School / PM / ArchitectStep of Repair ProcessJANFEBMARAPRMAYJUNJULAUGSEPOCTNOVDECJANFEBMARAPRMAYJUNJULAUGSEPOCTNOVDECJANFEBMARAPRMAYJUNJULAUGSEPOCTNOVDECJANFEBMARAPRMAYJUNJULAUGSEPOCTNOVQ4
4
Acadian Elementary Volkert ArchestrateDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
5
Roof RepairsDesign PhaseBid Phase Advertise: 10/10 Award: 11/15Construction Phase Complete
6
Demolition of Modular BuildingDesign PhaseQuotes ReceivedConstruction PhaseComplete
7
Asbestos Abatement (Ritter Consulting Engineers)Design PhaseBid Phase Advertise: 2/8 Award: 4/4Construction PhaseComplete
8
Building RepairsDesign PhaseBid Phase Advertise: 2/14 Award: 4/4Construction PhaseComplete
9
Site Prep for New Modular Building (Cheramie + Bruce)Design PhaseBid Phase Advertise: 10/10 Award: 12/5Construction Phase
10
Purchase of New Modular Building (Cheramie + Bruce)Design PhasePurchase Order IssuedConstruction Phase (Production, Delivery, Installation)Complete
11
Security Fencing (Cheramie + Bruce) Building FundsDesign PhaseBid Phase Advertise: 1/20 Award: 3/14Construction PhaseComplete
12
Andrew Price Volkert VergesRomeDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
13
Building RepairsDesign PhaseBid Phase Advertise: 7/25 Award: 9/5Construction PhaseComplete
14
Bayou Black Elementary HGI GFP ArchitectureDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
15
Building RepairsDesign PhaseBid Phase Advertise: 12/22 Award: 2/7Construction Phase Complete
16
Bayou Cane Volkert Craig HebertDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
17
Building RepairsRepair Work (TPSD Personnel)Complete
18
Bourg Elementary Volkert GFP ArchitectureDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
19
Purchase of New Modular Building (Cheramie + Bruce)Purchase Order IssuedConstruction Phase (Production, Delivery, and Installation of Modular Building)Complete
20
Demolition of Modular Building (Cheramie + Bruce)Construction Phase Complete
21
Site Prep for New Modular Building (Cheramie + Bruce)Design PhaseBid Phase Advertise: 5/13 Award: 6/7Construction Phase Complete
22
Building RepairsDesign PhaseBid Phase Advertise: 6/9 Award: 8/1Construction PhaseComplete
23
HL Bourgeois High HGI Gros / Flores / PositerryDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
24
Asbestos Abatement (Ritter Consulting Engineers)Design PhaseBid Phase Advertise: 3/31 Award: 5/3Constr. PhaseComplete
25
Building RepairsDesign PhaseBid Phase Advertise: 3/23 Award: 6/6Construction PhaseComplete
26
HVAC Replacement/ Upgrade (Thompson Luke & Associates) ESSER FundsDesign PhaseBid Phase Advertise: 10/17 Award: 12/20Construction Phase
27
Broadmoor Elementary HGI GFP ArchitectureDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
28
Purchase of New Modular Building (Cheramie + Bruce)Purchase Order IssuedConstruction Phase (Production, Delivery, and Installation of Modular Building)Complete
29
Demolition of Modular Building (Cheramie + Bruce)Construction Phase Complete
30
Site Prep for New Modular Building (Cheramie + Bruce)Design PhaseBid Phase Advertise: 5/13 Award: 6/7Construction Phase Complete
31
Building RepairsDesign PhaseBid Phase Advertise: 1/18 Award: 3/14Construction Phase Complete
32
Security Fencing (Cheramie + Bruce) Building FundsDesign PhaseBid Phase Advertise: 1/20 Award: 3/14Construction PhaseComplete
33
HVAC Replacement/ Upgrade (Thompson Luke & Associates ) ESSER FundsDesign PhaseBid Phase Advertise: 3/9 Award: 5/2Construction PhaseComplete
34
Caldwell Middle Volkert Duplantis Design GroupDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
35
Building RepairsDesign PhaseBid Phase Advertise: 5/17 Award: 7/5Construction PhaseComplete
36
Coteau-Bayou Blue Elementary Volkert ArchestrateDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
37
Asbestos AbatementDesign PhaseBid Phase Advertise: 2/8 Award: 4/4Construct PhaseComplete
38
Building RepairsDesign PhaseBid Phase Advertise: 2/14 Award: 5/2Construction PhaseComplete
39
Demolition of Portable BuildingsDesign PhaseQuotes ReceivedConstruction PhaseComplete
40
Dularge Elementary HGI ArchestrateDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
41
Asbestos Abatement (Ritter Consulting Engineers)Design PhaseBid Phase Advertise: 3/31 Award: 5/3Constr. PhaseComplete
42
Building RepairsDesign PhaseBid Phase Advertise: 2/14 Award: 5/2Construction PhaseComplete
43
HVAC Replacement/ Upgrade (Thompson Luke & Associates ) ESSER FundsDesign PhaseBid Phase Advertise: 3/9 Award: 5/2Construction PhaseComplete
44
East Houma Volkert ArchestrateDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
45
Preliminary Asbestos Abatement (Ritter Consulting Engineers)Const. PhaseComplete
46
Additional Asbestos Abatement (Ritter Consulting Engineers)Design PhaseBid Phase Advertise: 2/8 Award: 4/4Construct PhaseComplete
47
Demolition of Portable BuildingsDesign PhaseQuotes ReceivedConstruction PhaseComplete
48
Building RepairsDesign PhaseBid Phase Advertise: 2/14 Award: 5/2Construction PhaseComplete
