3
4
New Home Construction Budget11/1/2026
5
Color
WBS Number
Task name / TitleAssigned to
Planned start date
Planned end date
Deadline
Progress (%)
Duration (hours)
Estimated hours
Time log (minutes)
StatusPriority
Task description
Cost
Actual cost
6
1ZONING2/1/20274/5/202703680000
7
1.1Land Use2/1/20274/4/2027036000OpenMedium00
8
1.2Easements, Set Backs2/4/20274/5/2027036000OpenMedium00
9
1.3Access, Street Improvements2/4/20274/5/2027036000OpenMedium00
10
1.4Utilities Available2/4/20274/5/2027036000OpenMedium00
11
2HOUSE PLANS4/8/20276/12/202703840000
12
2.1Purchase Standard Plans4/8/20276/7/2027036000OpenMedium00
13
2.2Architect Original Drawings4/9/20276/10/2027036000OpenMedium00
14
2.3Specifications4/10/20276/11/2027036000OpenMedium00
15
2.4Architect Manage Job4/11/20276/12/2027036000OpenMedium00
16
2.5Engineer-Loads & Spans4/11/20276/12/2027036000OpenMedium00
17
2.6Draftsman4/11/20276/12/2027036000OpenMedium00
18
3LOT SURVEY6/13/20278/19/202703840000
19
3.1House & Driveway6/13/20278/14/2027036000OpenMedium00
20
3.2Well Locaton6/14/20278/15/2027036000OpenMedium00
21
3.3Septic Location6/17/20278/16/2027036000OpenMedium00
22
3.4Fire Hydrant & Truck Access6/18/20278/19/2027036000OpenMedium00
23
3.5Plot Plan6/18/20278/19/2027036000OpenMedium00
24
4FINANCIAL - LOAN8/20/202710/24/202703840000
25
4.1Land Cost8/20/202710/21/2027036000OpenMedium00
26
4.2Interest on Land8/21/202710/22/2027036000OpenMedium00
27
4.3Interest on Const. Loan8/22/202710/23/2027036000OpenMedium00
28
4.4Points, Etc.8/23/202710/24/2027036000OpenMedium00
29
5SEWER & WATER HOOKUP2/25/20274/26/2027036000OpenMedium00
30
6HEALTH PERMIT2/25/20274/30/202703760000
31
6.1Fees2/25/20274/26/2027036000OpenMedium00
32
6.2Percolation Test2/26/20274/29/2027036000OpenMedium00
33
6.3Soils Engineer2/27/20274/30/2027036000OpenMedium00
34
7INSURANCE2/28/20275/1/2027036000OpenMedium00
35
8LOT CLOSING COSTS3/1/20275/2/2027036000OpenMedium00
36
9BUILDING PERMITS3/4/20275/3/202703600000
37
9.1Fees3/4/20275/3/2027036000OpenMedium00
38
9.2Inspection Schedule3/4/20275/3/2027036000OpenMedium00
39
10PRELIMINARY LIST ONLY3/5/20275/6/2027036000OpenMedium00
40
11BUILD PHASE3/6/20275/7/2027036000OpenMedium00
41
12SPECIAL & DRY IN MATERIALS3/8/20275/10/202703680000
42
12.1Rough Hardware, Misc.3/8/20275/9/2027036000OpenMedium00
43
12.2Lolly Columns3/11/20275/10/2027036000OpenMedium00
44
12.3Steel Beams3/11/20275/10/2027036000OpenMedium00
45
12.4Rough Lumber, Trusses3/11/20275/10/2027036000OpenMedium00
46
13WINDOWS/OPENINGS3/13/20275/16/202703760000
47
13.1Windows, Grills, Screens3/13/20275/14/2027036000OpenMedium00
48
13.2Exterior Doors,Screens3/14/20275/15/2027036000OpenMedium00
49
13.3Skylights and Light Tubes3/15/20275/16/2027036000OpenMedium00
50
14DEMOLITION3/18/20275/17/2027036000OpenMedium00
51
15LOT CLEARING3/18/20275/21/202703760000
52
15.1Debris Removal & Clearing3/18/20275/17/2027036000OpenMedium00
