1 | Take a break - Public Toilet - status | ||||||||||||||
3 | Sl. No | Name of LSG | Target for high quality toilets | No. of existing high quality toilets | % of target achieved(Existing high quality toilets + Projects taken in sulekha) | Renovation | New construction | Remarks | |||||||
4 | No. of toilets for which projects taken in sulekha | TS issued by LSGD LID&EW (Nos) | No. of toilets for which work awarded & not completed | No. of toilets for which work completed | No. of toilets for which projects taken in sulekha | TS issued by LSGD LID&EW (Nos) | No. of toilets for which work awarded & not completed | No. of toilets for which work completed | |||||||
5 | Municipalities | ||||||||||||||
6 | 1 | Ottappalam | 5 | 100% | 3 | 3 | 3 | 2 | 2 | Renovation works are ongoing,New work not started,Land issue. | |||||
7 | 2 | Shornur | 5 | 60% | 2 | 1 | 1 | Only one new toilet block is taken under this project. Got TS approval. Due to some land issues it is not tendered. All follow up activities are on progress. Updated on 16/07/2021 | |||||||
8 | 3 | Chittoor Thathamangalam | 5 | 1 | 80% | 2 | 1 | DPC dt ON 19/10/2020 | |||||||
9 | 4 | Palakkad | 5 | 1 | 180% | 1 | 6 | 1 | |||||||
10 | 5 | Pattambi | 5 | 20% | 1 | Ts not obtained updated on 05/11/2020 | |||||||||
11 | 6 | Cherpulassery | 5 | 120% | 3 | 3 | DPC Approved, Estimate under preparation, PWD NOC Required. | ||||||||
12 | 7 | Mannarkad | 5 | 2 | 160% | 5 | DPC Approved,Estimate Prepared | ||||||||
13 | Grama Panchayaths | ||||||||||||||
14 | 1 | Anakkara | 2 | 150% | 1 | 1 | 2 | 2 | No one has taken the tender for last year. Re- tender has to be done. Updated on 15/07/21. | ||||||
15 | 2 | Chalisseri | 2 | 1 | 100% | 1 | 1 | work to be tendered.updated on 15/7/2021 | |||||||
16 | 3 | Kappur | 2 | 50% | 1 | lAND ISSUE .LAND TO BE AQUIRED FROM PWD UPDATED ON 15/07/21 | |||||||||
17 | 4 | Nagalassery | 2 | 100% | 2 | 1 | 1 | 1 | One Toilt block completed. Part bill submitted. Site not available for second toilet block. Updated on 15-07-2021 | ||||||
18 | 5 | Pattithara | 2 | 50% | 1 | 1 | 1 | Proposed site has to be chanched.Updated on 15-07-2021 | |||||||
19 | 6 | Thirumittacode | 2 | 50% | 1 | 1 | 1 | Land acquisition in progress. Updated on 15-07-2021 | |||||||
20 | 7 | Thrithala | 2 | 100% | 2 | 1 | 1 | 1 | 1 | 1 | Project is partially completed .Updated on 15-07-2021 | ||||
21 | 8 | Koppam | 2 | 100% | 2 | 2 | 2 | 2 | 2 Nos completed updated on 15.07.2021 | ||||||
22 | 9 | Kulukkallur | 2 | 50% | 1 | Health department NOC Not obtained For land Updated on 15.07.2021 | |||||||||
23 | 10 | Muthuthala | 2 | 100% | 1 | 1 | 1 | 1 | 1 | 1 | Work on going updated on 15.07.2021 | ||||
24 | 11 | Ongallur | 2 | 50% | 1 | 1 | 1 | Work on going ,updated on 15.07.2021 | |||||||
25 | 12 | Paruthur | 2 | 50% | 1 | 1 | 1 | Work on going 40% completed ,Updated on 15.07.2021 | |||||||
26 | 13 | Thiruvegapura | 2 | 50% | 1 | 1 | 1 | Work ongoing .50% completed updated on 15.07.2021 | |||||||
27 | 14 | Vilayur | 2 | 50% | 1 | PWD NOC required. Updated on 15.07.20221 | |||||||||
28 | 15 | Nellaya | 2 | 1 | 100% | 1 | Estimate preparation ongoing | ||||||||
29 | 16 | Vallapuzha | 2 | 0% | Approved by DPC on 05.11.2020.Land not available.Updated on 16/07/21 | ||||||||||
30 | 17 | Ambalapara | 2 | 150% | 2 | 1 | 1 | 1 | 1 | 2020-21 work bill submitted to treasury.project on 2021-22 , estimate under preperation. updated on 16/07/2021 | |||||