49
East Street Volkert ArchestrateDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
50
Asbestos Abatement (Ritter Consulting Engineers)Design PhaseBid Phase Ad.: 5/4 Awd: 6/7Construction PhaseComplete
51
Improved Project
52
Ellender Memorial High Volkert Craig HebertDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMAWaiting on FEMA ReviewFEMA Approval
53
Lease of Modular Buildings (Cheramie + Bruce)Bid Phase Ad.: 12/3 Aw: 1/18Construction Phase (Production, Delivery, and Installation of Modular Buildings)Complete
54
Site Prep for New Modular Buildings (Cheramie + Bruce)Bid Phase Advertise: 12/20 Award: 2/1Construction Phase Complete
55
Asbestos Abatement (Ritter Consulting Engineers)Design PhaseBid Phase Advertise: 3/29 Award: 6/7Construction Phase Complete
56
Baseball Field RepairsDesign PhaseBid Phase Advertise: 11/23 Award: 12/20Construction Phase Complete
57
Demolition of BuildingDesign Phase
58
New ConstructionDesign Phase (Projected)
59
Softball Field (Gros Flores Positerry)Design PhaseBid Phase Advertise: 6/14 Award: 8/6
60
Elysian Fields Volkert Craig HebertDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
61
Building RepairsDesign PhaseBid Phase Advertise: 10/20 Award: 12/5Construction PhaseComplete
62
Security Fencing (Cheramie + Bruce) Building FundsDesign PhaseBid Phase Advertise: 1/20 Award: 3/14Construction PhaseComplete
63
HVAC Replacement/ Upgrade (Castagnos Goodwin Utley) ESSER FundsDesign PhaseBid Phase Advertise: 3/31 Award: 6/6Construction PhaseComplete
64
Evergreen Jr. High Volkert Duplantis Design GroupDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
65
Asbestos Abatement (Ritter Consulting Engineers)Design PhaseBid Phase Advertise: 3/31 Award: 5/3Construction PhaseComplete
66
Roof RepairsDesign PhaseBid Phase Advertise: 11/16 Award: 10/3Construction PhaseComplete
67
Building RepairsDesign PhaseBid Phase Advertise: 10/25 Award: 1/9Construction Phase
68
Fletcher HGI VergesRomeDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
69
Building RepairsDesign PhaseBid Phase Advertise: 4/29 Award: 7/2
70
Gibson Elementary Volkert Duplantis Design GroupDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
71
Building RepairsDesign PhaseBid Phase Advertise: 5/17 Award: 7/5Construction PhaseComplete
72
Grand Caillou Elementary HGI The Merlin GroupDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMAWaiting on FEMA ReviewFEMA Approval
73
Demotition of Building Design PhaseBid Phase Advertise: 10/18 Award: 12/5Construction PhaseComplete
74
New ConstructionDesign Phase
75
Grand Caillou Middle HGI The Merlin GroupDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
76
Building RepairsDesign PhaseBid Phase Advertise: 9/21 Award: 11/1Construction Phase Complete
77
Honduras Elementary Volkert Cheramie + BruceDamage AssessmentsDevelop Initial Damage Assessments
78
Building RepairsDesign PhaseBid Phase Advertise: 9/15 Award: 11/7Construction Phase
79
Security Fencing (Cheramie + Bruce) Building FundsDesign PhaseBid Phase Advertise: 1/20 Award: 3/14Construction PhaseComplete
80
Houma Jr. High Volkert VergesRomeDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
81
Asbestos Abatement (Ritter Consulting Engineers)Design PhaseBid Phase Advertise: 3/31 Award: 5/3Constr. PhaseComplete
82
Roof RepairsDesign PhaseBid Phase Advertise: 9/21 Award: 11/1Construction Phase Complete
83
Building RepairsDesign PhaseBid Phase Advertise: 7/25 Award: 9/5Construction Phase
84
Lacache Middle Volkert ArchestrateDamage AssessmentsDevelop Initial Damage AssessmentsWaiting on FEMA Review
85
Asbestos Abatement (Ritter Consulting Engineers)Const. PhaseComplete
86
Lease of Modular Buildings (Cheramie + Bruce)Design PhaseConstruction Phase (Production, Delivery, and Installation)Complete
87
Site Prep for New Modular Buildings (Cheramie + Bruce)Design PhaseBid Phase Advertise: 3/17 Award: 5/2Construction PhaseComplete
88
Demolition of Portable BuildingsDesign PhaseQuotes ReceivedConstruction PhaseComplete
89
New ConstructionDesign Phase
90
Legion Park Elementary Volkert ArchestrateDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
91
Asbestos Abatement (Ritter Consulting Engineers)Design PhaseBid Phase Advertise: 3/31 Award: 5/3Constr. PhaseComplete
92
Roof RepairsDesign PhaseBid Phase Advertise: 9/20 Award: 11/15Construction Phase Complete
93
Building RepairsDesign PhaseBid Phase Advertise: 2/14 Award: 5/2Construction PhaseComplete
94
HVAC/Window Replacement (Archestrate) ESSER FundsDesign PhaseBid Phase Advertise: 3/15 Award: 5/2Construction PhaseComplete
95
Lisa Park Elementary HGI Duplantis Design GroupDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
96
Building RepairsDesign PhaseBid Phase Advertise: 6/23 Award: 9/5Construction PhaseComplete
97
Louis Miller TCT HGI Cheramie + BruceDamage AssessmentsDevelop Initial Damage Assessments DA Subm. to FEMA
98
Building RepairsDesign PhaseBid Phase Advertise: 2/9 Award: 4/8Construction Phase