Take a break - Public Toilet - status
3
Sl. No Name of LSGTarget for high quality toiletsNo. of existing high quality toilets% of target achieved(Existing high quality toilets + Projects taken in sulekha)Renovation New constructionRemarks
4
No. of toilets for which projects taken in sulekhaTS issued by LSGD LID&EW (Nos)No. of toilets for which work awarded & not completedNo. of toilets for which work completedNo. of toilets for which projects taken in sulekhaTS issued by LSGD LID&EW (Nos)No. of toilets for which work awarded & not completedNo. of toilets for which work completed
5
Municipalities
6
1Ottappalam5100%33322
Renovation works are ongoing,New work not started,Land issue.
7
2Shornur560%211
Only one new toilet block is taken under this project. Got TS approval. Due to some land issues it is not tendered. All follow up activities are on progress. Updated on 16/07/2021
8
3
Chittoor Thathamangalam
5180%21DPC dt ON 19/10/2020
9
4Palakkad51180%161
10
5Pattambi520%1
Ts not obtained updated on 05/11/2020
11
6Cherpulassery5120%33
DPC Approved, Estimate under preparation, PWD NOC Required.
12
7Mannarkad52160%5
DPC Approved,Estimate Prepared
13
Grama Panchayaths
14
1Anakkara2150%1122No one has taken the tender for last year. Re- tender has to be done. Updated on 15/07/21.
15
2Chalisseri21100%11work to be tendered.updated on 15/7/2021
16
3Kappur250%1lAND ISSUE .LAND TO BE AQUIRED FROM PWD UPDATED ON 15/07/21
17
4Nagalassery2100%2111One Toilt block completed. Part bill submitted. Site not available for second toilet block. Updated on 15-07-2021
18
5Pattithara250%111Proposed site has to be chanched.Updated on 15-07-2021
19
6Thirumittacode250%111Land acquisition in progress. Updated on 15-07-2021
20
7Thrithala2100%211111Project is partially completed .Updated on 15-07-2021
21
8Koppam2100%22222 Nos completed updated on 15.07.2021
22
9Kulukkallur250%1Health department NOC Not obtained For land Updated on 15.07.2021
23
10Muthuthala2100%111111Work on going updated on 15.07.2021
24
11Ongallur250%111Work on going ,updated on 15.07.2021
25
12Paruthur250%111Work on going 40% completed ,Updated on 15.07.2021
26
13Thiruvegapura250%111Work ongoing .50% completed updated on 15.07.2021
27
14Vilayur250%1PWD NOC required. Updated on 15.07.20221
28
15Nellaya21100%1Estimate preparation ongoing
29
16Vallapuzha20%Approved by DPC on 05.11.2020.Land not available.Updated on 16/07/21
30
17Ambalapara2150%211112020-21 work bill submitted to treasury.project on 2021-22 , estimate under preperation. updated on 16/07/2021
31
18Ananganadi21150%111111Work completed.updated on16/7/2021
32
19Chalavara2100%111111Updated on 16/07/2021
33
20Lakkidi-perur21100%111New work tendered. Agreement not executed.updated on 16.07.2021
34
21Vaniamkulam250%11Agreement executed with IRTC.Requasition submitted for the advance payment. updated on 16/07/2021
35
22Thrikkadeeri250%11Work not started due to site issue.UPDATED ON 16/7/2021
36
23Kadampazhipuram21150%1111Work completed.Updated on 15/07/2021
37
24Karimpuzha2100%111160%Updated on 16/07/2021
38
25Pookkottukavu250%112NOC still not approved from Irrigation Department Updated on 15/07/2021
39
26Sreekrishnapuram22300%222222work completed 15/07/2021
40
27Vellinezhi21150%211Updated on 15.07.2021
41
28Karakurissi2100%111111New work just started. in Renovation work incinarator pending
42
29Alanallur250%1Land Not available . Updated on 15.07.2021
43
30Karimba2100%211
One project completed. Second one waiting for land permission from Irrigation department.
44
31Kottappadam250%1111Work completed on 30/06/2021. Updated on 15/07/2021
45
32Kumaramputhur2100%211Land not available for one project. Other one structural work completedUpdated on 15/07/2021
46
33Kanjirapuzha2100%2111 1 work completed 1project droped due to land issueUpdated on 15/07/2021
47
34Thachanattukara250%1Police dept NOC.Updated on 15/07/2021
48
35Tachampara2200%21211 No land not available.Updated on 15/07/2021
49
36Thenkara2100%111Updated on 15.07.2021
50
37Agali21100%11Estimate Under Preparation.Updated on 15.07.2021
51
38Pudur250%111main slab completed plastering on going.Updated on 15/07/2021
52
39Sholayur2200%21112111no building physically completed,and remaning elctrification work.1no DPC approvalUpdated on 15/07/2021
53
40Keralassery2100%1111 completed-updated on 15.07.2021
54
41Kongad2100%111175% work completed balance work on progress
55
42Mankara2100%111Project has to be re tendered
56
43Mannur2100%111Land not yet obtained . updated on 15.07.21
57
44Mundur2100%222WORK COPMPLETED, BILL UNDER PREPARATION
58
45Parali250%111WORK COPMPLETED, BILL PAID
59
46Pirayiri2100%2Land for construction of toilet not obtained yet.15.07.2021
60
47Kottayi2100%111111Completed updated on 15/07/2021
61
48Kuthanoor250%111Lintel concreting Completed updated on 15/07/2021
62
49Kuzhalmannam2100%11111Land is not available updated on 15/07/2021
63
50Mathur2100%111111Agreement executed but land issues updated on 15/07/2021
64
51Peringottukurissi20%due to non availablity of fund existing toilet block renewed updated on 15.07.2021
65
52Thenkurissi2100%22NOC from PWD updated on 15.07.2021
66
53Kannadi250%1111.For New construction NOC from irrigation department to be obtained and the same is submitted to The District collector for sanction.2 The existing toilet will be rennovated and the same is not included in Sulekha updated on 15.07.2021
67
54Eruthempathy250%11Tender work completed, single person qouted, hence retender to be done.
