| A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | R | S | T | U | X | Y | Z | AA | AB | BT | BU | BV | BW | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Timestamp | Preservation Treatment | State/Province | Year | Lane Distance Completed | Lane Distance Completed - Lane Unit | Lane Width | Lane Width - Unit | Total Treatment Cost | Total Treatment Cost - Currency | Work Performed By | Treatment Service Life | Estimated Life Extension | Quantity 1 | Quantity 1 - Unit | Quantity 1 - Material Type | Quantity 2 | Quantity 2 - Unit | Quantity 2 - Unit | Quantity 2 - Material Type | Comments | Name | Phone Number | USD Cost Per SY | CAD Cost Per SM | USD Quantity Cost Per Lane Mile | CAD Quantity Cost Per Lane Kilometer | |
2 | 10/4/2021 15:03:45 | Chip Seal (Single) | Manitoba | 2020 | 696 | Kilometer | 3.8 | Meter | 10697793 | CAD | Contractor | 7 | 10 | 696 | Lane Kilometers | lane km of chip seal | Ryan Thompson | ryan.thompson@gov.mb.ca | 2043911361 | $2.61 | $3.95 | $19,065.19 | $15,000.00 | |||||
3 | 10/4/2021 15:09:15 | Chip Seal (Double) | Manitoba | 2020 | 60 | Kilometer | 3.8 | Meter | 1521000 | CAD | Contractor | 7 | 10 | 60 | Lane Kilometers | lane km | Ryan Thompson | Ryan.Thompson@gov.mb.ca | 2043911361 | $4.41 | $6.67 | $32,214.21 | $25,350.00 | |||||
4 | 10/4/2021 15:11:47 | Micro-surfacing (Two Lift) | Manitoba | 2020 | 536 | Kilometer | 3.8 | Meter | 15469521 | CAD | Contractor | 7 | 10 | 536 | Lane Kilometers | lane km | Ryan Thompson | Ryan.Thompson@gov.mb.ca | 2043911361 | $5.02 | $7.60 | $36,677.38 | $28,861.00 | |||||
5 | 10/4/2021 16:16:22 | Cold-In-Place Recycling | Iowa | 2019 | 132.9 | Mile | 12 | Feet | 29229000 | USD | Contractor | 935300 | Square Yards | Recycling Asphalt Pavement | 3600 | Tons | Asphalt Stabilizing Agent | Cold-in-place recycled pavement is typically resurfaced with an HMA overlay, so the life of the recycled pavement is impacted by the HMA resurfacing. | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $3.81 | $5.70 | $26,835.03 | $20,841.37 | |||
6 | 10/4/2021 16:25:08 | Cold-In-Place Recycling | Ontario | 2019 | 53.578 | Kilometer | 3.7 | Meter | 2,031,608.43 | CAD | Contractor | 198241 | Square Meters | CIREAM | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | $6.84 | $10.35 | $48,676.20 | $38,279.75 | |||||||
7 | 10/4/2021 16:29:19 | Hot-In-Place Recycling | Iowa | 2019 | 39.7 | Mile | 12 | Feet | 4995000 | USD | Contractor | 287700 | Square Yards | HIP Recycled Pavement | 420.5 | Tons | Asphalt Rejuvenating Agent | This is a new treatment for Iowa, so we don't have an estimate of service life or pavement life extension. | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $4.04 | $6.03 | $28,411.66 | $22,064.61 | |||
8 | 10/4/2021 16:37:25 | Concrete Pvmt Restoration | Ontario | 2019 | 1.025 | Kilometer | 3.7 | Meter | 1370928 | CAD | Contractor | 3794 | Square Meters | n/a | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | $167.51 | $253.60 | $1,085,436.30 | $874,344.55 | |||||||
9 | 10/4/2021 16:48:05 | Crack Sealing | Ontario | 2019 | 207.519 | Kilometer | 3.7 | Meter | 1184297.25 | CAD | Contractor | 207.519 | Lane Kilometers | Asphalt | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | N/A | N/A | $6.62 | $5.21 | |||||||
10 | 10/4/2021 16:52:08 | Thin HMA Overlay (US) | Iowa | 2019 | 33.9 | Mile | 12 | Feet | 3027000 | USD | Contractor | 18140 | Tons | HMA Thin Lift Surface HMA Thin Lift Surface Mix | 1317.3 | Tons | Asphalt Binder PG 58-34+EHT 90% Recovery | This treatment has only been used for six years, so service life and life extension are unknown due to limited data. | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $7.69 | $11.50 | $54,172.64 | $42,043.32 | |||
