1 | Status of New MCF projects - 2024-25 | ||||||||||
2 | # | LBName | Project No | ProjectName | Proj. Category | Project cost | New MCF Construction (Yes / No) | Project status | Issues (mention details of issue in Remarks column) | Remarks | |
3 | 1 | Aluva | 141 | Aluva municipality Construction of MCF | New | ₹12,500,000 | Yes | Project to be dropped | Land not available | Updated on 22-11-2024. proposed land proposed is in periyar valley under the authorization of irrigation , updated on 14/2/2025 | |
4 | 2 | Aluva | 175 | CONSTRUCTION OF MCF IN ALUVA MUNICIPAL AREAS | Spillover | ₹1,912,176 | Yes | 12 Work 75% completed | | MCF work ongoing.80% completed.updated on 14/2/2025 | |
5 | 3 | Angamaly | 263 | Construction of MCF in Ayyayipadam Second Phase | New | ₹5,195,258 | Yes | 11 Work 50% completed | | updated on23/01/2025 | |
6 | 4 | Chengannur | 318 | MCF -ADHIKA SOUKARYANGAL ORUKKAL | New | ₹1,000,000 | Yes | | Land not available | updated on 8/11/2024 land issue | |
7 | 5 | Cherthala | 262 | Majour MCF | Spillover | ₹388,477 | Yes | 14 Work Completed in all respect. | | ubdated on 16/12/2024 | |
8 | 6 | Eloor | 208 | MCF Construction near HIL | Spillover | ₹552,173 | Yes | 14 Work Completed in all respect. | | Bill Passed | |
9 | 7 | Eloor | 239 | INFRASTRUCTURE DEVELOPMENT IN MANJUMMEL MCF | Spillover | ₹1,800,000 | Yes | 12 Work 75% completed | | Work on Completion Stage. | |
10 | 8 | Eloor | 405 | MCF Construction near TCC Market | New | ₹500,000 | Yes | 09 Work started | | ||
11 | 9 | Feroke | 354 | MCF CONSTRUCTION | New | ₹5,610,000 | Yes | 07 Agreement Executed | | updated on 18/08/2025 | |
12 | 10 | Irinjalakkuda | 243 | Construction of MCF in Hill plant completion of existing centre windrow compost unit improovement ward -32 | New | ₹2,000,000 | No | Project to be dropped | | vide project no .509/25 , works in progress .Duplication project and dropped in the DPC.The fund allocated was urban agglomeration fund | |
13 | 11 | Irinjalakkuda | 509 | Construction of MCF in Hill Park plant completion of Existing center Windrow compost unit improvement ward-32 | New | ₹8,800,000 | Yes | 12 Work 75% completed | ടി പ്രവൃത്തി പൂർത്തീകരിക്കുന്നതിന് 2024-2025 ൽ 8800000രൂപയും 2025 -2026ൽ1000000 രൂപയും മതിയാകും.മുൻവർഷങ്ങളിലെ fund ആവശ്യമില്ല .നിലവിലുള്ള windrow compost യൂണിറ്റിന്റെ പുനരുദ്ധാരണ പ്രവൃത്തികൾ പൂർത്തീകരിച്ചു, 980000 രൂപയുടെ part bill നൽകിയിട്ടുണ്ട് .പുതിയ MCF നിർമ്മാണം മറ്റൊരു ഭാഗത്തേക്ക് മാറ്റി Roofl level വരെ പൂർത്തീകരിച്ചിട്ടുണ്ട് .Approximate bill amount 50 lakhs after RE Approval . 90% work completed. RE under preparation | ||
14 | 12 | Iritty | 401 | Costruction of MCF at athithattu | New | ₹3,000,000 | Yes | Project need revision | Land not available | At the Proposed site for new MCF, biomining project in progress need to be completed first . Because of that, for the construction of new MCF, either new location need to be identified or it can be proposed after completion of bio mining project . So project needs revision. | |
15 | 13 | Iritty | 404 | Costruction of MCF at muthappankari | New | ₹3,000,000 | Yes | Project to be dropped | | correct project name - Construction of MCF at Chavasseryparamb | |
16 | 14 | Iritty | 405 | Costruction of MCF at muthappankari | New | ₹3,000,000 | Yes | 03 TS obtained | | Tender notice to be published on 16/12/24 | |
17 | 15 | Kalpetta | 376 | VELLARAMKUNNU MCF DEVELOPMENT | Spillover | ₹2,500,000 | Yes | 12 Work 75% completed | | The work is physically completed. Bill under processing | |
18 | 16 | Kanjhangad | 543 | MCF EXTENSION SECOND STAGE | New | ₹4,200,000 | Yes | 01 Preparing Estimate | other issues | Delay in first face | |
19 | 17 | Karunagappally | 413 | CONSTRUCTION OF MCF | New | ₹10,000,000 | Yes | 09 Work started | | ||
20 | 18 | Kasargod | 159 | MCF BUILDING CONSTRUCTION | New | ₹100,000 | Yes | Project to be dropped | Land not available | Project dropped in revision | |
21 | 19 | Kunnamkulam | 213 | Kunnamkulam nagarasabha swatch bharath mission urban 20 MCF Construction completion 23-24 | Spillover | ₹956,000 | No | 04 Tendered | | Part bill given,Final bill under preparaion,Updated on16/12/24 | |