68
55Kozhinjampara2100%222Work agreement executed.Work not Started yet due to unavailabilty of suitable site.
69
56Nalleppilly2100%222One work ongoing-reached block work upto roof level and the other work in the pt. compound site not cleard by the LB- needs to shift the pipe line(pumping main).
70
57Perumatty2100%111111Two works ongoing, maintanance works tiles work balance and new work main slab completed up dated 15.07.2021
71
58Vadakarapathy250%1Tender process not done - Land not available for new toilet construction. (15/07/2021)
72
59Elappully2100%11111work completed .updated on 15/7/21
73
60Polpully2100%11Land not available for new toilet construction. only one project in sulekha for both new and renovation works.secretary to revise project in next DPC
74
61Pattencherry20%projects not taken in sulekha updated on 15/07/2021
75
62Kollengode2100%22(Renovation)80% work completed (single project: Two Toilet maintenance) incineretor fitting work balance,part bill paid 1,07,185/-.updated on 15/07/2021
76
63Koduvayur250%111 Work in progress,(Foundation completed) Plinth Belt work in completed .Updated on 22/07/2021
77
64Muthalamada2100%221One work Re-tendered and called for quatation But NO RESPONSE.The Other work just started after demolishing damaged building inside the panchayat office premises but board dicided to shift the location to kambrathchalla Town area. This Land is under PWD .Updated On 15.07.2021

78
65Puthunagaram2100%11111Renovation Work- not started, New Work- land dispute. updated on 15/07/2021
79
66Vadavannur250%1Land not available. updated on 15/07/2021
80
67Peruvemb2200%22one project at plastering stage. request submitted to DP for Electrical Estimate. One project not started .due to land issue with revenue. updated on 15.07.2021
81
68Ayiloor250%111work cancelled due to building problem. updated on 16/07/2021
82
69Nelliampathy250%11No land available.Updated on 16/07/2021
83
70Elavancherry20%
Land not available for new toilet construction.
84
71Pallassana2100%221One Work under progressing.90% completed. and one work not started.updated on 15/07/2021
85
72Melarcode2100%11111111TS obtained,updated on17.11.20 waiting for clarification from revenue dept.Updated on 16/07/2021
86
73Nemmara250%111Work under progressing.80% completed. updated on 16/07/2021
87
74Vandazhy250%11land dispute,waiting for clarification from revenue dept.Updated on 16/07/2021
88
75Alathur2100%11Existing bus stand building Toilet unit Renovation,One toilet unit Land aquisition required
89
76Erimayur2100%11
Earlier, a place on the side of NH544, near Thottupalam, Erimayur, was earmarked for Take a Break Project as suggested by Panchayat Secretary and Village officer. Estimate was also prepared according to this place and subsequently, TS obtained. But, later, NHAI didn't give the consent for this place in view of future widening process. Panchayat Board is still looking for another suitable place for this project.Updated on 16.7.2021
90
77Kavassery2100%222 Toilet is for new construction. TS obtained , Tendered . One project dropped due to non availability of NOC from Irrigation Dept. One toilet which is constructed in Village office compound to be rennovated which need permission from Revenew Dept. Updated on 16/07/21
91
78Kizhakkancherry250%1Revision required for the project,as the amount increased to cope up the requirements.
92
79Puducode2100%2Revision required for the project.Site not available yet.
93
80Tarur2100%11111 Toilet is for new construction agreement executed space available in school compound and 1 toilet for maintenance , maintenance toilet need NOC from palakkad district mini industrial estate and commerce .New proposals is meant to have land issue. updated on 28/10/2020
94
81Vadakkancheri2150%222111Target 3 toilet blocks. This includes renovation works of two toilet blocks(10 units)and construction one new toilet block.T.S Accorded for renovation and new toilet work and it is Tendered.Renovation works completed.New toilet construction was proposed in PWD land,and as they raised objection work couldn't started.
95
82Kannambra2100%2211one project completed, another one 80% work completed, updatd on 15/7/21
96
83Kodumba250%111
97
84Akathethara2150%11221Targe three toilets, 2 toilets is for new construction and 1 toilet for maintenance, new toile is meant to have land issue, letter given to concerned dept to resolve the same. maintence work toilet is got completed except sanitary napkin destroyer unit.. updated on 15/07/2021
98
85Malampuzha2100%111The existing take a break project has been changed to Deposit work of Nirmmithi because of no participation in tender .Updated on 15.07.2021
99
86Marutharode2400%4444Rennovation of 4 toilets completed. The napkin incinerator and name board for the project has to be installed.
100
87Puduppariyaram2100%222The works to be tendered on 16/11/2020
101
88Pudusseri20%11115 Gents toilet,5 Ladies Toilet, 1 Disabled ,One Rest room included in the toilet block. The roof slab shuttering going on. updated on 15/07/2021