11 | 10/4/2021 16:57:07 | Hot-In-Place Recycling | Ontario | 2019 | 154.866 | Kilometer | 3.7 | Meter | 7559853.25 | CAD | Contractor | 573007 | Square Meters | n/a | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | $8.71 | $13.19 | $62,017.49 | $48,804.73 | |||||||
12 | 10/4/2021 16:58:59 | Micro-surfacing (Two Lift) | Iowa | 2019 | 188.6 | Mile | 12 | Feet | 8656000 | USD | Contractor | 4 - 6 years | 4 years | 26780 | Tons | Aggregate | 715400 | Gallons | Emulsion | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $2.55 | $3.81 | $17,921.91 | $13,916.64 | ||
13 | 10/4/2021 17:03:59 | Micro-surfacing (Single Lift) | Iowa | 2019 | 55.4 | Mile | 12 | Feet | 1332000 | USD | Contractor | 3 - 5 years | 4 years | 6780 | Tons | Aggregate | 143800 | Gallons | Emulsion | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $1.95 | $2.91 | $13,697.62 | $10,634.09 | ||
14 | 10/4/2021 17:06:24 | Joint Resealing - Concrete | Ontario | 2019 | 17.926 | Kilometer | 3.7 | Meter | 448150 | CAD | Contractor | 17.926 | Lane Kilometers | Concrete | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | N/A | N/A | $31,610.58 | $24,897.22 | |||||||
15 | 10/4/2021 17:16:24 | Crack Sealing | Iowa | 2019 | 465.7 | Mile | 12 | Feet | 2395000 | USD | Contractor | 3 - 6 Years | 3 Years | 428500 | Pounds | Crack Sealing Material | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | N/A | N/A | $920.12 | $714.64 | |||||
16 | 10/4/2021 17:20:52 | Crack Filling | Iowa | 2019 | 930.9 | Mile | 12 | Feet | 4438000 | USD | Contractor | 3 - 5 years | 2 years | 222000 | Gallons | Emulsion for Crack Filling | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | N/A | N/A | $989.69 | $768.67 | |||||
17 | 10/4/2021 17:25:06 | Joint Resealing - Concrete | Iowa | 2019 | 87.4 | Mile | 12 | Feet | 913000 | USD | Contractor | 4 - 8 years | 3 years | 79700 | Pounds | PCC Joint Sealing Material | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | N/A | N/A | $911.90 | $708.07 | |||||
18 | 10/4/2021 17:28:55 | Micro-surfacing (Two Lift) | Ontario | 2019 | 188.7 | Kilometer | 3.7 | Meter | 4985795.92 | CAD | Contractor | 698193 | Square Meters | n/a | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | $5.65 | $8.55 | $40,204.13 | $31,635.14 | |||||||
19 | 10/4/2021 17:36:12 | Thin HMA Overlay (Metric) | Ontario | 2019 | 24.828 | Kilometer | 3.7 | Meter | 901401.66 | CAD | Contractor | 91886 | Square Meters | SP 12.5 | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | $6.48 | $9.81 | $45,942.41 | $36,200.87 | |||||||
20 | 10/5/2021 12:42:02 | Cold-In-Place Recycling | Ontario | 2020 | 112.389 | Kilometer | 3.7 | Meter | 3446321.8 | CAD | Contractor | 415841 | Square Meters | CIREAM & CIR | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | $5.41 | $8.19 | $38,491.17 | $30,300.16 | |||||||
21 | 10/5/2021 12:51:19 | Concrete Pvmt Restoration | Ontario | 2020 | 0.896 | Kilometer | 3.7 | Meter | 1286608 | CAD | Contractor | 3316 | Square Meters | n/a | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | $256.35 | $388.09 | $1,694,033.87 | $1,429,564.44 | |||||||
22 | 10/5/2021 12:58:25 | Crack Sealing | Ontario | 2020 | 131.44 | Kilometer | 3.7 | Meter | 712212.5 | CAD | Contractor | 131.44 | Lane Kilometers | Asphalt | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | N/A | N/A | $7,943.51 | $6,247.15 | |||||||
