft PDD or advanced feasibility study | Symbiosis is only considering projects that are post-feasibility. For guidance on what should be included in an advanced feability study, please refer to the RFP Readiness Checklist. If your project is pre-feasibility, please refer to our list of pre-feasibility project resources on our website and consider applying to our next RFP! | ||||||||||||||||||||||||
17 | 11 | Required | Please provide a registry ID number and link to the project's registry page. | open ended | n/a | N/A | 500 | |||||||||||||||||||||||
18 | 12 | Optional | We want to hear about your project's story. What are the most important highlights you want to share with Symbiosis members about your project? What makes your project unique or differentiated? Are there innovations or novel approaches you are using to increase project quality, impact, or scale? | open-ended | n/a | N/A | 2000 | |||||||||||||||||||||||
19 | 13 | Optional | Optional: Upload documents that provide an overview of your project or organization (e.g. brochure or pitch deck). | file upload | n/a | N/A | ||||||||||||||||||||||||
20 | 14 | Required | A proposal for a 10-year offtake with a pay-on-delivery payment structure is required. Please select any additional longer offtake proposals you would like to submit with a pay-on-delivery payment structure. | multi-select | 1. 15 years (2026 - 2040) 2. 20 years (2026 - 2045) 3. 30 years (2026 - 2055) | Symbiosis is seeking minimum 10-year offtakes (for contracts signed in 2025, this means deliveries through 2035), with the possibility of signing longer term contracts where required to unlock financing. If a 10-year offtake is not feasible for your project at any price per CRU, you may leave this table blank and explain below why this is the case. | N/A | |||||||||||||||||||||||
21 | 15 | Required | Please fill out the following tables with the details of your pay-on-delivery offtake proposal(s). | table | See platform | Fill out only the years in which the project plans to issue and deliver credits (ideally every 1-3 years). The remaining rows can be blank. | N/A | |||||||||||||||||||||||
22 | 16 | Required | Approximately how many hectares of total planting would this offtake support? | numeric | N/A | |||||||||||||||||||||||||
23 | 17 | Optional | If you are interested in pursuing a partial prepayment option, please fill out the following table to illustrate how partial prepayment would impact average price per CRU for your project. | table | See platform | Symbiosis may consider partial prepayment for projects where it can be catalytic to unlocking larger amounts of outside finance and/or blend down the price per CRU, especially for regions or project types with particularly long payback periods. | N/A | |||||||||||||||||||||||
24 | 18 | Required | How do you plan to finance project activities and how does this plan impact the price per CRU proposed? If a signed offtake would reduce your cost of capital or enable you to access financing that would otherwise not be available, please describe. | open-ended text | n/a | Provide as much detail as possible about what source or sources of financing you plan to use for which aspects of the project (for example: philanthropic or international grants, development bank loan, balance sheet funding, project equity, revolving credit facility, etc) as well as the status of financing (already secured, identified but not secured, in conversation, not sure yet). Also describe the role that offtake will play in allowing you to secure funding and/or lower your cost of capital. | 500 | |||||||||||||||||||||||
25 | 19 | Required | Please provide a description of the key drivers of price per CRU for your proposal. If there are uncertainties in your proposed price per CRU that could change in negotiations, please highlight them here. | open-ended text | n/a | We would like to understand what is driving the price per CRU of your project (some examples might include: land acquisition as a large upfront cost that requires substantial financing, conservative carbon removal projections due to dynamic baseline uncertainty or conservative leakage deductions, paying landowners for their true opportunity cost, etc.) | 500 | |||||||||||||||||||||||
26 | 20 | Optional | What is your approach to ensuring you are able to meet the minimum delivery guarantees required by offtakes with Symbiosis members? | open-ended text | n/a | Examples may include some or all of the following: setting aside a portion of CRUs in an internal buffer, providing replacement CRUs from other projects in your portfolio, holding carbon delivery insurance, providing seller security (e.g. letter of credit, parent guaranty, escrow, etc.), among others. | 500 | |||||||||||||||||||||||
