Commissioning plan 2018 shift by shift
2
3
DateShiftTimeTeamStatusActivity
4
30/03/2018Friday
5
M4OP/RFEstablish circulating beam, RF adjustments
6
M4OP/BIBI and feedback checkout
7
A4OPLINAC2 & RF crate issue & PS quad
8
A4OPPre-cycle, Q' check, FB checks
9
N4OPTL kick response
10
N4OPTL kick response
11
31/03/2018Saturday
12
M4OPTCP alignment, coarse loss maps, collimator BPM checks
13
M4OPTCP alignment, coarse loss maps, RF setup nominal bunch, nominal bunch in B2
14
A4OPFirst ramp, vdm cycle setup at injection
15
A4OP/OMCOMC checks, vdm ramp
16
N4OPramps for Q'
17
N4OPramp for blowup
18
01/04/2018Sunday
19
M4ADTADT setup
20
M4OP/ADTADT setup
New settings of Daniel to be tested in next ramps
21
A4ADTADT setup
22
A4OPFlat orbit with nominal bunch, bumps with nominal, probe ramp with bumps
23
N4Zzzzz
24
N4Zzzzz
25
02/04/2018Monday
26
M4OPBeta* levelling test (dry)
27
M4OMCOptics at injection
28
A4OMCLinear optics at FT - 30 cm
29
A4OMCLinear optics at FT - 30 cm, aperture with AC dipole at 30 cm
30
N4Automated collimator alignment tests
31
N4Cycle cleaning
32
03/04/2018Tuesday
33
M4OP/RFRF cavity phasing
34
M4OP/RFRF cavity phasing & blowup & full -detuning, ALICE sol + spectrometer
35
A4OMCOptics at 27/25 cm
36
A4OMCOptics at 27/25 cm
37
N4OMCOptics at 27/25 cm
38
N4OP/OMCRCS and coupling decay investigation
39
04/04/2018Wednesday
40
M4COLLAutomated collimator alignment / ULO scan
41
M4ABTIP6 / dump aperture
42
A4ABTIP6 / dump aperture
SPS mains intervention
43
A4ABTIP6 / dump aperture
44
N4OPAutomated collimator alignment
45
N4OPFMCM tests
46
05/04/2018Thursday
47
M4OMCNL optics IR15 (a4)
failed ramp (blow up & IT GPN network disruption)
48
M4OMCNL optics IR15 (a4)
49
A6OMCNL optics IR15 (a4)
50
A2COLLCollimator alignment at injection, aperture at injection
51
N4COLLCollimator alignment at injection, aperture at injection
52
N4COLLFMCM tests
53
06/04/2018Friday
54
M4OP/RF/EXPLongitudinal blow up test / splashes for ATLAS/CMS
55
M6COLLAperture at 30 / 25 cm with probe (no collisions)
56
A5OP/RFAccess ATLAS/ full detuning test/ LBDS B1 MDB kicker issue
57
A1OP/RFCycle with nominal bunch to FT
58
N4OP/OMCFMCM tests / optics in ramp
59
N4OP/MPSFMCM tests
60
07/04/2018Saturday
61
M4OMCNL optics & beta* - correction
62
M4OMCNL optics & beta* - correction
63
A4ABTTCDI, TCLI, TDI setup
No beam2 (TED TT40) / access to point 6 (QPS)
64
A4ABTTCDI, TCLI, TDI setup
65
N4ABTTCDI, TCLI, TDI setup
66
N4OP/MPSRamp for nominal bunch to FT
67
08/04/2018Sunday
68
M4COLLCollimator alignment on FT = 1 nominal + 7 probes per beam
Issue with longitudinal blow up
69
M4COLLBlow up tests - identify issue with blow up
70
A1OP/RFvdm cycle to FT with bumps and nominal - long blow up test
71
A3COLLCollimator alignment on FT = 1 nominal + 7 probes per beam
72
A4COLLCollimator alignment on FT = 1 nominal + 7 probes per beam
73
N4OPAcesss
74
N4OPAcesss
75
09/04/2018Monday
76
M4OPTest ramp for blow up / recommissioning PELP ramp to collision
77
M4OP/COLLFull cycle to collisions with probe (no collisions, just cycle)
78
A4ABTInjection protection setup and validation (TDI, TCLIA/B) + TCDQ
79
A4ABTInjection protection setup and validation (TDI, TCLIA/B) + TCDQ
80
N4OPPPLP cycles with nomial + pilots
81
N4OPPPLP cycles with nomial + pilots
82
10/04/2018Tuesday
83
M4Access & IT5 BS regeneration
84
M4Access & IT5 BS regeneration
85
A4OPRecovery
86
A4OMCOptics at 30 cm & 25 cm
87
N4OMCOptics at 30 cm & 25 cm
88
N4OPOptics at 30 cm & 25 cm
89
11/04/2018Wednesday
90
M4ABTAperture measurements in IR2/IR8
91
M4ABTTDI validation with MKI knob
92
A4OPPLEP with pilot to 30 cm (with collimator functions) to collisions
93
A4OP
PLEP with pilot to 30 cm (with collimator functions) to collisions with TCDQ + coupling corrections
94
N4OPLLRB IR, ramp with pilot with COLL/TCDQ functions corrected + coupling meas
95
N4OP PLEP with nominal to 30 cm
96
12/04/2018Thursday
97
M4OP/COLLCollisions at 30 cm, TCT & TCL alignment
98
M4OP/COLLCollisions at 30 cm, TCT & TCL alignment
99
A4ABTBLM test in TI2/8, IR6 interlock BPMs
no beam from PS due to electical fault in RF rack
100
A4COLLBLM test in TI2/8, IR6 interlock BPMs