23 | 10/5/2021 13:02:11 | Diamond Grinding | Ontario | 2020 | 25.45 | Kilometer | 3.7 | Meter | 1680845.25 | CAD | Contractor | 94165 | Square Meters | n/a | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | $11.79 | $17.85 | $83,513.69 | $65,915.50 | |||||||
24 | 10/5/2021 13:23:11 | Hot-In-Place Recycling | Ontario | 2020 | 110.172 | Kilometer | 3.7 | Meter | 5230021.2 | CAD | Contractor | 407640 | Square Meters | n/a | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | $8.47 | $12.83 | $60,317.03 | $47,459.36 | |||||||
25 | 10/5/2021 13:36:00 | Joint Resealing - Concrete | Ontario | 2020 | 26.618 | Kilometer | 3.7 | Meter | 57212 | CAD | Contractor | 26.618 | Lane Kilometers | n/a | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | N/A | N/A | $29,772.67 | $23,430.82 | |||||||
26 | 10/5/2021 14:16:05 | Micro-surfacing (Two Lift) | Ontario | 2020 | 179.053 | Kilometer | 3.7 | Meter | 5149020.73 | CAD | Contractor | 662498 | Square Meters | n/a | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | $5.25 | $7.95 | $37,383.82 | $29,407.37 | |||||||
27 | 10/5/2021 14:39:11 | Thin HMA Overlay (Metric) | Ontario | 2020 | 43.978 | Kilometer | 3.7 | Meter | 2033987.5 | CAD | Contractor | 162719 | Square Meters | SP 12.5 FC 1 | Shen Lai Chen | shenlai.chen@ontario.ca | 437 688 7628 | $8.26 | $12.50 | $58,644.17 | $46,226.99 | |||||||
28 | 10/7/2021 10:25:19 | Concrete Pvmt Restoration | Indiana | 2021 | 67 | Mile | 12 | Feet | $16,000,000 | USD | Contractor | 6 | 6 | 0 | Square Yards | unknown | Todd Shields | tshields@indot.in.gov | 317-515-1227 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
29 | 10/7/2021 10:28:06 | Cold-In-Place Recycling | Indiana | 2021 | 100 | Mile | 12 | Feet | $38,000,000 | USD | Contractor | 10 | 10 | 0 | Square Yards | Unknown | Todd Shields | tshields@indot.in.gov | 317-515-1227 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
30 | 10/7/2021 10:37:01 | Crack Sealing | Indiana | 2021 | 3308 | Mile | 12 | Feet | $4,200,000 | USD | Agency | 3 | 3 | 0 | Square Yards | Hot pour sealant | Todd Shields | tshields@indot.in.gov | 317-515-1227 | N/A | N/A | $0.00 | $0.00 | |||||
31 | 10/7/2021 10:40:31 | Fog Seal | Indiana | 2021 | 1,100 | Mile | 12 | Feet | $2,000,000 | USD | Agency | 2 | 2 | 0 | Square Yards | Diluted SS-1h | Fog seal always done in conjunction with chip seal | Todd Shields | tshields@indot.in.gov | 317-515-1227 | $0.00 | $0.00 | $0.00 | $0.00 | ||||
32 | 10/7/2021 10:41:53 | Chip Seal (Single) | Indiana | 2021 | 1,100 | Mile | 12 | Feet | $10,000,000 | USD | Agency | 6 | 6 | 0 | Square Yards | CRS-2P or AE 90 S | Todd Shields | tshields@indot.in.gov | 317-515-1227 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
33 | 10/7/2021 10:43:18 | Scrub Seal | Indiana | 2021 | 42 | Mile | 12 | Feet | $350,000 | USD | Agency | 4 | 4 | 0 | Square Yards | CRS 2P or AE 90S | Todd Shields | tshields@indot.in.gov | 317-515-1227 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
34 | 10/7/2021 16:59:02 | Crack Sealing | Iowa | 2020 | 579.9 | Mile | 12 | Feet | 2225800 | USD | Contractor | 3 - 6 years | 3 years | 593650 | Pounds | Crack Sealing Material | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | N/A | N/A | $1,023.71 | $795.10 | |||||
35 | 10/7/2021 17:06:46 | Joint Resealing - Concrete | Iowa | 2020 | 49.6 | Mile | 12 | Feet | 527100 | USD | Contractor | 4 - 8 years | 3 years | 80380 | Pounds | PCC Joint Sealing Material | Francis Todey | Francis.Todey@iowadot.us | 515-238-1398 | N/A | N/A | $1,620.56 | $1,257.51 | |||||
