New Home Construction Budget9/23/2026
5
Color
WBS Number
Task name / TitleAssigned to
Planned start date
Planned end date
Deadline
Progress (%)
Duration (hours)
Estimated hours
Time log (minutes)
StatusPriority
Task description
Cost
Actual cost
6
1ZONING12/24/20262/25/202703680000
7
1.1Land Use12/24/20262/24/2027036000OpenMedium00
8
1.2Easements, Set Backs12/27/20262/25/2027036000OpenMedium00
9
1.3Access, Street Improvements12/27/20262/25/2027036000OpenMedium00
10
1.4Utilities Available12/27/20262/25/2027036000OpenMedium00
11
2HOUSE PLANS2/28/20275/4/202703840000
12
2.1Purchase Standard Plans2/28/20274/29/2027036000OpenMedium00
13
2.2Architect Original Drawings3/1/20275/2/2027036000OpenMedium00
14
2.3Specifications3/2/20275/3/2027036000OpenMedium00
15
2.4Architect Manage Job3/3/20275/4/2027036000OpenMedium00
16
2.5Engineer-Loads & Spans3/3/20275/4/2027036000OpenMedium00
17
2.6Draftsman3/3/20275/4/2027036000OpenMedium00
18
3LOT SURVEY5/5/20277/11/202703840000
19
3.1House & Driveway5/5/20277/6/2027036000OpenMedium00
20
3.2Well Locaton5/6/20277/7/2027036000OpenMedium00
21
3.3Septic Location5/9/20277/8/2027036000OpenMedium00
22
3.4Fire Hydrant & Truck Access5/10/20277/11/2027036000OpenMedium00
23
3.5Plot Plan5/10/20277/11/2027036000OpenMedium00
24
4FINANCIAL - LOAN7/12/20279/15/202703840000
25
4.1Land Cost7/12/20279/12/2027036000OpenMedium00
26
4.2Interest on Land7/13/20279/13/2027036000OpenMedium00
27
4.3Interest on Const. Loan7/14/20279/14/2027036000OpenMedium00
28
4.4Points, Etc.7/15/20279/15/2027036000OpenMedium00
29
5SEWER & WATER HOOKUP1/17/20273/18/2027036000OpenMedium00
30
6HEALTH PERMIT1/17/20273/22/202703760000
31
6.1Fees1/17/20273/18/2027036000OpenMedium00
32
6.2Percolation Test1/18/20273/21/2027036000OpenMedium00
33
6.3Soils Engineer1/19/20273/22/2027036000OpenMedium00
34
7INSURANCE1/20/20273/23/2027036000OpenMedium00
35
8LOT CLOSING COSTS1/21/20273/24/2027036000OpenMedium00
36
9BUILDING PERMITS1/24/20273/25/202703600000
37
9.1Fees1/24/20273/25/2027036000OpenMedium00
38
9.2Inspection Schedule1/24/20273/25/2027036000OpenMedium00
39
10PRELIMINARY LIST ONLY1/25/20273/28/2027036000OpenMedium00
40
11BUILD PHASE1/26/20273/29/2027036000OpenMedium00
41
12SPECIAL & DRY IN MATERIALS1/28/20274/1/202703680000
42
12.1Rough Hardware, Misc.1/28/20273/31/2027036000OpenMedium00
43
12.2Lolly Columns1/31/20274/1/2027036000OpenMedium00
44
12.3Steel Beams1/31/20274/1/2027036000OpenMedium00
45
12.4Rough Lumber, Trusses1/31/20274/1/2027036000OpenMedium00
46
13WINDOWS/OPENINGS2/2/20274/7/202703760000
47
13.1Windows, Grills, Screens2/2/20274/5/2027036000OpenMedium00
48
13.2Exterior Doors,Screens2/3/20274/6/2027036000OpenMedium00
49
13.3Skylights and Light Tubes2/4/20274/7/2027036000OpenMedium00
50
14DEMOLITION2/7/20274/8/2027036000OpenMedium00
51
15LOT CLEARING2/7/20274/12/202703760000
52
15.1Debris Removal & Clearing2/7/20274/8/2027036000OpenMedium00
