Create professional Gantt charts in GanttPRO in a few clicks
3
4
New Home Construction Budget12/3/2025
5
Color
WBS Number
Task name / TitleAssigned to
Planned start date
Planned end date
Deadline
Progress (%)
Duration (hours)
Estimated hours
Time log (minutes)
StatusPriority
Task description
Cost
Actual cost
6
1ZONING3/5/20265/7/202603680000
7
1.1Land Use3/5/20265/6/2026036000OpenMedium00
8
1.2Easements, Set Backs3/8/20265/7/2026036000OpenMedium00
9
1.3Access, Street Improvements3/8/20265/7/2026036000OpenMedium00
10
1.4Utilities Available3/8/20265/7/2026036000OpenMedium00
11
2HOUSE PLANS5/10/20267/14/202603840000
12
2.1Purchase Standard Plans5/10/20267/9/2026036000OpenMedium00
13
2.2Architect Original Drawings5/11/20267/12/2026036000OpenMedium00
14
2.3Specifications5/12/20267/13/2026036000OpenMedium00
15
2.4Architect Manage Job5/13/20267/14/2026036000OpenMedium00
16
2.5Engineer-Loads & Spans5/13/20267/14/2026036000OpenMedium00
17
2.6Draftsman5/13/20267/14/2026036000OpenMedium00
18
3LOT SURVEY7/15/20269/20/202603840000
19
3.1House & Driveway7/15/20269/15/2026036000OpenMedium00
20
3.2Well Locaton7/16/20269/16/2026036000OpenMedium00
21
3.3Septic Location7/19/20269/17/2026036000OpenMedium00
22
3.4Fire Hydrant & Truck Access7/20/20269/20/2026036000OpenMedium00
23
3.5Plot Plan7/20/20269/20/2026036000OpenMedium00
24
4FINANCIAL - LOAN9/21/202611/25/202603840000
25
4.1Land Cost9/21/202611/22/2026036000OpenMedium00
26
4.2Interest on Land9/22/202611/23/2026036000OpenMedium00
27
4.3Interest on Const. Loan9/23/202611/24/2026036000OpenMedium00
28
4.4Points, Etc.9/24/202611/25/2026036000OpenMedium00
29
5SEWER & WATER HOOKUP3/29/20265/28/2026036000OpenMedium00
30
6HEALTH PERMIT3/29/20266/1/202603760000
31
6.1Fees3/29/20265/28/2026036000OpenMedium00
32
6.2Percolation Test3/30/20265/31/2026036000OpenMedium00
33
6.3Soils Engineer3/31/20266/1/2026036000OpenMedium00
34
7INSURANCE4/1/20266/2/2026036000OpenMedium00
35
8LOT CLOSING COSTS4/2/20266/3/2026036000OpenMedium00
36
9BUILDING PERMITS4/5/20266/4/202603600000
37
9.1Fees4/5/20266/4/2026036000OpenMedium00
38
9.2Inspection Schedule4/5/20266/4/2026036000OpenMedium00
39
10PRELIMINARY LIST ONLY4/6/20266/7/2026036000OpenMedium00
40
11BUILD PHASE4/7/20266/8/2026036000OpenMedium00
41
12SPECIAL & DRY IN MATERIALS4/9/20266/11/202603680000
42
12.1Rough Hardware, Misc.4/9/20266/10/2026036000OpenMedium00
43
12.2Lolly Columns4/12/20266/11/2026036000OpenMedium00
44
12.3Steel Beams4/12/20266/11/2026036000OpenMedium00
45
12.4Rough Lumber, Trusses4/12/20266/11/2026036000OpenMedium00
46
13WINDOWS/OPENINGS4/14/20266/17/202603760000
47
13.1Windows, Grills, Screens4/14/20266/15/2026036000OpenMedium00
48
13.2Exterior Doors,Screens4/15/20266/16/2026036000OpenMedium00
49
13.3Skylights and Light Tubes4/16/20266/17/2026036000OpenMedium00
50
14DEMOLITION4/19/20266/18/2026036000OpenMedium00
51
15LOT CLEARING4/19/20266/22/202603760000
52