36 | 10/7/2021 17:14:27 | Crack Filling | Iowa | 2020 | 881.2 | Mile | 12 | Feet | 4643900 | USD | Contractor | 3 - 5 years | 2 years | 174450 | Gallons | Emulsion for Crack Filling | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | N/A | N/A | $849.29 | $659.63 | |||||
37 | 10/7/2021 17:24:16 | Micro-surfacing (Two Lift) | Iowa | 2020 | 65.4 | Mile | 12 | Feet | 3580300 | USD | Contractor | 4 - 6 years | 4 years | 7030 | Tons | Aggregate for Micro-surfacing | 193490 | Gallons | Emulsion for Micro-surfacing | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $1.88 | $2.81 | $13,209.79 | $10,255.46 | ||
38 | 10/7/2021 17:32:49 | Micro-surfacing (Single Lift) | Iowa | 2020 | 57 | Mile | 12 | Feet | 856300 | USD | Contractor | 3 - 5 years | 4 years | 3485 | Tons | Aggregate for Micro-surfacing | 115860 | Gallons | Emulsion for Micro-surfacing | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $1.31 | $1.96 | $9,220.41 | $7,156.36 | ||
39 | 10/7/2021 17:40:37 | Diamond Grinding | Iowa | 2020 | 56.1 | Mile | 12 | Feet | 2978000 | USD | Contractor | 6 - 8 years | 411100 | Square Yards | Pavement Grinding - Limestone | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $2.91 | $4.36 | $20,518.36 | $15,934.11 | ||||||
40 | 10/7/2021 17:54:02 | Thin HMA Overlay (US) | Iowa | 2020 | 65.4 | Mile | 12 | Feet | 6973000 | USD | Contractor | 40350 | Tons | HMA Thin Lift Surface (3/8") | 3228.1 | Tons | Binder - PG 64-34E+, 90% Elastic Recovery | This material has not been used long enough to determine an anticipated treatment life. | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $7.58 | $11.33 | $53,369.11 | $41,433.29 | |||
41 | 10/8/2021 16:21:43 | Cold-In-Place Recycling | Iowa | 2020 | 144.1 | Mile | 12 | Feet | 35068000 | USD | Contractor | 1136800 | Square Yards | Cold-in-Place Recycling of Asphalt Pavement | 4119 | Tons | Asphalt Stabilizing Agent | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $3.95 | $5.91 | $27,839.46 | $21,614.58 | ||||
42 | 10/20/2021 16:12:44 | Chip Seal (Single) | North Dakota | 2020 | 2177 | Mile | 24 | Feet | 36,500/Mile | USD | Both | 7-10 years | 4354 | Lane Miles | Single Chip Seal | Stephanie Weigel | sjweigel@nd.gov | 701-328-2528 | $2.59 | $3.88 | $36,500.00 | $28,349.59 | ||||||
43 | 10/20/2021 16:15:05 | Crack Sealing | North Dakota | 2020 | 1737 | Mile | 24 | Feet | N/A | USD | Agency | 2 years | 3474 | Lane Miles | Crack Sealing | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | N/A | N/A | $0.00 | $0.00 | ||||||
44 | 10/20/2021 16:18:10 | Diamond Grinding | North Dakota | 2020 | 35 | Mile | 24 | Feet | N/A | USD | Contractor | 10-15 years | 70 | Lane Miles | Concrete Grinding | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | $0.00 | $0.00 | $0.00 | $0.00 | ||||||
45 | 10/20/2021 16:19:48 | Dowel Bar Retrofit | North Dakota | 2020 | 6 | Mile | 24 | Feet | N/A | USD | Contractor | 10-15 years | 12 | Lane Miles | Dowel Bar Retrofit | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | N/A | N/A | $0.00 | $0.00 | ||||||
46 | 10/20/2021 16:27:23 | Micro Milling | North Dakota | 2020 | 58 | Mile | 24 | Feet | N/A | USD | Contractor | 816640 | Square Yards | MicroMill | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | $0.87 | $1.30 | $12,249.60 | $9,508.52 | |||||||
