Incentive "Sweet-Spots " for North Carolina, South Carolina, Georgia, Tennessee and Alabama
3
4
North Carolina
5
TVA Territory Generation Partners ProgramSystem Size - 200kW
6
Installer Contract Cost$1,320,000.00($6.60/watt)
7
35% Corporate Tax Credit ($2.5M Max)$(462,000.00)$92,400 Annual Corporate Tax Deduction For 5 Years
8
30% Federal Treasury Grant$(396,000.00)Federal Treasury Grant Program
9
Base Cost w/o Production Incentives$462,000.00
10
11
TVA Generation Partners Program$(857,670.00)(Avg. $.22/kWh, $57k/Year. 15 year Contract)
12
Cost After All Incentives$(395,670.00)
13
TVA Territory Midsized Renewable Standard OfferSystem Size - 1.25mW
14
Installer Contract Cost$7,100,000.00(5.68/watt)
15
35% Corporate Tax Credit ($2.5M Max)$(2,500,000.00)$500k Annual Corporate Tax Deduction For 5 Years
16
30% Federal Treasury Grant$(2,130,000.00)Federal Treasury Grant Program
17
Base Cost w/o Production Incentives$2,470,000.00
18
19
TVA Mid-Sized Renewable Standard Program$(1,350,000.00)(Avg. $.056/kWh, $90k/Year. 15 year Contract)
20
Cost After All Incentives$1,120,000.00
21
PEC TerritorySystem Size - 1.25mW
22
Installer Contract Cost$7,100,000.00(5.68/watt)
23
35% Corporate Tax Credit$(2,500,000.00)$500k Annual Corporate Tax Deduction For 5 Years
24
30% Federal Treasury Grant$(2,130,000.00)Federal Treasury Grant Program
25
Base Cost w/o Production Incentives$2,470,000.00
26
Net Metering Cost Savings (Max 1mW)$(3,550,000.00)(Avg. $.11/kWh, $142k/Year. Life of System (25 Years)
27
PEC SunSense Commercial PV Program$(2,339,000.00)(Avg. $.18/kWh, $117k/Year. 20 year Contract)
28
Cost After All Incentives$131,000.00
29
Duke TerritorySystem Size - 1.25mW
30
Installer Contract Cost$7,100,000.00(5.68/watt)
31
35% Corporate Tax Credit ($2.5M Max)$(2,500,000.00)$500k Annual Corporate Tax Deduction For 5 Years
32
30% Federal Treasury Grant$(2,130,000.00)Federal Treasury Grant Program
33
Base Cost w/o Production Incentives$2,470,000.00
34
Net Metering Cost Savings (Max 1mW)$(3,550,000.00)(Avg. $.11/kWh, $142k/Year. Life of System (25 Years)
35
Duke - Standard Purchase Offer for RECs$(604,268.00)(Avg. $.031/kWh, $130k/Year. 15 year Contract)
36
Cost After All Incentives$1,865,732.00
37
South Carolina
38
All Investor Owned UtilitiesSystem Size - 25kW
39
Installer Contract Cost$140,000.00($5.60/watt)
40
25% Corporate Tax Credit ($35k Max)$(35,000.00)$3500 Annual Corporate Tax Deduction For 10 Years
41
30% Federal Treasury Grant$(42,000.00)Federal Treasury Grant Program
42
Net Metering Cost Savings (100kW Max)$(90,750.00)(Avg. $.11/kWh, $4k/Year. Life of System (25 Years)
43
Cost After All Incentives$(27,750.00)
44
All UtilitiesSystem Size ~ 100kW
45
ConserFund Revolving Loan Program -
46
The South Carolina Energy Office offers the ConserFund Loan Program to fund energy efficiency improvements in state agencies, local governments, public colleges and universities, school districts and non-profit organizations. The ConserFund Loan Program will fund a variety of efficiency improvements, but priority is given to projects that have a fast energy savings payback. Generally, ConserFund loans are to be used on retrofits of existing buildings. However, ConserFund may be used to finance energy recovery systems, ground source heat pumps, biomass, solar, and other renewable energy systems in new construction facilities.
Organizations may finance one or multiple projects, covering up to 100% of eligible project costs, from $25,000 to $500,000. Implementation of the energy efficiency improvement must begin within six months of the loan closing and the proposed energy improvement must have long-term cost reductions to qualify.
47
48
49
50
51
52
53
Georgia
54
Georgia Power Solar Buyback ProgramSystem Size - 100kW
55
Installer Contract Cost$650,000.00($6.50/watt)
56
30% Federal Treasury Grant$(195,000.00)Federal Treasury Grant Program
57
Base Cost w/o Production Incentives$455,000.00
58
59
Net Metering Cost Savings (100kW Max)$(350,000.00)(Avg. $.11/kWh, $14k/Year. Life of System (25 Years)
60
Georgia Solar Buy Back Program$(110,000.00)(Avg. $.17/kWh, $22k/Year. 5 year Contract)
61
Cost After All Incentives$(5,000.00)
62
TVA TerritorySystem Size - 200kW
63
Installer Contract Cost$1,300,000.00($6.50/watt)
64
30% Federal Treasury Grant$(390,000.00)Federal Treasury Grant Program
65
Base Cost w/o Production Incentives$910,000.00
66
67
TVA Generation Partners Program$(900,000.00)(Avg. $.22/kWh, $60k/Year. 15 year Contract)
68
Cost After All Incentives$10,000.00
69
Alabama - Alabama Territory is not worth enterning unless in TVA Territory (10 year payback required for Loan Incentive)
70
Alabama SAVES Revolving Loan Program (TVA Territory Only)System Size - 1mW$4,000,000 Loan from SAVES Program (<10 year payback)
71
Installer Contract Cost$6,000,000.00($6.00/watt)
72
30% Federal Treasury Grant$(2,000,000.00)Federal Treasury Grant Program
73
Base Cost w/o Production Incentives$4,000,000.00
74
75
TVA Mid-Sized Renewable Standard Program$(1,950,000.00)(Avg. $.056/kWh, $72k/Year. 15 year Contract)
76
Cost After All Incentives$2,050,000.00
77
Local Government (Schools) Revolving Loan Program (TVA Territory Only)System Size - 75kW$500,000 Loan from AL (<10 year payback)
78
Installer Contract Cost$500,000.00($6.66/watt)
79
30% Federal Treasury Grant$(150,000.00)Federal Treasury Grant Program
80
Base Cost w/o Production Incentives$350,000.00
81
82
TVA Generation Partners Program$(315,000.00)(Avg. $.22/kWh, $21k/Year. 15 year Contract)
83
Cost After All Incentives$35,000.00
84
Mississippi - Mississippi Territory is not worth enterning unless in TVA Territory (7 year payback required for Loan Incentive)
85
Alabama SAVES Revolving Loan Program (TVA Territory Only)System Size - 50kW$300,000 Loan from State Loan Program (<7 year payback)
86
Installer Contract Cost$300,000.00($6.00/watt)
87
30% Federal Treasury Grant$(100,000.00)Federal Treasury Grant Program
88
Base Cost w/o Production Incentives$200,000.00
89
90
TVA Generation Partners Program$(210,000.00)(Avg. $.22/kWh, $14k/Year. 15 year Contract)
91
Cost After All Incentives$(10,000.00)