Channel Strategy, Selection, and Management Plan
2
Project InformationGantt Chart (End of Week)
3
IDProject NameOwnerBudgetDurationStartEnd9-Jul16-Jul23-Jul30-Jul6-Aug13-Aug20-AugStatus
4
1Channel Strategy, Selection, and Management PlanR. Ihrig 95,600 33 days5-Jul18-Aug
5
Planned (to date): 85,200 305-Jul13-Aug
6
Actual (to date): 89,000 30Actual
7
Variance:(3,800)0 Comments: Provide comments on overall health of the project.
8
Dependencies on:
9
Dependencies for:
10
11
IDDeliverable Name/Task NameAssigned ToCostDurationStartEnd9-Jul16-Jul23-Jul30-Jul6-Aug13-Aug20-AugStatus
12
1.1Channel StrategyR. Ihrig 4,800 5 days5-Jul9-Jul
13
1.1.1Define objectivesR. Ihrig 800 0.5 days5-Jul5-Jul
14
1.1.2Develop channel schemaS. Abbas 800 1 day5-Jul6-Jul
15
1.1.3Assess channel pros and consS. Abbas 2,400 3 days6-Jul9-Jul
16
1.1.4Determine channel alignment with objectivesR. Ihrig 800 0.5 days9-Jul9-Jul
17
Summary
18
Planned (to date): 4,800 55-Jul9-JulComments: Provide comments.
19
Actual (to date): 6,000 5Actual
20
Variance:(1,200)0
21
Dependencies on:
22
Dependencies for:
23
Comments:
24
25
IDDeliverable Name/Task NameAssigned ToCostDurationStartEnd9-Jul16-Jul23-Jul30-Jul6-Aug13-Aug20-AugStatus
26
1.2Channel PlanD. Daniels 24,000 7 days12-Jul20-Jul
27
1.2.1Develop channel tactical calendarB. Gage 1,200 1 day12-Jul12-Jul
28
1.2.2Develop high-level positioning for preferred channel typeR. Ihrig 1,600 1 day12-Jul12-Jul
29
1.2.3Develop pricing, discounts, and promotion guidelinesR. Ihrig, D. Daniels, S. Abbas 8,800 2 days13-Jul14-Jul
30
1.2.4Define channel functionsD. Daniels 4,000 2 days15-Jul16-Jul
31
1.2.5Develop a budget for overall channel managementB. Gage, R. Ihrig, D. Daniels, S. Abbas 5,600 1 day19-Jul19-Jul
32
1.2.6Develop channel planS. Abbas, D. Daniels 2,800 1 day20-Jul20-Jul
33
Summary
34
Planned (to date): 24,000 712-Jul20-JulComments: Provide comments.
35
Actual (to date): 25,400 7Actual
36
Variance:(1,400)0
37
Dependencies on:
38
Dependencies for:
39
40
IDDeliverable Name/Task NameAssigned ToCostDurationStartEnd9-Jul16-Jul23-Jul30-Jul6-Aug13-Aug20-AugStatus
41
1.3Channel SelectionR. Ihrig 42,400 13 days21-Jul6-Aug
42
1.3.1Develop channel partner selection criteriaR. Ihrig, D. Daniels 3,600 1 day21-Jul21-Jul
43
1.3.2Create a channel selection matrixD. Daniels, S. Abbas 5,600 2 days22-Jul23-Jul
44
1.3.3Identify target channel partnersR. Ihrig, D. Daniels, S. Abbas 13,200 3 days26-Jul28-Jul
45
1.3.4Develop channel partners profileD. Daniels, S. Abbas 5,600 2 days29-Jul30-Jul
46
1.3.5Determine contractual termsR. Ihrig, S. Ito 6,400 2 days2-Aug3-Aug
47
1.3.6Negotiate contractR. Ihrig, S. Ito 6,400 2 days4-Aug5-Aug
48
1.3.7Sign off on contractR. Ihrig 1,600 1 day6-Aug6-Aug
49
Summary
50
Planned (to date): 42,400 1321-Jul6-AugComments: Provide comments.
51
Actual (to date): 43,000 13Actual
52
Variance:(600)0
53
Dependencies on:
54
Dependencies for:
55
56
IDDeliverable Name/Task NameAssigned ToCostDurationStartEnd9-Jul16-Jul23-Jul30-Jul6-Aug13-Aug20-AugStatus
57
1.4Channel ManagementR. Ihrig 24,400 8 days9-Aug18-Aug
58
1.4.1Define training needsS. Abbas, D. Daniels 2,800 1 day9-Aug9-Aug
59
1.4.2Define promotion needsD. Daniels, R. Ihrig 7,200 2 days10-Aug11-Aug
60
1.4.3Develop timing requirements and budgetR. Ihrig, B. Gage 2,800 1 day12-Aug12-Aug
61
1.4.4Develop a channel communication planB. Gage 1,200 1 day13-Aug13-Aug
62
1.4.5Determine channel performance criteriaR. Ihrig 1,600 1 day16-Aug16-Aug
63
1.4.6Develop channel marketing management planD. Daniels, S. Abbas, R. Ihrig 8,800 2 days17-Aug18-Aug
64
Summary
65
Planned (to date): 14,000 59-AugtodayComments: Provide comments.
66
Actual (to date): 14,600 5Actual
67
Variance:(600)0
68
Dependencies on:
69
Dependencies for:
70
71
Planned
72
Planned to date
73
Actual
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100