47 | 10/20/2021 16:29:22 | Micro-surfacing (Single Lift) | North Dakota | 2020 | 405 | Mile | 24 | Feet | 60,000/mile | USD | Both | 8-12 years | 810 | Lane Miles | Single Microsurface | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | $4.26 | $6.37 | $60,000.00 | $46,601.72 | ||||||
48 | 10/20/2021 16:31:16 | Slurry Seal | North Dakota | 2020 | 63 | Mile | 24 | Feet | 46,000/mile | USD | Contractor | 7-10 years | 126 | Lane Miles | Slurry Seal | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | $3.27 | $4.88 | $46,000.00 | $35,724.85 | ||||||
49 | 10/20/2021 16:35:35 | Concrete Pvmt Restoration | North Dakota | 2020 | 35 | Mile | 24 | Feet | 90,000/mile | USD | Contractor | 10-15 years | 70 | Lane Miles | Concrete Pavement Repair | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | $6.32 | $9.45 | $89,000.00 | $69,038.12 | ||||||
50 | 10/20/2021 16:37:36 | Thin HMA Overlay (US) | North Dakota | 2020 | 309 | Mile | 24 | Feet | 170,000/mile | USD | Contractor | 8-12 years | 618 | Lane Miles | Thin Lift Overlay | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | $12.07 | $18.05 | $170,000.00 | $132,038.01 | ||||||
51 | 10/20/2021 17:43:55 | Chip Seal (Single) | North Dakota | 2019 | 1971 | Mile | 24 | Feet | 35,000/mile | USD | Both | 7-10 years | 3942 | Lane Miles | Single Chip Seal | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | $2.49 | $3.72 | $35,000.00 | $27,184.28 | ||||||
52 | 10/20/2021 17:45:23 | Concrete Pvmt Restoration | North Dakota | 2019 | 19 | Mile | 24 | Feet | 90,000/mile | USD | Contractor | 10-15 years | 38 | Lane Miles | Concrete Pavement Repair | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | $6.39 | $9.56 | $90,000.00 | $69,852.94 | ||||||
53 | 10/20/2021 17:46:44 | Crack Sealing | North Dakota | 2019 | 1669 | Mile | 24 | Feet | N/A | USD | Agency | 2 years | 3338 | Lane Miles | Crack Sealing | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | N/A | N/A | $0.00 | $0.00 | ||||||
54 | 10/20/2021 17:48:19 | Diamond Grinding | North Dakota | 2019 | 19 | Mile | 24 | Feet | 60,000/mile | USD | Contractor | 10-15 years | 11147 | Square Yards | Concrete Grinding | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | $0.24 | $0.36 | $3,385.17 | $2,627.38 | ||||||
55 | 10/20/2021 17:50:01 | Micro Milling | North Dakota | 2019 | 39 | Mile | 24 | Feet | N/A | USD | Contractor | 22880 | Square Yards | MicroMill | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | $0.03 | $0.05 | $451.73 | $350.67 | |||||||
56 | 10/20/2021 17:51:48 | Micro-surfacing (Single Lift) | North Dakota | 2019 | 601 | Mile | 24 | Feet | 67,000/mile | USD | Both | 8-12 years | 1202 | Lane Miles | Single MicroSurface | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | $4.76 | $7.11 | $67,000.00 | $52,035.30 | ||||||
57 | 10/20/2021 17:53:18 | Slurry Seal | North Dakota | 2019 | 83 | Mile | 24 | Feet | 47,000/mile | USD | Contractor | 7-10 years | 166 | Lane Miles | Slurry Seal | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | $3.34 | $4.99 | $47,000.00 | $36,498.88 | ||||||
58 | 10/20/2021 17:54:52 | Thin HMA Overlay (US) | North Dakota | 2019 | 306 | Mile | 24 | Feet | 170,000/mile | USD | Contractor | 8-12 years | 612 | Lane Miles | Thin Lift Overlay | Stephanie Weigel | sjweigel@nd.gov | 7013282528 | $12.07 | $18.05 | $170,000.00 | $132,030.46 | ||||||
59 | 11/12/2021 9:59:20 | Diamond Grinding | South Dakota | 2019 | 85 | Mile | 14 | Feet | 3,500,000 | USD | Contractor | 797200 | Square Yards | Diamond Grinding | Shea Lemmel | Shea.Lemmel@state.sd.us | 605-773-2730 | $5.01 | $7.49 | $41,173.04 | $31,978.33 | |||||||
