Commissioning plan for 2018 PbPb run, following TS3
3
Preconditions
4
Optics measured and mostly corrected to collisions
5
Base cycle defined and sequence ~ ready
6
Single bunch injection not yet established
7
8
DateShiftTimeStatusActivityTeamNotes
9
02/11/2018FridayDraft for discussion, everything tentative!
10
M4DoneTS3, Linac3 Pb source repair, BLM thresholds modified
11
M4DoneTS3, Linac3 Pb source repair, BLM thresholds modifiedIon source recovery continues through weekend
12
A4DoneRecovery, precycleOP
13
A4DoneEPC Interventions for PC faults @P3 and @P8
14
N4DoneCycle with one p probe (Q20) for final optics checks, IP2 crossing angle reversalOP, OMCCheck optics with both crossing angle sign in IR2, nominally in collision
15
N4DoneCycle with one p probe (Q20) for final optics checks, IP2 crossing angle reversalOP, OMC
16
03/11/2018Saturday
17
M4DoneCycle with one p probe (Q20) for final optics checks, IP2 crossing angle reversalOP, OMC
18
M6DoneLift intervention P8, acces for WSEN, Schindler
19
A2DoneSteering of TI2 and TI8 with Q26, including TCDI setupABT, OP
20
A6DoneSteering of TI2 and TI8 with Q26, including TCDI setupABT, OP
21
N2DoneCycle with 30 probe bunches (Q20) to find collsions in all IRsOP
22
N5DoneCycle with 30 probe bunches (Q20) for 'final' cleaning OP
23
04/11/2018Sunday
24
M3DoneCycle with few probes for commissioning, collisions, collimator & crystal reference, IR2 aperture check, loss maps, possible IR5 apertureOP, COLLAperture check with positive crossing angle in IR2, check loss maps in physics conditions
25
M4DoneCycle with few probes for commissioning, collisions, collimator & crystal reference, IR2 aperture check, loss maps, possible IR5 apertureOP, COLLTake time to do negative crossing angle as well
26
A4DoneCycle with few probes for commissioning, collisions, collimator & crystal reference, IR2 aperture check, loss maps, possible IR5 apertureOP
27
A4DoneMKBV Fault, SPS no beam (RF)
28
N4High beta VdMOP,EXP
29
N4
Not complete
High beta VdMOP,EXP
30
05/11/2018MondayOP
31
M4DoneSetup of Pb injection and capture (phases, delays)ABT, RF,OPExperts needed.
32
M6DoneSetup of Pb injection and capture (phases, delays)ABT, RF,OP
33
A4DoneTL check, Abort Gap Keeper validation for ionsABT, RF,OP
34
A4Cycle with few ion bunches to collisions (positive pol)OPFirst cycle lost due to fRF in the ramp, second & third cycle lost due to instability just before collisions
35
N4Cycle with few ion bunches to collisions (positive pol)OPSee detailed table on PbPb loss map sheet
36
N4DoneCycle with few ion bunches to collisions (positive pol)OP
37
06/11/2018Tuesday
38
M4OPLost on
39
M4No beam from CPS (ions)OP
40
A4OP, RF
41
A4DoneCycle to collisions with positive polarity - collimation hierarchy checkOP, RF
42
N4DoneCycle to collisions with positive polarity - collimation hierarchy checkOP
43
N4Loss maps with positive crossing angle in IP2OP
44
07/11/2018WednesdayOP
45
M4DoneCycle with negative polarity, IR2 aperture checkOP,COLL
46
M4DoneCycle with negative polarity, IR2 aperture checkOP,COLL
47
A4Cycle for TCP check and crystal setupOP,COLLOne cycle lost
48
A4DoneCycle for TCP check and crystal setupOP,COLL
49
N2DoneCycle for TCP check and crystal setupOP,COLL
50
N6DoneLoss maps with positive crossing angle in IP2 (collisions)OPIf possible move on faster with ramp-up fills
51
08/11/2018ThursdayOP
52
M5No beam from PS
53
M3DoneIR6 interlock BPMS, loss maps with positive crossing angle in IP2OPDelay from PS intervention
54
A4DoneLoss maps with positive crossing angle in IP2 OPLMs completed
55
A4DonePbPb Stable Beams,100 ns train injection ~50 bunches, 2h SBOP
56
N4Done
PbPb Stable Beams,100 ns train injection ~50 bunches, 2h SB, BFPP bump studies
OPCheck list before start of full physics production
57
N4DonePbPb Stable Beams,100 ns train injection ~50 bunches, 2h SBOP
58
09/11/2018Friday
59
M4DoneStudy of losses on TCTs in squeeze OP,COLL
60
M4DoneStudy of losses on TCTs in squeeze BLM thresholds update
61
A4DoneLoss map repetition for TCT changes squeeze & collisionsOP,ABTOne cycle lost on TCT interlock
62
A4DoneLoss map repetition for TCT changes squeeze & collisions
63
N4DonePbPb Stable Beams,100 ns train injection 260 bunches, first fillLevelling ALICE at 10^27cm^-2s^-1
64
N4DonePbPb Stable Beams,100 ns train injection 260 bunches, first fill
65
10/11/2018Saturday
66
M4LINAC3 RF amplifier
67
M3LINAC3 RF amplifier
68
A5PbPb Stable Beams,100 ns train injection 260 bunches, second fill
69
A4PbPb Stable Beams,100 ns train injection 260 bunches, second fill
70
N4PbPb Stable Beams,100 ns train injection ~450 bunches, two fills with total 6h SB
71
N4PbPb Stable Beams,100 ns train injection ~450 bunches, two fills with total 6h SB
72
11/11/2018Sunday
73
M4PbPb Stable Beams,100 ns train injection ~630 bunches, SB, long fillsLevelling ATLAS/CMS at 3. 10^27cm^-2s^-1
74
M4PbPb Stable Beams,100 ns train injection ~630 bunches, SB, long fills
75
A4PbPb production
76
A4PbPb production
77
N4PbPb production
78
N4PbPb production
79
12/11/2018Monday
80
M4PbPb production
81
M4PbPb production
82
A4VDM
83
A4VDM
84
N4VDM
85
N4PbPb production
86
13/11/2018Tuesday
87
M4PbPb production
88
M4PbPb production
89
A4PbPb production
90
A4PbPb production
91
N4PbPb production
92
N4PbPb production
93
14/11/2018Wednesday
94
M4PbPb production
95
M4PbPb production
96
A4PbPb production
97
A4PbPb production
98
N4PbPb production
99
N4PbPb production
100