27 | 21 | Optional | Any other information we should know about your commercial proposal(s) shared above? | open-ended text | n/a | If there are specific constraints around term length or rationale for requiring prepayment that we should know about, please describe them here. | 2000 | |||||||||||||||||||||||
28 | 22 | Optional | Do you have any additional alternative commercial proposals you would like Symbiosis members to consider? | Select | Yes, No | N/A | ||||||||||||||||||||||||
29 | 23 | Optional | Please share an overview of your alternative proposal(s) and upload any documents with additional details. | Open-ended and file upload | n/a | N/A | 2000 | |||||||||||||||||||||||
30 | 24 | Required | Please upload your project's primary boundary file for the project. | file upload | n/a | KML format. Clear project boundary for the area supporting the commercial offtake proposal. If all properties or parcels have not yet been identified for the full commercial proposal because the proposal includes multiple years of enrollment/expansion, upload the properties/parcels that have been identified to date. Project boundaries should include any internal zoning areas if available (e.g., passive vs active restoration areas, or public vs. private ownership areas, land already enrolled/acquired versus under negotiation or identified, etc). There should be consistency in the names of these zones between the attribute table of the file and the rest of the documentation presented. | ||||||||||||||||||||||||
31 | 25 | Optional | Describe what is represented in the boundary file that has been uploaded. | open-ended text | n/a | 500 | ||||||||||||||||||||||||
32 | 26 | Optional | Please review the results of the land suitability assessment. Is there additional information, or additional data, you'd like to provide to explain or give feedback on the results? Please use the file upload to share additional data. | file upload and open-ended text | n/a | N/A | 1000 | |||||||||||||||||||||||
33 | 27 | Optional | *Project documents are required for submission. Please refer to the RFP Readiness Checklist for guidance on document uploads. We expect all project developers to submit a project boundary (to be uploaded in Project DMRV Analysis tab) and completed PDD or feasibility study (feasibility study required if PDD is not submitted, optional if PDD is submitted), as well as verification reports, if available ("Primary Documents"). The remaining documents ("Supporting Documents") are also required; they may or may not already be detailed in a project developer’s PDD or feasibility study. If the information below is already covered by your PDD or feasibility study, please extract this information and paste it into a document to upload. If the information is not already included in those documents, it may be submitted as separate new documents. We will accept draft versions of any Supporting Documents. | check box with file upload | Feasibility Study (required if PDD not submitted, optional if PDD submitted) PDD (draft or final form) (if available) Verification reports (if available) Baselining Data and Procedures Carbon Removal Projections Impact Assessment Implementation Plan Adaptive Long-term Management Plan Project Financial Model & Budget Stakeholder engagement & benefit sharing plan MRV Plan | N/A | ||||||||||||||||||||||||
34 | 28 | Optional | Please upload any additional documents for consideration as part of your submission. | file upload | n/a | N/A | N/A | |||||||||||||||||||||||
35 | 29 | Required | What is the project's first year of planting? | year | n/a | N/A | ||||||||||||||||||||||||
36 | 30 | Optional | What is your estimated, average implementation cost per hectare? | numeric | n/a | N/A | N/A | |||||||||||||||||||||||
37 | 31 | Optional | What is the approximate distribution of reforestation/restoration intervention types across your entire project area? | table | See platform | N/A | ||||||||||||||||||||||||
38 | 32 | Required | Describe the key forest management activities that are planned for the maintenance stage and how will these activities support the long-term durability of the project? | open-ended text | n/a | These should be derived from your Adaptive Long-term Ecosystem or Forest Management Plan. For example, how will the project manage fire risk long-term? | 2000 | |||||||||||||||||||||||
39 | 33 | Optional | Please describe your general implementation timeline, include any past, current, and future activities that are associated with your commercial offer. | open-ended text | n/a | N/A | 1000 | |||||||||||||||||||||||