31 | 18 | Ananganadi | 2 | 1 | 150% | 1 | 1 | 1 | 1 | 1 | 1 | Work completed.updated on16/7/2021 | |||
32 | 19 | Chalavara | 2 | 100% | 1 | 1 | 1 | 1 | 1 | 1 | Updated on 16/07/2021 | ||||
33 | 20 | Lakkidi-perur | 2 | 1 | 100% | 1 | 1 | 1 | New work tendered. Agreement not executed.updated on 16.07.2021 | ||||||
34 | 21 | Vaniamkulam | 2 | 50% | 1 | 1 | Agreement executed with IRTC.Requasition submitted for the advance payment. updated on 16/07/2021 | ||||||||
35 | 22 | Thrikkadeeri | 2 | 50% | 1 | 1 | Work not started due to site issue.UPDATED ON 16/7/2021 | ||||||||
36 | 23 | Kadampazhipuram | 2 | 1 | 150% | 1 | 1 | 1 | 1 | Work completed.Updated on 15/07/2021 | |||||
37 | 24 | Karimpuzha | 2 | 100% | 1 | 1 | 1 | 1 | 60% | Updated on 16/07/2021 | |||||
38 | 25 | Pookkottukavu | 2 | 50% | 1 | 1 | 2 | NOC still not approved from Irrigation Department Updated on 15/07/2021 | |||||||
39 | 26 | Sreekrishnapuram | 2 | 2 | 300% | 2 | 2 | 2 | 2 | 2 | 2 | work completed 15/07/2021 | |||
40 | 27 | Vellinezhi | 2 | 1 | 150% | 2 | 1 | 1 | Updated on 15.07.2021 | ||||||
41 | 28 | Karakurissi | 2 | 100% | 1 | 1 | 1 | 1 | 1 | 1 | New work just started. in Renovation work incinarator pending | ||||
42 | 29 | Alanallur | 2 | 50% | 1 | Land Not available . Updated on 15.07.2021 | |||||||||
43 | 30 | Karimba | 2 | 100% | 2 | 1 | 1 | One project completed. Second one waiting for land permission from Irrigation department. | |||||||
44 | 31 | Kottappadam | 2 | 50% | 1 | 1 | 1 | 1 | Work completed on 30/06/2021. Updated on 15/07/2021 | ||||||
45 | 32 | Kumaramputhur | 2 | 100% | 2 | 1 | 1 | Land not available for one project. Other one structural work completedUpdated on 15/07/2021 | |||||||
46 | 33 | Kanjirapuzha | 2 | 100% | 2 | 1 | 1 | 1 | 1 work completed 1project droped due to land issueUpdated on 15/07/2021 | ||||||
47 | 34 | Thachanattukara | 2 | 50% | 1 | Police dept NOC.Updated on 15/07/2021 | |||||||||
48 | 35 | Tachampara | 2 | 200% | 2 | 1 | 2 | 1 | 1 No land not available.Updated on 15/07/2021 | ||||||
49 | 36 | Thenkara | 2 | 100% | 1 | 1 | 1 | Updated on 15.07.2021 | |||||||
50 | 37 | Agali | 2 | 1 | 100% | 1 | 1 | Estimate Under Preparation.Updated on 15.07.2021 | |||||||
51 | 38 | Pudur | 2 | 50% | 1 | 1 | 1 | main slab completed plastering on going.Updated on 15/07/2021 | |||||||
52 | 39 | Sholayur | 2 | 200% | 2 | 1 | 1 | 1 | 2 | 1 | 1 | 1no building physically completed,and remaning elctrification work.1no DPC approvalUpdated on 15/07/2021 | |||
53 | 40 | Keralassery | 2 | 100% | 1 | 1 | 1 | 1 completed-updated on 15.07.2021 | |||||||
54 | 41 | Kongad | 2 | 100% | 1 | 1 | 1 | 1 | 75% work completed balance work on progress | ||||||
55 | 42 | Mankara | 2 | 100% | 1 | 1 | 1 | Project has to be re tendered | |||||||
56 | 43 | Mannur | 2 | 100% | 1 | 1 | 1 | Land not yet obtained . updated on 15.07.21 | |||||||
57 | 44 | Mundur | 2 | 100% | 2 | 2 | 2 | WORK COPMPLETED, BILL UNDER PREPARATION | |||||||
58 | 45 | Parali | 2 | 50% | 1 | 1 | 1 | WORK COPMPLETED, BILL PAID | |||||||
59 | 46 | Pirayiri | 2 | 100% | 2 | Land for construction of toilet not obtained yet.15.07.2021 | |||||||||
60 | 47 | Kottayi | 2 | 100% | 1 | 1 | 1 | 1 | 1 | 1 | Completed updated on 15/07/2021 | ||||
61 | 48 | Kuthanoor | 2 | 50% | 1 | 1 | 1 | Lintel concreting Completed updated on 15/07/2021 | |||||||
62 | 49 | Kuzhalmannam | 2 | 100% | 1 | 1 | 1 | 1 | 1 | Land is not available updated on 15/07/2021 | |||||
