3 | ||||||||||||||||||||||||||
4 | New Home Construction Budget | 9/15/2025 | ||||||||||||||||||||||||
5 | Color | WBS Number | Task name / Title | Assigned to | Planned start date | Planned end date | Deadline | Progress (%) | Duration (hours) | Estimated hours | Time log (minutes) | Status | Priority | Task description | Cost | Actual cost | ||||||||||
6 | 1 | ZONING | 12/16/2025 | 2/17/2026 | 0 | 368 | 0 | 0 | 0 | 0 | ||||||||||||||||
7 | 1.1 | Land Use | 12/16/2025 | 2/16/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
8 | 1.2 | Easements, Set Backs | 12/19/2025 | 2/17/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
9 | 1.3 | Access, Street Improvements | 12/19/2025 | 2/17/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
10 | 1.4 | Utilities Available | 12/19/2025 | 2/17/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
11 | 2 | HOUSE PLANS | 2/20/2026 | 4/26/2026 | 0 | 384 | 0 | 0 | 0 | 0 | ||||||||||||||||
12 | 2.1 | Purchase Standard Plans | 2/20/2026 | 4/21/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
13 | 2.2 | Architect Original Drawings | 2/21/2026 | 4/24/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
14 | 2.3 | Specifications | 2/22/2026 | 4/25/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
15 | 2.4 | Architect Manage Job | 2/23/2026 | 4/26/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
16 | 2.5 | Engineer-Loads & Spans | 2/23/2026 | 4/26/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
17 | 2.6 | Draftsman | 2/23/2026 | 4/26/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
18 | 3 | LOT SURVEY | 4/27/2026 | 7/3/2026 | 0 | 384 | 0 | 0 | 0 | 0 | ||||||||||||||||
19 | 3.1 | House & Driveway | 4/27/2026 | 6/28/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
20 | 3.2 | Well Locaton | 4/28/2026 | 6/29/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
21 | 3.3 | Septic Location | 5/1/2026 | 6/30/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
22 | 3.4 | Fire Hydrant & Truck Access | 5/2/2026 | 7/3/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
23 | 3.5 | Plot Plan | 5/2/2026 | 7/3/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
24 | 4 | FINANCIAL - LOAN | 7/4/2026 | 9/7/2026 | 0 | 384 | 0 | 0 | 0 | 0 | ||||||||||||||||
25 | 4.1 | Land Cost | 7/4/2026 | 9/4/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
26 | 4.2 | Interest on Land | 7/5/2026 | 9/5/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
27 | 4.3 | Interest on Const. Loan | 7/6/2026 | 9/6/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
28 | 4.4 | Points, Etc. | 7/7/2026 | 9/7/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
29 | 5 | SEWER & WATER HOOKUP | 1/9/2026 | 3/10/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
30 | 6 | HEALTH PERMIT | 1/9/2026 | 3/14/2026 | 0 | 376 | 0 | 0 | 0 | 0 | ||||||||||||||||
31 | 6.1 | Fees | 1/9/2026 | 3/10/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
32 | 6.2 | Percolation Test | 1/10/2026 | 3/13/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
33 | 6.3 | Soils Engineer | 1/11/2026 | 3/14/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
34 | 7 | INSURANCE | 1/12/2026 | 3/15/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
35 | 8 | LOT CLOSING COSTS | 1/13/2026 | 3/16/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
36 | 9 | BUILDING PERMITS | 1/16/2026 | 3/17/2026 | 0 | 360 | 0 | 0 | 0 | 0 | ||||||||||||||||
37 | 9.1 | Fees | 1/16/2026 | 3/17/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
38 | 9.2 | Inspection Schedule | 1/16/2026 | 3/17/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
39 | 10 | PRELIMINARY LIST ONLY | 1/17/2026 | 3/20/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
40 | 11 | BUILD PHASE | 1/18/2026 | 3/21/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
41 | 12 | SPECIAL & DRY IN MATERIALS | 1/20/2026 | 3/24/2026 | 0 | 368 | 0 | 0 | 0 | 0 | ||||||||||||||||
42 | 12.1 | Rough Hardware, Misc. | 1/20/2026 | 3/23/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
43 | 12.2 | Lolly Columns | 1/23/2026 | 3/24/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
44 | 12.3 | Steel Beams | 1/23/2026 | 3/24/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
45 | 12.4 | Rough Lumber, Trusses | 1/23/2026 | 3/24/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
46 | 13 | WINDOWS/OPENINGS | 1/25/2026 | 3/30/2026 | 0 | 376 | 0 | 0 | 0 | 0 | ||||||||||||||||
47 | 13.1 | Windows, Grills, Screens | 1/25/2026 | 3/28/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
48 | 13.2 | Exterior Doors,Screens | 1/26/2026 | 3/29/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
49 | 13.3 | Skylights and Light Tubes | 1/27/2026 | 3/30/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
50 | 14 | DEMOLITION | 1/30/2026 | 3/31/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
51 | 15 | LOT CLEARING | 1/30/2026 | 4/4/2026 | 0 | 376 | 0 | 0 | 0 | 0 | ||||||||||||||||