40 | 34 | Required | What is the total maximum expansion potential for the project by 2030 (in hectares)? | # | # of hectares restored by 2030 | Assume that project expansion is NOT limited by offtake and financing, but consider other limiting factors for the project (land eligibility, land enrollment, leakage, seedling supply, labor, etc.) | 500 | |||||||||||||||||||||||
41 | 35 | Required | At this full expansion potential, how many CRUs could the project deliver by 2055? | # | # CRUs delivered by 2055 | N/A | ||||||||||||||||||||||||
42 | 36 | Required | Please briefly describe how the project could achieve this expansion potential. Please focus on what are the main bottlenecks or limitations to scale. | open-ended text | n/a | Examples of bottlenecks may include: seedling or seed supply, enrolling new landowners, identifying suitable planting sites, hiring or training workforce...) | 1000 | |||||||||||||||||||||||
43 | 37 | Required | What types of revenue streams are planned for your project in addition to carbon credits? | multi-select | 1. Silviculture (Includes timber management and commercialization) 2. Agroforestry (Timber and/or other forest products) 3. Silvopastoral (Includes livestock grazing and commercialization) 4. Non-timber forest products (Includes resins, fibers, wildlife-based products, etcetera) 5. Tourism 6. Other 7. None, the only revenue is from the sale of carbon credits | N/A | ||||||||||||||||||||||||
44 | 38 | Required | Please describe the revenue streams and the estimated percentage of revenue expected to come from other revenue streams selected and the carbon credits respectively. | open-ended text | n/a | Revenue is defined as any sources of monetary income that benefit project stakeholders, including landowners, project developers, and any relevant project partner. | 1000 | |||||||||||||||||||||||
45 | 39 | Required | If your project is or will generate other revenue streams, please describe how your project is additional even with non-carbon revenue? What is the role of these other revenue streams in the long-term durability of the project? | open-ended text | n/a | N/A | 2000 | |||||||||||||||||||||||
46 | 40 | Optional | Describe the current land and forest cover distribution of the project area, focusing on the approximate proportions of forest age classes and types. | open-ended text | n/a | N/A | 2000 | |||||||||||||||||||||||
47 | 41 | Required | Please briefly describe the historical and current land-uses in the area, including any cultural, political, biophysical, or economic factors that have prevented vegetation growth and led to a persistent low carbon state such as that in the baseline scenario. | open ended text | n/a | N/A | 2000 | |||||||||||||||||||||||
48 | 42 | Required | Unless you are using Ecosystem Restoration Standard's M001 or Isometric's Reforestation methodologies for developing your project, please describe the general method to design and develop your dynamic baselines, including the selection of the donor pool area, the proposed stocking index, matching criteria and data sources, matching method and performance. | open-ended text | n/a | N/A | 2000 | |||||||||||||||||||||||
49 | 43 | Required | If not using a certified dynamic baseline procedure, justify and describe what alternative statistical approach is being used to set your baseline deduction. | open-ended text | n/a | E.g., if you are using a difference-in-difference approach instead of matching, or another peer-reviewed matching procedure | 1000 | |||||||||||||||||||||||
50 | 44 | Required | Please briefly describe the regulatory and policy context of the project area, including the existence of any regulations, policies (including government subsidies), or laws that mandate, support, or promote any activities related to restoration, reforestation, or revegetation in the project area | open ended text | n/a | N/A | 2000 | |||||||||||||||||||||||
51 | 45 | Required | Please describe how you estimated project removals, including model sources, parameterization and treatment of uncertainty. Please also indicate whether pilot and/or locally collected data has been used to validate the estimated project removals. | open ended text | n/a | N/A | 2000 | |||||||||||||||||||||||
52 | 46 | Optional | If available, please provide the sources of allometric equations used in your project or other assumptions for growth. | open ended text | n/a | N/A | 1000 | |||||||||||||||||||||||
53 | 47 | Required | Please indicate which carbon pools are being considered for crediting in your project and commercial offer and approximate percentage of each. | multi-select | 1. Aboveground biomass (AGB) 2. Belowground biomass (BGB) 3. Soil carbon (SOC) 4. Any additional carbon pools | N/A | N/A | |||||||||||||||||||||||
