Superelevationdistributionformula
 Share
The version of the browser you are using is no longer supported. Please upgrade to a supported browser.Dismiss

 
View only
 
 
ABCDEFGHIJKLMNOP
1
Super elevation Runoff (SR)Maximum Relative Gradient (G)
2
Speed Km/h100
3
PC Chainage1183.013
4
PT Chainage1313.913
5
Full Superelevtion Rate (%)6.00
6
Normal Cross Slope2.00
7
Lane width3.60
8
G ( see chart)0.44
9
α1.00
10
Length of Super elevation Runoff (SR)49.09
11
12
Tangent Run out (TR)
13
Length of Tangent Run out (TR)16.36Multiple Adjustment (α)
14
15
Chainage solution in case of Right hand Curve
16
ChainageIDL/SR/SRemarks
17
1133.92TR-2.00-2.00
18
1150.29SR0.00-2.00
19
1199.376636BFS6.00-6.00
20
1297.549364EFS6.00-6.00
21
1346.64SR0.00-2.00
22
1363.00TR-2.00-2.00