63 | 50 | Mathur | 2 | 100% | 1 | 1 | 1 | 1 | 1 | 1 | Agreement executed but land issues updated on 15/07/2021 | ||||
64 | 51 | Peringottukurissi | 2 | 0% | due to non availablity of fund existing toilet block renewed updated on 15.07.2021 | ||||||||||
65 | 52 | Thenkurissi | 2 | 100% | 2 | 2 | NOC from PWD updated on 15.07.2021 | ||||||||
66 | 53 | Kannadi | 2 | 50% | 1 | 1 | 1 | 1.For New construction NOC from irrigation department to be obtained and the same is submitted to The District collector for sanction.2 The existing toilet will be rennovated and the same is not included in Sulekha updated on 15.07.2021 | |||||||
67 | 54 | Eruthempathy | 2 | 50% | 1 | 1 | Tender work completed, single person qouted, hence retender to be done. | ||||||||
68 | 55 | Kozhinjampara | 2 | 100% | 2 | 2 | 2 | Work agreement executed.Work not Started yet due to unavailabilty of suitable site. | |||||||
69 | 56 | Nalleppilly | 2 | 100% | 2 | 2 | 2 | One work ongoing-reached block work upto roof level and the other work in the pt. compound site not cleard by the LB- needs to shift the pipe line(pumping main). | |||||||
70 | 57 | Perumatty | 2 | 100% | 1 | 1 | 1 | 1 | 1 | 1 | Two works ongoing, maintanance works tiles work balance and new work main slab completed up dated 15.07.2021 | ||||
71 | 58 | Vadakarapathy | 2 | 50% | 1 | Tender process not done - Land not available for new toilet construction. (15/07/2021) | |||||||||
72 | 59 | Elappully | 2 | 100% | 1 | 1 | 1 | 1 | 1 | work completed .updated on 15/7/21 | |||||
73 | 60 | Polpully | 2 | 100% | 1 | 1 | Land not available for new toilet construction. only one project in sulekha for both new and renovation works.secretary to revise project in next DPC | ||||||||
74 | 61 | Pattencherry | 2 | 0% | projects not taken in sulekha updated on 15/07/2021 | ||||||||||
75 | 62 | Kollengode | 2 | 100% | 2 | 2 | (Renovation)80% work completed (single project: Two Toilet maintenance) incineretor fitting work balance,part bill paid 1,07,185/-.updated on 15/07/2021 | ||||||||
76 | 63 | Koduvayur | 2 | 50% | 1 | 1 | 1 | Work in progress,(Foundation completed) Plinth Belt work in completed .Updated on 22/07/2021 | |||||||
77 | 64 | Muthalamada | 2 | 100% | 2 | 2 | 1 | One work Re-tendered and called for quatation But NO RESPONSE.The Other work just started after demolishing damaged building inside the panchayat office premises but board dicided to shift the location to kambrathchalla Town area. This Land is under PWD .Updated On 15.07.2021 | |||||||
78 | 65 | Puthunagaram | 2 | 100% | 1 | 1 | 1 | 1 | 1 | Renovation Work- not started, New Work- land dispute. updated on 15/07/2021 | |||||
79 | 66 | Vadavannur | 2 | 50% | 1 | Land not available. updated on 15/07/2021 | |||||||||
80 | 67 | Peruvemb | 2 | 200% | 2 | 2 | one project at plastering stage. request submitted to DP for Electrical Estimate. One project not started .due to land issue with revenue. updated on 15.07.2021 | ||||||||
81 | 68 | Ayiloor | 2 | 50% | 1 | 1 | 1 | work cancelled due to building problem. updated on 16/07/2021 | |||||||
82 | 69 | Nelliampathy | 2 | 50% | 1 | 1 | No land available.Updated on 16/07/2021 | ||||||||
83 | 70 | Elavancherry | 2 | 0% | Land not available for new toilet construction. | ||||||||||
84 | 71 | Pallassana | 2 | 100% | 2 | 2 | 1 | One Work under progressing.90% completed. and one work not started.updated on 15/07/2021 | |||||||
