1 | Type | Funding | Project Name | Project No. | FPM Lead | Phase | Completes |
|---|---|---|---|---|---|---|---|
2 | MP | GPR | Prairie Springs Science Center Completion | 19G1J | Scott S | Bidding | Dec, 2028 |
3 | MP | GPR | Graff Main Hall HVAC System Renovation | 20D1B | Scott S | Construction | Sep, 2025 |
4 | MP | PR | CFA Parking Ramp & Police Bldg Addition | 20J1T | Scott S | Construction | Apr, 2026 |
5 | MP | PR | Residence Halls Elevator Tower Additions | 21E2J | Scott S/Dave J | Design | TBD |
6 | MP | Split | Chiller #2 Replacement and #6 Installation | 24D3M | Scott S | Bidding | Apr, 2027 |
7 | |||||||
8 | Type | Funding | Project Name | Project No. | FPM Lead | Phase | Completes |
9 | MFR | GPR | Graff/Mitchell Exterior Repairs | 23F3Z | Scott S | Construction | Aug, 2026 |
10 | MFR | PR | Residence Hall Fire Sprinkler Retrofit | 25D2K | Scott S/Dave J | Design | TBD |
11 | MFR | Split | Heating Plant Boiler Burner Replacement | 25J2T | Scott S/Gary | AE Selection | TBD |
12 | |||||||
13 | Type | Funding | Project Name | Project No. | FPM Lead | Phase | Completes |
14 | AAPR | PR | Murphy Learning Center Renovation | 24L1V | Scott S/Scott H | Design | TBD |
15 | AAPR | GPR | Wing CS Lab Renovation | 23F4N | Scott S/Scott H | Construction | Dec, 2025 |
16 | AAPR | Split | Steam Line Replacement MH 14-17-18 | 23J3K | Scott S | Construction | Sep, 2026 |
18 | AAPR | GPR | Mitchell and Morris Lab Renovations | 25H3Z | Scott S/Scott H | AE Selection | TBD |
19 | AAPR | Split | Chiller Line Replacement | 25H4A | Scott S | AE Selection | TBD |
20 | AAPR | Split | Fiber Optic Loop Completion | 25I6U | Scott S | AE Selection | TBD |
21 | |||||||
22 | Type | Funding | Project Name | Project No. | FPM Lead | Phase | Completes |
23 | SMPR | GPR | Murphy Electrical SwitchReplacement | 24J2C | Scott S/Tom | Construction | Jun, 2026 |
24 | SMPR | Split | Heat Plant Air Compressor | 25C1Z | Scott S/Gary | Construction | Apr, 2026 |
25 | SMPR | Split | Heat Plant Water Level Conrols | 25C1Y | Scott S/Gary | Construction | Apr, 2026 |
26 | SMPR | GPR | GPR Andover Head End Replacement | 25H1I | Scott S/Brian | Construction | TBD |
27 |