54 | 48 | Required | Please provide a short description of the current land and agricultural use, including information about kinds of agricultural production in the project area. If the project area is not productive for agriculture, describe why is this the case. If available, please describe any agricultural output change estimations in the project area (i.e., the difference between agricultural production in the baseline scenario vs in the project scenario). | open ended text | n/a | N/A | 2000 | |||||||||||||||||||||||
55 | 49 | Required | Please select the types of agriculture production that are currently, or were recently, in the project area. If the project area is not used for agriculture, please select none. | multi-select | See platform | N/A | N/A | |||||||||||||||||||||||
56 | 50 | Optional | If applicable, please describe any agricultural subsidy programs that affect the project area, including the operation rules or requirements of these programs. | open ended text | n/a | N/A | 500 | |||||||||||||||||||||||
57 | 51 | Required | Please describe the project's leakage mitigation measures. If none, answer N/A. | open ended text | n/a | E.g., is any agricultural intensification planned? | 1000 | |||||||||||||||||||||||
58 | 52 | Required | What is the project crediting period? | numeric | n/a | |||||||||||||||||||||||||
59 | 53 | Required | Please describe natural and anthropogenic risk of reversals and any mitigation strategies. | open-ended text | n/a | N/A | 2000 | |||||||||||||||||||||||
60 | 54 | Optional | If your project is using a land leasing model, what is the project contract length (in years) with landowners for crediting? Are there any renewal periods? If so, how often? | numeric | n/a | N/A | N/A | |||||||||||||||||||||||
61 | 55 | Required | What is the anticipated duration (in years) of the post-crediting monitoring period? | numeric | n/a | N/A | N/A | |||||||||||||||||||||||
62 | 56 | Required | Please describe what legal or socioeconomic approaches or mechanisms is your project is relying on to prevent potential long-term reversals after the project crediting period . | open ended text | n/a | 2000 | ||||||||||||||||||||||||
63 | 57 | Required | Please describe your carbon measurement, reporting, verification (MRV) plan including the integration of remote sensing and field-based methods for inventories at verification, data sources, key partners (if any), and how will the plan be implemented. If you are using Ecosystem Restoration Standard's M001 methodology, please describe how you plan to validate ERS' remote sensing estimations in the field. | open ended text | n/a | N/A | 2000 | |||||||||||||||||||||||
64 | 58 | Required | Is the project located in a high ecological conservation value area (e.g. threatened species habitat, biome with high levels of biodiversity, important watersheds, national reserves, etc.)? If yes, please provide a brief overview of why the area is a high ecological conservation value area. Include any references to relevant studies. | open ended text | n/a | 2000 | ||||||||||||||||||||||||
65 | 59 | Required | Please briefly describe your reference ecosystem(s) and how this reference ecosystem was determined. | open ended text | n/a | If available, please provide a link to the formal description for this reference ecosystem | 1000 | |||||||||||||||||||||||
66 | 60 | Required | What ecological benefits do you expect your project will generate? Are these aligned with the goals of the Global Biodiversity Framework' 2030 Targets? If so, how? | open ended text | n/a | Please refer to the Global Biodiversity Framework 2030 targets to make this connection, it it exists. | 1000 | |||||||||||||||||||||||
67 | 61 | Required | Are you using or plan to use any particular methodology or plan to keep track of the expected ecological benefits you listed? What specific biodiversity metrics and/or ecosystem services do you expect to measure and monitor? What data collection methods are you using or considering? Methods include but are not limited to: camera traps, eDNA, acoustic monitoring, field surveys. | open ended text | n/a | N/A | 1000 | |||||||||||||||||||||||
68 | 62 | Optional | Have you established any partnerships with researchers, institutions, or NGOs to support your ecological restoration goals? If so, please list the names and briefly describe the role of these partners. | open ended text | n/a | N/A | 1000 | |||||||||||||||||||||||