60 | 11/12/2021 10:08:52 | Micro-surfacing (Two Lift) | South Dakota | 2019 | 95 | Mile | 12 | Feet | 1,906,300 | USD | Contractor | 347705 | Gallons | Asphalt Emulsion | 10708 | Tons | Mineral Aggregate | Shea Lemmel | Shea.Lemmel@state.sd.us | 605-773-2730 | $2.85 | $4.26 | $20,066.33 | $15,584.55 | ||||
61 | 11/12/2021 10:39:57 | Crack Sealing | South Dakota | 2019 | 880 | Mile | 14 | Feet | 1,086,134 | USD | Contractor | 643050 | Pounds | Asphalt Concrete Crack Sealing | Shea Lemmel | Shea.Lemmel@state.sd.us | 605-773-2730 | N/A | N/A | $1,234.95 | $959.15 | |||||||
62 | 11/12/2021 10:41:06 | Crack Sealing | South Dakota | 2020 | 850 | Mile | 14 | Feet | 1,035,934 | USD | Contractor | 639140 | Pounds | Asphalt Concrete Crack Sealing | Shea Lemmel | Shea.Lemmel@state.sd.us | 605-773-2730 | N/A | N/A | $1,218.13 | $946.10 | |||||||
63 | 11/15/2021 11:45:40 | Thin HMA Overlay (Metric) | Saskatchewan | 2019 | 51.13 | Kilometer | 3.7 | Meter | 1497979.15 | CAD | Agency | 10 years | 0 | Square Feet | N/A | Taylor Fiesel | Taylor.fiesel@gov.sk.ca | (306) 527-3023 | $0.00 | $0.00 | $0.00 | $0.00 | ||||||
64 | 11/18/2021 11:17:42 | Scrub Seal | Saskatchewan | 2019 | 30.05 | Kilometer | 3.7 | Meter | 486895.73 | CAD | Agency | 0 | Lane Kilometers | N/A | Taylor James Fiesel | Taylor.fiesel@gov.sk.ca | 3065273023 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||
65 | 11/18/2021 11:47:52 | Chip Seal (Single) | Saskatchewan | 2019 | 316.69 | Kilometer | 4.44 | Meter | 5320093.24 | CAD | Both | 10 years | 8-12 years | 000 | Lane Kilometers | N/A | Taylor James Fiesel | Taylor.fiesel@gov.sk.ca | 3065273023 | $0.00 | $0.00 | $0.00 | $0.00 | |||||
66 | 11/25/2021 9:25:38 | Rejuvenator Fog Seal | Saskatchewan | 2019 | 37.37 | Kilometer | 3.7 | Meter | 309460.96 | CAD | Agency | 000 | Kilograms | N/a | Taylor Fiesel | Taylor.fiesel@gov.sk.ca | 3065273023 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||
67 | 11/25/2021 10:50:56 | Micro-surfacing (Single Lift) | Saskatchewan | 2019 | 372.45 | Kilometer | 3.95 | Meter | 9127069.54 | CAD | Agency | 0 | Kilograms | N/A | Taylor Fiesel | Taylor.fiesel@gov.sk.ca | 3065273023 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||
68 | 12/1/2021 15:47:27 | Micro-surfacing (Two Lift) | Iowa | 2021 | 121 | Mile | 12 | Feet | 3,092,000 | USD | Contractor | 4 - 6 years | 4 years | 14350 | Tons | Aggregate | 451,300 | Gallons | Asphalt Emulsion | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $2.17 | $3.24 | $15,261.86 | $11,849.88 | ||
69 | 12/1/2021 15:56:27 | Chip Seal (Single) | Iowa | 2021 | 39 | Mile | 12 | Feet | 1082000 | USD | Contractor | 3 - 5 years | 3 years | 4100 | Tons | 3/8" Cover Aggregate | 101500 | Gallons | CRS-2P Asphalt Emulsion | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $1.38 | $2.07 | $9,741.67 | $7,562.20 | ||
70 | 12/1/2021 16:04:42 | Crack Sealing | Iowa | 2021 | 386 | Mile | 12 | Feet | 1852000 | USD | Contractor | 3 - 6 years | 3 years | 470700 | Pounds | Crack sealing material | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | N/A | N/A | $1,219.43 | $947.01 | |||||
71 | 12/1/2021 16:33:31 | Crack Filling | Iowa | 2021 | 957 | Mile | 12 | Feet | 4636000 | USD | Contractor | 3 - 5 years | 2 years | 197000 | Gallons | Asphalt Emulsion | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | N/A | N/A | $946.92 | $735.46 | |||||