15.1Debris Removal & Clearing4/19/20266/18/2026036000OpenMedium00
53
15.2Dump Fee4/20/20266/21/2026036000OpenMedium00
54
15.3Bury Stumps, etc.4/21/20266/22/2026036000OpenMedium00
55
16DRIVEWAY, rough4/23/20266/25/202603680000
56
16.1Grade4/23/20266/24/2026036000OpenMedium00
57
16.2Base Rock, Culverts4/26/20266/25/2026036000OpenMedium00
58
17UTILITIES4/26/20266/28/202603680000
59
17.1Temporary at startup4/26/20266/25/2026036000OpenMedium00
60
17.2Transfer to permanent4/27/20266/28/2026036000OpenMedium00
61
18WELL or PUBLIC WATER4/28/20266/29/2026036000OpenMedium00
62
19SEPTIC or PUBLIC SEWER4/29/20266/30/2026036000OpenMedium00
63
20LAYOUT HOUSE FOOTPRINT5/3/20267/2/202603600000
64
20.1Establish Finish Floor Height5/3/20267/2/2026036000OpenMedium00
65
20.2Set Back Distances5/3/20267/2/2026036000OpenMedium00
66
21DIG FOUNDATION5/3/20267/2/2026036000OpenMedium00
67
22ROCK PROBLEM5/4/20267/5/2026036000OpenMedium00
68
23PREPARE FOR FOOTINGS5/6/20267/8/202603680000
69
23.1Lay out and excavate5/6/20267/7/2026036000OpenMedium00
70
23.2Form, Rebar, Grade Pegs5/7/20267/8/2026036000OpenMedium00
71
24POUR FOOTINGS & PADS5/10/20267/9/202603600000
72
24.1Yds. of Concrete5/10/20267/9/2026036000OpenMedium00
73
25SET BRICK POINTS5/10/20267/9/2026036000OpenMedium00
74
26TERMITE TREATMENT5/11/20267/12/2026036000OpenMedium00
75
27RADON CONTROL5/12/20267/13/2026036000OpenMedium00
76
28FOUNDATION WALLS5/14/20267/20/202603840000
77
28.1Block/Course5/14/20267/15/2026036000OpenMedium00
78
28.2Piers5/17/20267/16/2026036000OpenMedium00
79
28.3Pour Wall, Yds. Of Concrete5/17/20267/16/2026036000OpenMedium00
80
28.4Lintels, Rebar5/17/20267/16/2026036000OpenMedium00
81
28.5Parging5/18/20267/19/2026036000OpenMedium00
82
28.6Cement, Sand, etc.5/19/20267/20/2026036000OpenMedium00
83
29WATERPROOF FOUNDATION.5/20/20267/21/2026036000OpenMedium00
84
30COLUMNS/BEAMS SET5/21/20267/22/2026036000OpenMedium00
85
31UNDERGROUND PLUMBING5/24/20267/23/2026036000OpenMedium00
86
32BRICK/STONE, to finish grade5/24/20267/23/2026036000OpenMedium00
87
33GARAGE DOORS5/25/20267/27/202603680000
88
33.1Openers5/25/20267/26/2026036000OpenMedium00
89
33.2Trim, Backing, Weatherstrip5/26/20267/27/2026036000OpenMedium00
90
34DRAIN TILE5/27/20267/28/2026036000OpenMedium00
91
35FIRE PLACE - INTERIOR5/31/20267/30/202603600000
92
35.1Pour Hearth5/31/20267/30/2026036000OpenMedium00
93
35.2Firebox, or Set Prefab5/31/20267/30/2026036000OpenMedium00
94
35.3Brick or Stone Facing5/31/20267/30/2026036000OpenMedium00
95
36PREPARE CONC. SLABS ETC.6/2/20268/6/202603840000
96
36.1Gravel, Wire, Poly, Grade Stakes6/2/20268/3/2026036000OpenMedium00
97
36.2Labor to Prepare for Slab6/3/20268/4/2026036000OpenMedium00
98
36.3Rebar, Wire, form boards6/4/20268/5/2026036000OpenMedium00
99
36.4
Labor-Prepare, Form other Conc.
6/7/20268/6/2026036000OpenMedium00
100
36.5
Deck & Post Hole footings, etc.
6/7/20268/6/2026036000OpenMedium00