53
15.2Dump Fee3/19/20275/20/2027036000OpenMedium00
54
15.3Bury Stumps, etc.3/20/20275/21/2027036000OpenMedium00
55
16DRIVEWAY, rough3/22/20275/24/202703680000
56
16.1Grade3/22/20275/23/2027036000OpenMedium00
57
16.2Base Rock, Culverts3/25/20275/24/2027036000OpenMedium00
58
17UTILITIES3/25/20275/27/202703680000
59
17.1Temporary at startup3/25/20275/24/2027036000OpenMedium00
60
17.2Transfer to permanent3/26/20275/27/2027036000OpenMedium00
61
18WELL or PUBLIC WATER3/27/20275/28/2027036000OpenMedium00
62
19SEPTIC or PUBLIC SEWER3/28/20275/29/2027036000OpenMedium00
63
20LAYOUT HOUSE FOOTPRINT4/1/20275/31/202703600000
64
20.1Establish Finish Floor Height4/1/20275/31/2027036000OpenMedium00
65
20.2Set Back Distances4/1/20275/31/2027036000OpenMedium00
66
21DIG FOUNDATION4/1/20275/31/2027036000OpenMedium00
67
22ROCK PROBLEM4/2/20276/3/2027036000OpenMedium00
68
23PREPARE FOR FOOTINGS4/4/20276/6/202703680000
69
23.1Lay out and excavate4/4/20276/5/2027036000OpenMedium00
70
23.2Form, Rebar, Grade Pegs4/5/20276/6/2027036000OpenMedium00
71
24POUR FOOTINGS & PADS4/8/20276/7/202703600000
72
24.1Yds. of Concrete4/8/20276/7/2027036000OpenMedium00
73
25SET BRICK POINTS4/8/20276/7/2027036000OpenMedium00
74
26TERMITE TREATMENT4/9/20276/10/2027036000OpenMedium00
75
27RADON CONTROL4/10/20276/11/2027036000OpenMedium00
76
28FOUNDATION WALLS4/12/20276/18/202703840000
77
28.1Block/Course4/12/20276/13/2027036000OpenMedium00
78
28.2Piers4/15/20276/14/2027036000OpenMedium00
79
28.3Pour Wall, Yds. Of Concrete4/15/20276/14/2027036000OpenMedium00
80
28.4Lintels, Rebar4/15/20276/14/2027036000OpenMedium00
81
28.5Parging4/16/20276/17/2027036000OpenMedium00
82
28.6Cement, Sand, etc.4/17/20276/18/2027036000OpenMedium00
83
29WATERPROOF FOUNDATION.4/18/20276/19/2027036000OpenMedium00
84
30COLUMNS/BEAMS SET4/19/20276/20/2027036000OpenMedium00
85
31UNDERGROUND PLUMBING4/22/20276/21/2027036000OpenMedium00
86
32BRICK/STONE, to finish grade4/22/20276/21/2027036000OpenMedium00
87
33GARAGE DOORS4/23/20276/25/202703680000
88
33.1Openers4/23/20276/24/2027036000OpenMedium00
89
33.2Trim, Backing, Weatherstrip4/24/20276/25/2027036000OpenMedium00
90
34DRAIN TILE4/25/20276/26/2027036000OpenMedium00
91
35FIRE PLACE - INTERIOR4/29/20276/28/202703600000
92
35.1Pour Hearth4/29/20276/28/2027036000OpenMedium00
93
35.2Firebox, or Set Prefab4/29/20276/28/2027036000OpenMedium00
94
35.3Brick or Stone Facing4/29/20276/28/2027036000OpenMedium00
95
36PREPARE CONC. SLABS ETC.5/1/20277/5/202703840000
96
36.1Gravel, Wire, Poly, Grade Stakes5/1/20277/2/2027036000OpenMedium00
97
36.2Labor to Prepare for Slab5/2/20277/3/2027036000OpenMedium00
98
36.3Rebar, Wire, form boards5/3/20277/4/2027036000OpenMedium00
99
36.4
Labor-Prepare, Form other Conc.
5/6/20277/5/2027036000OpenMedium00
100
36.5
Deck & Post Hole footings, etc.
5/6/20277/5/2027036000OpenMedium00