69 | 63 | Required | What is the species composition for plantings in the project? If the project plans to plant more than 10 species, or if your project uses passive restoration approaches (e.g. assisted natural regeneration) select the top 10 species based on abundance or dominance. If your project uses a mix of direct planting and passive restoration, please focus only on the direct plantings. | table | Species Name - Native or Non-Native - Percent of Seedlings Planted | N/A | ||||||||||||||||||||||||
70 | 64 | Required | Please describe any ecological and/or socioeconomic rationales for your species composition. If non-native species are included, please explain why. If fewer than 5 species are included, please explain why more species weren't included. | open-ended text | n/a | 500 | ||||||||||||||||||||||||
71 | 65 | Required | If your project includes an active reforestation component, please describe your overall restoration/reforestation supply chain, focusing on the sources and collection process of germplasm used for seedling production. | open-ended text | n/a | 1000 | ||||||||||||||||||||||||
72 | 66 | Required | Briefly describe your site preparation methods for planting. Do they require the application of herbicides, fertilizers, biomass removals, and/or subsoiling? | open-ended text | n/a | 1000 | ||||||||||||||||||||||||
73 | 67 | Required | What is your land strategy? | drop-down | 1. Land acquisition by project developer or partners from individual private landowners 2. Land acquisition by project developer or partners from a collective of landowners or a community 3. Land acquisition by project developer or partners from an organization 4. Land-based (i.e., lease) agreements between project developers and individual private landowners 5. Land-based agreements (i.e., lease) between project developers and a collective of landowners or communities 6. Project developer is (are) the original landowner(s) 7. Publicly owned land under a concession model | N/A | N/A | |||||||||||||||||||||||
74 | 68 | Required | What is status of land acquisition and/or landowner enrollment? | drop-down | 1. Contracts signed for all of the planned project area 2. Contracts signed for some of the planned project area 3. Contract in negotiation for all of the planned project are 4. Contract in negotiation for some of the planned project area 5. Verbal discussions underway for some or all of the planned project area 6. Other: [write in] | N/A | ||||||||||||||||||||||||
75 | 69 | Optional | If you have not uploaded a land ownership or enrollment plan, please explain how you will accomplish the necessary outreach to new landowners to meet the enrollment targets if landowners have not yet been identified or under contract negotiations. | open ended text | n/a | N/A | 2000 | |||||||||||||||||||||||
76 | 70 | Optional | Please tell us about who lives in and around the project area, including potential marginalized communities, migration trends, inhabitation of indigenous peoples and local communities (IPLCs) in or near the project area, presence of any relevant rural or urban communities that could be positively or negatively affected by the project. | open ended text | n/a | 1000 | ||||||||||||||||||||||||
77 | 71 | Required | Please describe the role and level of involvement of local leadership (i.e., indigenous groups, local communities, landowners, farmers) in the project design, implementation, and governance. | open ended text | n/a | 1000 | ||||||||||||||||||||||||
78 | 72 | Required | Do you have a benefit sharing plan with the landowners (in addition to the restoration of their land)? | drop-down | Yes No | Benefit sharing may include a revenue share or royalty with landowners, fixed lease payments, job creation, timber or agroforestry revenue.... | ||||||||||||||||||||||||
79 | 73 | Required | Please provide a description of the benefit sharing plan, including: (a) how the beneficiaries, the benefits types, and their allocation were determined, (b) the amount and payment structure of any monetary benefits, and (c) whether and how beneficiaries have agreed and to this benefit sharing plan and what evidence you have to support that. | open ended text | n/a | N/A | 2000 | |||||||||||||||||||||||
80 | 74 | Required | Please confirm that the stakeholder engagement plan you uploaded provides details on the traditional and/or indigenous communities if any are impacted by the project. In addition, the plan uploaded should provide a plan to engage landowners and/or impacted communities to ensure Free, Prior and Informed Consent (FPIC) prior to implementing project activities, and throughout the life of the project. | drop-down | Yes No | N/A | N/A | |||||||||||||||||||||||