72 | 12/1/2021 17:46:57 | Cold-In-Place Recycling | Iowa | 2021 | 115 | Mile | 12 | Feet | 26924000 | USD | Contractor | Not known, CIP is resurfaced with HMA | 858100 | Square Yards | Cold-in-Place Recycled Pavement | 3644 | Tons | Asphalt Stabilizing Agent | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $3.87 | $5.78 | $27,227.23 | $21,144.86 | |||
73 | 12/1/2021 17:54:35 | Hot-In-Place Recycling | Iowa | 2021 | 36 | Mile | 12 | Feet | 7886000 | USD | Contractor | Unknown, treatment has been used only 3 years | 284000 | Square Yards | Hot-in-place recycled pavement | 415 | Tons | Rejuvenating Agent | Francis Todey | Francis.Todey@iowadot.us | 515-239-1398 | $5.71 | $8.54 | $40,217.92 | $31,203.56 | |||
74 | 12/13/2021 15:23:22 | Chip Seal (Single) | Michigan | 2020 | 394.95 | Mile | 12 | Feet | 19229088 | USD | Contractor | 6 | 850000 | Square Yards | Chip Seal | Tyler Hunt | huntt2@michigan.gov | 5172569592 | $0.61 | $0.91 | $4,303.80 | $3,342.77 | ||||||
75 | 12/16/2021 16:55:09 | Bonded Wearing Course | Michigan | 2020 | 500.1 | Mile | 12 | Feet | $55,595,933 | USD | Contractor | 5.5 | 7 | 1173587 | Square Yards | HMA | Tyler Hunt | huntt2@michigan.gov | 517-256-9592 | $15.79 | $23.61 | $111,163.40 | $86,334.97 | |||||
76 | 12/16/2021 22:12:37 | Scrub Seal | Michigan | 2021 | 35.5 | Mile | 12 | Feet | 1321974 | USD | Contractor | 6 | 6 | 290114 | Square Yards | Scrub Seal Mix | Tyler HUnt | huntt2@michigan.gov | 517-256-9592 | $5.28 | $7.90 | $37,183.63 | $28,846.56 | |||||
77 | 2/17/2022 16:29:58 | Chip Seal (Single) | Ohio | 2017 | 608.99 | Mile | 10 | Feet | 7788181 | USD | Contractor | 8 years | 4583489 | Square Yards | Chip Seal | Patrick Bierl | patrick.bierl@dot.ohio.gov | $2.33 | $3.49 | $13,697.78 | $10,639.16 | |||||||
78 | 2/17/2022 16:33:10 | Chip Seal (Double) | Ohio | 2017 | 111.08 | Mile | 10 | Feet | 523868 | USD | Contractor | 135521 | Square Yards | Double Chip Seal | Patrick Bierl | patrick.bierl@dot.ohio.gov | $0.80 | $1.20 | $4,696.27 | $3,647.62 | ||||||||
79 | 2/17/2022 16:37:59 | Crack Filling | Ohio | 2017 | 1047.83 | Mile | 12 | Feet | 108469.2 | USD | Contractor | 35568 | Pounds | Crack Fill Material | Patrick Bierl | patrick.bierl@dot.ohio.gov | N/A | N/A | $128.98 | $100.18 | ||||||||
80 | 2/17/2022 16:40:51 | Micro-surfacing (Single Lift) | Ohio | 2017 | 574.3 | Mile | 11.5 | Feet | 18251828 | USD | Contractor | 11-15 years | 5173361 | Square Yards | Micro Surfacing | Patrick Bierl | patrick.bierl@dot.ohio.gov | $3.40 | $5.09 | $22,970.70 | $17,840.62 | |||||||
81 | 2/17/2022 16:42:59 | Micro-surfacing (Two Lift) | Ohio | 2017 | 346.73 | Mile | 12 | Feet | 16239446 | USD | Contractor | 3060269 | Square Yards | Two-Lift Micro Surfacing | Patrick Bierl | patrick.bierl@dot.ohio.gov | $2.26 | $3.37 | $15,883.75 | $12,337.58 | ||||||||
82 | 2/17/2022 17:05:34 | Chip Seal (Single) | Iowa | 2017 | 25 | Mile | 12 | Feet | 600000 | USD | Contractor | 5 years | 3 years | 3530 | Tons | 3/8" limestone aggregate | 84760 | Gallons | CRS-2P emulsion | $1.68 | $2.51 | $11,817.34 | $9,163.57 | |||||
83 | 2/17/2022 17:08:59 | Chip Seal (Single) | Iowa | 2016 | 35 | Mile | 12 | Feet | 493500 | USD | Both | 5 years | 3 years | 35 | Lane Miles | Chip Seal (CRS-2P emulsion, 3/8" limestone aggregate) | $1.04 | $1.55 | $7,300.00 | $5,662.68 | ||||||||
84 | 2/17/2022 17:12:56 | Chip Seal (Single) | Iowa | 2018 | 37 | Mile | 12 | Feet | 555000 | USD | Contractor | 3-5 years | 3 years | 37 | Lane Miles | Chip Seal | $1.52 | $2.27 | $10,700.00 | $8,303.27 | ||||||||
85 | 2/17/2022 17:14:39 | Chip Seal (Double) | Iowa | 2018 | 30 | Mile | 12 | Feet | 780000 | USD | Contractor | 3-5 years | 3 years | 30 | Lane Miles | Double Chip Seal | $2.27 | $3.40 | $16,000.00 | $12,422.36 | ||||||||