52 | 15.1 | Debris Removal & Clearing | 1/30/2026 | 3/31/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
53 | 15.2 | Dump Fee | 1/31/2026 | 4/3/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
54 | 15.3 | Bury Stumps, etc. | 2/1/2026 | 4/4/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
55 | 16 | DRIVEWAY, rough | 2/3/2026 | 4/7/2026 | 0 | 368 | 0 | 0 | 0 | 0 | ||||||||||||||||
56 | 16.1 | Grade | 2/3/2026 | 4/6/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
57 | 16.2 | Base Rock, Culverts | 2/6/2026 | 4/7/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
58 | 17 | UTILITIES | 2/6/2026 | 4/10/2026 | 0 | 368 | 0 | 0 | 0 | 0 | ||||||||||||||||
59 | 17.1 | Temporary at startup | 2/6/2026 | 4/7/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
60 | 17.2 | Transfer to permanent | 2/7/2026 | 4/10/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
61 | 18 | WELL or PUBLIC WATER | 2/8/2026 | 4/11/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
62 | 19 | SEPTIC or PUBLIC SEWER | 2/9/2026 | 4/12/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
63 | 20 | LAYOUT HOUSE FOOTPRINT | 2/13/2026 | 4/14/2026 | 0 | 360 | 0 | 0 | 0 | 0 | ||||||||||||||||
64 | 20.1 | Establish Finish Floor Height | 2/13/2026 | 4/14/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
65 | 20.2 | Set Back Distances | 2/13/2026 | 4/14/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
66 | 21 | DIG FOUNDATION | 2/13/2026 | 4/14/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
67 | 22 | ROCK PROBLEM | 2/14/2026 | 4/17/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
68 | 23 | PREPARE FOR FOOTINGS | 2/16/2026 | 4/20/2026 | 0 | 368 | 0 | 0 | 0 | 0 | ||||||||||||||||
69 | 23.1 | Lay out and excavate | 2/16/2026 | 4/19/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
70 | 23.2 | Form, Rebar, Grade Pegs | 2/17/2026 | 4/20/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
71 | 24 | POUR FOOTINGS & PADS | 2/20/2026 | 4/21/2026 | 0 | 360 | 0 | 0 | 0 | 0 | ||||||||||||||||
72 | 24.1 | Yds. of Concrete | 2/20/2026 | 4/21/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
73 | 25 | SET BRICK POINTS | 2/20/2026 | 4/21/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
74 | 26 | TERMITE TREATMENT | 2/21/2026 | 4/24/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
75 | 27 | RADON CONTROL | 2/22/2026 | 4/25/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
76 | 28 | FOUNDATION WALLS | 2/24/2026 | 5/2/2026 | 0 | 384 | 0 | 0 | 0 | 0 | ||||||||||||||||
77 | 28.1 | Block/Course | 2/24/2026 | 4/27/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
78 | 28.2 | Piers | 2/27/2026 | 4/28/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
79 | 28.3 | Pour Wall, Yds. Of Concrete | 2/27/2026 | 4/28/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
80 | 28.4 | Lintels, Rebar | 2/27/2026 | 4/28/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
81 | 28.5 | Parging | 2/28/2026 | 5/1/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
82 | 28.6 | Cement, Sand, etc. | 3/1/2026 | 5/2/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
83 | 29 | WATERPROOF FOUNDATION. | 3/2/2026 | 5/3/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
84 | 30 | COLUMNS/BEAMS SET | 3/3/2026 | 5/4/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
85 | 31 | UNDERGROUND PLUMBING | 3/6/2026 | 5/5/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
86 | 32 | BRICK/STONE, to finish grade | 3/6/2026 | 5/5/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
87 | 33 | GARAGE DOORS | 3/7/2026 | 5/9/2026 | 0 | 368 | 0 | 0 | 0 | 0 | ||||||||||||||||
88 | 33.1 | Openers | 3/7/2026 | 5/8/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
89 | 33.2 | Trim, Backing, Weatherstrip | 3/8/2026 | 5/9/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
90 | 34 | DRAIN TILE | 3/9/2026 | 5/10/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
91 | 35 | FIRE PLACE - INTERIOR | 3/13/2026 | 5/12/2026 | 0 | 360 | 0 | 0 | 0 | 0 | ||||||||||||||||
92 | 35.1 | Pour Hearth | 3/13/2026 | 5/12/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
93 | 35.2 | Firebox, or Set Prefab | 3/13/2026 | 5/12/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
94 | 35.3 | Brick or Stone Facing | 3/13/2026 | 5/12/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
95 | 36 | PREPARE CONC. SLABS ETC. | 3/15/2026 | 5/19/2026 | 0 | 384 | 0 | 0 | 0 | 0 | ||||||||||||||||
96 | 36.1 | Gravel, Wire, Poly, Grade Stakes | 3/15/2026 | 5/16/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
97 | 36.2 | Labor to Prepare for Slab | 3/16/2026 | 5/17/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
98 | 36.3 | Rebar, Wire, form boards | 3/17/2026 | 5/18/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
99 | 36.4 | Labor-Prepare, Form other Conc. | 3/20/2026 | 5/19/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||
100 | 36.5 | Deck & Post Hole footings, etc. | 3/20/2026 | 5/19/2026 | 0 | 360 | 0 | 0 | Open | Medium | 0 | 0 | ||||||||||||||