81 | 75 | Required | Can you confirm that all the land ownership associated to the project is granted under statute, regulation, or decree by a competent authority of the country in which your project is being developed? | drop-down | Yes No | N/A | N/A | |||||||||||||||||||||||
82 | 76 | Optional | If applicable, describe any formal or informal land tenure characteristics of the land involved in the project. | open ended text | n/a | N/A | 1000 | |||||||||||||||||||||||
83 | 77 | Optional | Please describe if you are you using or plan to use any particular methodology to determine, assess, and monitor appropriate local engagement, and to keep track of any expected socioeconomic outcomes. | open ended text | n/a | N/A | 1000 | |||||||||||||||||||||||
84 | 78 | Required | Is your organization (the organization submitting the project) the project developer for the project? | drop-down | Yes No | The project developer is the organization responsible for the overall project design, implementation, registration and validation, and management. The project developer may outside some or all of these functions, but it ultimately successful for the project's success. | N/A | |||||||||||||||||||||||
85 | 79 | Required | What is the name of your organization? | open ended text | n/a | N/A | 100 | |||||||||||||||||||||||
86 | 80 | Required | What is the role of your organization? | open ended text | n/a | Please provide role (e.g. broker, investor, advisor) and whether you will be the organization with whom Symbiosis members will ultimately contract for offtake. | 200 | |||||||||||||||||||||||
87 | 81 | Required | What is the name of the organization that will be the project developer for the project? If you are the project developer then enter your own organization's name. | open ended text | n/a | N/A | 100 | |||||||||||||||||||||||
88 | 82 | Required | What is the website of the project developer? Write N/A if no website is available. | open ended text | n/a | N/A | 100 | |||||||||||||||||||||||
89 | 83 | Required | What type of organization is the project developer? | drop-down | 1. For-profit company 2. Global non-profit organization 3. Local non-profit organization 4. Other | N/A | N/A | |||||||||||||||||||||||
90 | 84 | Required | Please describe the project developer's source of financial backing (for example: philanthropic donors, venture capital or private equity, family office, subsidiary or a larger organization, self-funded). | open ended text | n/a | N/A | 500 | |||||||||||||||||||||||
91 | 85 | Required | What is the experience level of the project developer organization? | check multiple boxes | 1. The organization has registered and issued credits for 1 or more projects under same registry as this project 2. The organization has registered and issued credits for 1 or more projects under other registries 3. The organization has listed but not yet registered or issued credits for 1 or more projects under any registry 4. The organization has not yet listed or registered projects | N/A | ||||||||||||||||||||||||
92 | 86 | Required | How many years of experience does the project developer have? | number | # years | N/A | N/A | |||||||||||||||||||||||
93 | 87 | Required | Please share a brief description of the project developer's experience with similar projects to your proposed project. Include links to other projects you have listed or registered. | open ended text | n/a | N/A | 500 | |||||||||||||||||||||||
94 | 88 | Required | What is the name of the organization that will be implementing the project forestry activities? If your organization will be resposible for implementation, then enter your own organization's name. | open ended text | n/a | N/A | 100 | |||||||||||||||||||||||
95 | 89 | Required | What is the website of the implementation partner? Write N/A if no website is available. | open ended text | n/a | N/A | 100 | |||||||||||||||||||||||
96 | 90 | Required | How much land has the implementation organization restored in the last 5 years in similar projects? | drop-down | 1. Less than 100 hectares 2. Between 100 and 1,000 hectares 3. Between 1,000 and 5,000 hectares 4. More than 5,000 hectares | N/A | ||||||||||||||||||||||||
97 | 91 | Required | How many relevant years of experience does the implementation organization have? | number | # years | N/A | N/A | |||||||||||||||||||||||
98 | 92 | Required | Please share a brief description of the implementation organization's experience with similar projects to your proposed project. | open ended text | n/a | N/A | 500 | |||||||||||||||||||||||
99 | 93 | Optional | What is the name of the organization that will be conducting stakeholder engagement activities, if different from the developer? | open ended text | n/a | 100 | ||||||||||||||||||||||||