86 | 2/17/2022 17:17:34 | Cold-In-Place Recycling | Iowa | 2017 | 199 | Mile | 12 | Feet | 48954000 | USD | Contractor | 1400000 | Square Yards | CIR, 3-4" recycling depth, foamed asphalt stabilizing agent | $3.06 | $4.57 | $21,527.64 | $16,718.70 | ||||||||||
87 | 2/17/2022 17:19:48 | Cold-In-Place Recycling | Iowa | 2016 | 155 | Mile | 12 | Feet | 33015000 | USD | Contractor | 1090000 | Square Yards | CIR, 3-4" recycling depth, foamed asphalt stabilizing agent | $3.20 | $4.78 | $22,503.23 | $17,474.95 | ||||||||||
88 | 2/17/2022 17:23:49 | Cold-In-Place Recycling | Iowa | 2018 | 238 | Mile | 12 | Feet | 53074000 | USD | Contractor | 1734000 | Square Yards | CIR, 3-4" recycling depth, foamed asphalt stabilizing agent-surfaced with HMA overlay | $3.62 | $5.42 | $25,500.00 | $19,802.27 | ||||||||||
89 | 2/17/2022 17:25:50 | Joint Resealing - Concrete | Iowa | 2017 | 25 | Mile | 12 | Feet | 230000 | USD | Contractor | 7 years | 3 years | 25 | Lane Miles | Joint Sealant | N/A | N/A | $7,300.00 | $5,660.67 | ||||||||
90 | 2/17/2022 17:27:54 | Joint Resealing - Concrete | Iowa | 2016 | 76 | Mile | 12 | Feet | 661200 | USD | Contractor | 7 years | 3 years | 76 | Lane Miles | Joint Sealant | N/A | N/A | $7,900.00 | $6,131.54 | ||||||||
91 | 2/17/2022 17:30:18 | Joint Resealing - Concrete | Iowa | 2018 | 112 | Mile | 12 | Feet | 795200 | USD | Contractor | 4-8 years | 3 years | 112 | Lane Miles | Joint Sealant | N/A | N/A | $6,200.00 | $4,814.20 | ||||||||
92 | 2/17/2022 17:45:20 | Concrete Pvmt Restoration | Iowa | 2018 | 4 | Mile | 12 | Feet | 416000 | USD | Contractor | 4 | Lane Miles | Concrete Pavement Restoration | $11.51 | $17.20 | $81,000.00 | $62,307.69 | ||||||||||
93 | 2/17/2022 17:47:56 | Crack Filling | Iowa | 2017 | 720 | Mile | 12 | Feet | 2592000 | USD | Contractor | 5 years | 2 years | 720 | Lane Miles | Crack Fill Material | N/A | N/A | $1,700.00 | $1,320.33 | ||||||||
94 | 2/17/2022 17:49:58 | Crack Filling | Iowa | 2016 | 436 | Mile | 12 | Feet | 1656800 | USD | Contractor | 5 years | 2 years | 436 | Lane Miles | Crack Fill Material | N/A | N/A | $2,000.00 | $1,553.37 | ||||||||
95 | 2/17/2022 17:51:58 | Crack Filling | Iowa | 2018 | 706 | Mile | 12 | Feet | 2894600 | USD | Contractor | 3-5 years | 2 years | 706 | Lane Miles | Crack Fill Material | N/A | N/A | $2,000.00 | $1,553.42 | ||||||||
96 | 2/17/2022 17:55:16 | Crack Sealing | Iowa | 2017 | 305 | Mile | 12 | Feet | 1159000 | USD | Contractor | 5 years | 3 years | 305 | Lane Miles | Crack Sealant | N/A | N/A | $2,000.00 | $1,553.27 | ||||||||
97 | 2/17/2022 17:57:17 | Crack Sealing | Iowa | 2016 | 789 | Mile | 12 | Feet | 2998200 | USD | Contractor | 5 years | 3 years | 789 | Lane Miles | Crack Sealant | N/A | N/A | $2,000.00 | $1,553.39 | ||||||||
98 | 2/17/2022 17:59:11 | Crack Sealing | Iowa | 2018 | 322 | Mile | 12 | Feet | 1191400 | USD | Contractor | 3-6 years | 3 years | 322 | Lane Miles | Crack Sealant | N/A | N/A | $1,800.00 | $1,397.84 | ||||||||
99 | 2/17/2022 18:00:46 | Diamond Grinding | Iowa | 2017 | 8 | Mile | 12 | Feet | 464000 | USD | Contractor | 8 years | 57300 | Square Yards | Diamond Grinding | $3.05 | $4.56 | $21,487.50 | $16,656.98 | |||||||||
100 | 2/17/2022 18:02:33 | Diamond Grinding | Iowa | 2018 | 22 | Mile | 12 | Feet | 2068000 | USD | Contractor | 6-8 years | 160000 | Square Yards | Diamond Grinding | $3.20 | $4.79 | $22,545.45 | $17,464.79 |