This is a baseline checklist. Additional quality control items should be added from the Contractor's quality control plan.
2
In order to capture QC items unique to the particular wall system, coordinate with the Wall Company's technical representative to add items from the Wall Company's construction manual, recommendations, etc. to this baseline checklist.
3
Because most of the items on the checklist occur repeatedly throughout construction of each wall, the checklist should be completed daily, once for each portion of each wall constructed that day.
4
Include daily test results, measurements, and/or documentation that show the following have been met:
5
6
Date:
7
Project:
8
Project Number:
9
Wall quality coordinator:
10
Wall on-site supervisor:
11
Wall Company's Technical Rep.:
12
Resident Engineer:
13
Wall Number:
14
From STA:
15
To STA:
16
Lift/Row:
17
18
19
DateQuality Control Plan
20
Date of authorized Quality control plan
21
22
N/A
NoYesRequired Experience
23
The wall on-site supervisor has the required experience
24
The wall quality coordinator has the required experience
25
The Wall Company's technical representative has the required experience
26
27
N/A
NoYesTraining
28
The wall construction training was conducted by the wall quality coordinator and the Wall Company's technical representative
29
All personnel participating in wall construction attended the wall construction training
30
New personnel who did not attend the initial training have been trained by the wall quality coordinator
31
32
N/A
NoYesWall Company's Technical Representative
33
The Wall Company's technical representative was on-site during the first 5 days of wall construction of each wall
34
The wall quality coordinator coordinated with the Wall Company's technical representative and the Engineer during all phases of wall construction
35
The Wall Company's technical representative was contacted, and provided technical assistance, as needed
36
The Wall Company's technical representative has been kept up-to-date (through communications, pictures, data, information, site visits, etc.) on construction progress and issues.
37
The portion of the wall constructed today was according to the specifications, Wall Company authorized drawings, and the Wall Company's construction manual
38
Concerns of the Wall Company's technical representative have been addressed
39
Guidance for quality construction from the Wall Company's technical representative has been implemented
40
41
N/A
NoYesWall Company Authorized Drawings and Other Requirements
42
Wall facing elements meet specifications, tolerances, and Wall Company authorized drawings
43
Wall drainage elements meet requirements
44
Soil reinforcement and properties meet Wall Company authorized drawings
45
Facing elements delivered to site meet project requirements
46
Facing elements delivered to site free of chips, cracks, etc.
47
Wall connections meet Wall Company authorized drawings
48
Other materials test results meet specifications and Wall Company authorized drawings
49
Materials certifications meet specifications and Wall Company authorized drawings
50
51
N/A
NoYesMSE Backfill
52
MSE backfill source material is consistent [no apparent changes (e.g. water content, gradation, organics, fines content, etc.) observed in the material]
53
MSE backfill is free of organics and other deleterious material
54
55
N/A
NoYesRunoff
56
Wall fill graded to drain runoff away from wall face at end of each day
57
58
N/A
NoYesFoundation (Subgrade) Preparation
59
Foundation (subgrade) consistently firm (and proof-rolled) throughout and prepared for wall placement (as determined by the Engineer)
60
Foundation (subgrade) soft/wet material removed and replaced with compacted MSE backfill or other suitable material as determined by the Engineer
61
62
N/A
NoYesLeveling Pad
63
Leveling pad location and dimensions staked and excavated to the correct elevation and horizontal location
64
Leveling pad placed correctly according to location and dimension requirements, and constructed level
65
Leveling pad material meets Department specifications
66
Steps in leveling pads meet specifications and Wall Company authorized drawings
67
Leveling pad concrete meets cure time requirements before setting facing elements.
68
Leveling pad clean before placement of wall facing elements
69
70
N/A
NoYesSequencing
71
Wall facing, backfill, soil reinforcement, drainage elements, filter fabric, etc. placed in correct sequence per authorized drawings and Wall Company's construction manual
72
73
N/A
NoYesDrainage and Filter Fabric
74
Drainage elements correctly tied into base drains according to the authorized wall drawings and contract plans
75
Drainage elements placed according to the authorized wall drawings and contract plans
76
Filter fabric placed according to the drawings
77
78
N/A
NoYesWall Face Bracing
79
Wall facing elements temporarily held in place/braced to meet tolerances, according to Wall Company's recommendations
80
81
N/A
NoYesPlaced MSE Backfill
82
Maximum fines content (15%) of placed MSE backfill in not exceeded
83
Placed MSE backfill meets other gradation requirements
84
Placed MSE backfill meets plasticity (PI<6) requirements
85
Placed MSE backfill meets electrochemical requirements
86
Placed MSE backfill is free of organics and other deleterious material
87
Placed MSE backfill not placed in frozen conditions
88
Placed MSE backfill has an internal friction angle of not less than 34 degrees
89
MSE backfill moisture content requirements for compaction are met
90
Placed MSE backfill meets moisture/density requirements
91
92
N/A
NoYesHeavy Equipment Zone
93
Heavy equipment not used within 3 feet of back of wall face
94
Heavy equipment not used within 3 feet of piles/drilled shafts
95
Heavy equipment not used within 3 feet of drainage boxes
96
Heavy equipment not used within 3 feet of other obstructions
97
98
N/A
NoYesLifts
99
MSE backfill placed starting from near wall face (approximately 3 feet) to back of soil reinforcements
100
Lift thicknesses 12 inch (loose) or less as necessary to obtain the specified density