53
15.2Dump Fee2/8/20274/11/2027036000OpenMedium00
54
15.3Bury Stumps, etc.2/9/20274/12/2027036000OpenMedium00
55
16DRIVEWAY, rough2/11/20274/15/202703680000
56
16.1Grade2/11/20274/14/2027036000OpenMedium00
57
16.2Base Rock, Culverts2/14/20274/15/2027036000OpenMedium00
58
17UTILITIES2/14/20274/18/202703680000
59
17.1Temporary at startup2/14/20274/15/2027036000OpenMedium00
60
17.2Transfer to permanent2/15/20274/18/2027036000OpenMedium00
61
18WELL or PUBLIC WATER2/16/20274/19/2027036000OpenMedium00
62
19SEPTIC or PUBLIC SEWER2/17/20274/20/2027036000OpenMedium00
63
20LAYOUT HOUSE FOOTPRINT2/21/20274/22/202703600000
64
20.1Establish Finish Floor Height2/21/20274/22/2027036000OpenMedium00
65
20.2Set Back Distances2/21/20274/22/2027036000OpenMedium00
66
21DIG FOUNDATION2/21/20274/22/2027036000OpenMedium00
67
22ROCK PROBLEM2/22/20274/25/2027036000OpenMedium00
68
23PREPARE FOR FOOTINGS2/24/20274/28/202703680000
69
23.1Lay out and excavate2/24/20274/27/2027036000OpenMedium00
70
23.2Form, Rebar, Grade Pegs2/25/20274/28/2027036000OpenMedium00
71
24POUR FOOTINGS & PADS2/28/20274/29/202703600000
72
24.1Yds. of Concrete2/28/20274/29/2027036000OpenMedium00
73
25SET BRICK POINTS2/28/20274/29/2027036000OpenMedium00
74
26TERMITE TREATMENT3/1/20275/2/2027036000OpenMedium00
75
27RADON CONTROL3/2/20275/3/2027036000OpenMedium00
76
28FOUNDATION WALLS3/4/20275/10/202703840000
77
28.1Block/Course3/4/20275/5/2027036000OpenMedium00
78
28.2Piers3/7/20275/6/2027036000OpenMedium00
79
28.3Pour Wall, Yds. Of Concrete3/7/20275/6/2027036000OpenMedium00
80
28.4Lintels, Rebar3/7/20275/6/2027036000OpenMedium00
81
28.5Parging3/8/20275/9/2027036000OpenMedium00
82
28.6Cement, Sand, etc.3/9/20275/10/2027036000OpenMedium00
83
29WATERPROOF FOUNDATION.3/10/20275/11/2027036000OpenMedium00
84
30COLUMNS/BEAMS SET3/11/20275/12/2027036000OpenMedium00
85
31UNDERGROUND PLUMBING3/14/20275/13/2027036000OpenMedium00
86
32BRICK/STONE, to finish grade3/14/20275/13/2027036000OpenMedium00
87
33GARAGE DOORS3/15/20275/17/202703680000
88
33.1Openers3/15/20275/16/2027036000OpenMedium00
89
33.2Trim, Backing, Weatherstrip3/16/20275/17/2027036000OpenMedium00
90
34DRAIN TILE3/17/20275/18/2027036000OpenMedium00
91
35FIRE PLACE - INTERIOR3/21/20275/20/202703600000
92
35.1Pour Hearth3/21/20275/20/2027036000OpenMedium00
93
35.2Firebox, or Set Prefab3/21/20275/20/2027036000OpenMedium00
94
35.3Brick or Stone Facing3/21/20275/20/2027036000OpenMedium00
95
36PREPARE CONC. SLABS ETC.3/23/20275/27/202703840000
96
36.1Gravel, Wire, Poly, Grade Stakes3/23/20275/24/2027036000OpenMedium00
97
36.2Labor to Prepare for Slab3/24/20275/25/2027036000OpenMedium00
98
36.3Rebar, Wire, form boards3/25/20275/26/2027036000OpenMedium00
99
36.4
Labor-Prepare, Form other Conc.
3/28/20275/27/2027036000OpenMedium00
100
36.5
Deck & Post Hole footings, etc.
3/28/20275/27/2027036000OpenMedium00