85 | 72 | Melarcode | 2 | 100% | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | TS obtained,updated on17.11.20 waiting for clarification from revenue dept.Updated on 16/07/2021 | ||
86 | 73 | Nemmara | 2 | 50% | 1 | 1 | 1 | Work under progressing.80% completed. updated on 16/07/2021 | |||||||
87 | 74 | Vandazhy | 2 | 50% | 1 | 1 | land dispute,waiting for clarification from revenue dept.Updated on 16/07/2021 | ||||||||
88 | 75 | Alathur | 2 | 100% | 1 | 1 | Existing bus stand building Toilet unit Renovation,One toilet unit Land aquisition required | ||||||||
89 | 76 | Erimayur | 2 | 100% | 1 | 1 | Earlier, a place on the side of NH544, near Thottupalam, Erimayur, was earmarked for Take a Break Project as suggested by Panchayat Secretary and Village officer. Estimate was also prepared according to this place and subsequently, TS obtained. But, later, NHAI didn't give the consent for this place in view of future widening process. Panchayat Board is still looking for another suitable place for this project.Updated on 16.7.2021 | ||||||||
90 | 77 | Kavassery | 2 | 100% | 2 | 2 | 2 Toilet is for new construction. TS obtained , Tendered . One project dropped due to non availability of NOC from Irrigation Dept. One toilet which is constructed in Village office compound to be rennovated which need permission from Revenew Dept. Updated on 16/07/21 | ||||||||
91 | 78 | Kizhakkancherry | 2 | 50% | 1 | Revision required for the project,as the amount increased to cope up the requirements. | |||||||||
92 | 79 | Puducode | 2 | 100% | 2 | Revision required for the project.Site not available yet. | |||||||||
93 | 80 | Tarur | 2 | 100% | 1 | 1 | 1 | 1 | 1 Toilet is for new construction agreement executed space available in school compound and 1 toilet for maintenance , maintenance toilet need NOC from palakkad district mini industrial estate and commerce .New proposals is meant to have land issue. updated on 28/10/2020 | ||||||
94 | 81 | Vadakkancheri | 2 | 150% | 2 | 2 | 2 | 1 | 1 | 1 | Target 3 toilet blocks. This includes renovation works of two toilet blocks(10 units)and construction one new toilet block.T.S Accorded for renovation and new toilet work and it is Tendered.Renovation works completed.New toilet construction was proposed in PWD land,and as they raised objection work couldn't started. | ||||
95 | 82 | Kannambra | 2 | 100% | 2 | 2 | 1 | 1 | one project completed, another one 80% work completed, updatd on 15/7/21 | ||||||
96 | 83 | Kodumba | 2 | 50% | 1 | 1 | 1 | ||||||||
97 | 84 | Akathethara | 2 | 150% | 1 | 1 | 2 | 2 | 1 | Targe three toilets, 2 toilets is for new construction and 1 toilet for maintenance, new toile is meant to have land issue, letter given to concerned dept to resolve the same. maintence work toilet is got completed except sanitary napkin destroyer unit.. updated on 15/07/2021 | |||||
98 | 85 | Malampuzha | 2 | 100% | 1 | 1 | 1 | The existing take a break project has been changed to Deposit work of Nirmmithi because of no participation in tender .Updated on 15.07.2021 | |||||||
99 | 86 | Marutharode | 2 | 400% | 4 | 4 | 4 | 4 | Rennovation of 4 toilets completed. The napkin incinerator and name board for the project has to be installed. | ||||||
100 | 87 | Puduppariyaram | 2 | 100% | 2 | 2 | 2 | The works to be tendered on 16/11/2020 | |||||||
101 | 88 | Pudusseri | 2 | 0% | 11 | 11 | 5 Gents toilet,5 Ladies Toilet, 1 Disabled ,One Rest room included in the toilet block. The roof slab shuttering going on. updated on 15/07/2021 |