22 | 20 | Kunnamkulam | 332 | MCF in Greenpark | Spillover | ₹2,020,185 | Yes | 14 Work Completed in all respect. | | Bill paid,Updated on 16/12/24 | |
23 | 21 | Mananthavady | 904 | MCF BUILDING CONSTRUCTION | New | ₹4,120,000 | Yes | Project to be dropped | Soil investigation | Land not available. | |
24 | 22 | Manjeri | 1170 | Construction of MCF Building at Vettekode | Spillover | ₹5,100,000 | Yes | 09 Work started | | work in progress , extention work of existing building | |
25 | 23 | Mukkam | 604 | CONSTRUCTION OF MCF | New | ₹466,600 | Yes | | Land not available | Updated on 28/06/2025 | |
26 | 24 | Muvattupuzha | 218 | MCF Installation | Spillover | ₹850,000 | Yes | 08 Site handed over | Land not available | The project is proposed within the Dumpyard Compound of Muvattupuzha Municipality. Land will be available only after the biomining in dumping yard.(updated on 24/01/2025) | |
27 | 25 | Muvattupuzha | 289 | URGENT ELECTRIFICATION MAINTENANCE WORKS IN MCF BUILDING-WARD 25 | New | ₹70,000 | No | 04 Tendered | other issues | PROJECT DROPPED IN REVISION. This project was intended for Urgent Electrification Maintenance Works of existing MCF (using CFC Tied Grant). However, project was dropped in Revision since there was an existing KSWMP project for MCF Renovation including civil and electrical works.(updated on 24/01/2025) | |
28 | 26 | Pala | 430 | Establishment of MCF -RRF in Municipality | New | ₹5,027,500 | Yes | | Land not available | LAND ISSUES. LAND IS NOT FEASIBLE. Updated on 06/02/2025 | |
29 | 27 | Palakkad | 374 | CONSTRUCTION OF METERIAL COLLECTION CENTER MCF | New | ₹3,900,000 | Yes | 04 Tendered | | ||
30 | 28 | Pandalam | 719 | MCF | New | ₹5,000,000 | Yes | 01 Preparing Estimate | location change | 2 nos of cost 4700000, 1estimate under preparation,1 Location change waiting for confirmation | |
31 | 29 | Paravoor | 364 | Construction of MCF in Paravur Municipality | New | ₹3,200,000 | Yes | 04 Tendered | | Updated on 13-01-2025 | |
32 | 30 | Pathanamthitta | 371 | CONSTRUCTION OF CONTAINER MCF | New | ₹1,875,000 | Yes | 01 Preparing Estimate | NOC PWD | NOC from PWD | |
33 | 31 | Perinthalmanna | 401 | CONSTRUCTION OF MCF AT VARIOUS PLACES | Spillover | ₹403,738 | Yes | 12 Work 75% completed | location change | MINI MCF OUT OF 4 ,3 NOS COMPLETED.LAND NOT IDENTIFIED FOR 4TH ONE | |
34 | 32 | Ponnani | 490 | CONSTRUCTION OF MCF CENTER | Spillover | ₹498,000 | No | Project to be dropped | Land not available | updated on15/02/2025 | |
35 | 33 | Quilandy | 163 | Construction of Modern MCF | New | ₹8,500,000 | Yes | 01 Preparing Estimate | NOC PWD | PWD NOC required. Letter submitted for PWD NOC. Updated on 19/06/2025 | |
36 | 34 | Ramanattukara | 333 | MCF | New | ₹4,250,000 | Yes | 01 Preparing Estimate | | Now decided to rennovate the existing building in the Ramanattukara Municipality new building plot updated on 19/08/25 | |
37 | 35 | Sulthan Bathery | 683 | CONSTRUCTION OF MCF IN KARUVALLIKKUNNU | New | ₹3,920,000 | Yes | 07 Agreement Executed | | Work not started. | |
38 | 36 | Thalassery | 562 | NEW MCF CONSTRUCTION AT KANDIKKAL | Spillover | ₹2,180,325 | Yes | 14 Work Completed in all respect. | | civil work completed. electrical work is proposed new sulegha project 2024-25.. | |
39 | 37 | Thirur | 256 | Installing MCF near Vandipetta | Spillover | ₹3,000,000 | Yes | 06 Work awarded | NOC Railway | Railway NOC required,Letter given on 06/04/2024 to Divisional Manager, Work Branch, Palakkad Division | |
40 | 38 | Thiruvalla | 480 | SBM20 - Construction for MCF 1 tone | Spillover | ₹2,000,000 | Yes | Project to be dropped | Land not available | ||
41 | 39 | Tirurangadi | 430 | CONSTRUCTION OF MCF | New | ₹3,000,000 | Yes | Project to be dropped | wet land | Type of land available is wet (Nancha). Dropd in revision as per resolution no.1(2) dated 12.1.2025. | |
42 | 40 | Tripunithura | 491 | INSTALLATION OF MCF | Spillover | ₹8,500,000 | Yes | 06 Work awarded | Public protests | Stay order against construction in the proposed site(Irumbanam smasanam) .Hence not able to start | |
43 | 41 | Vadakara | 309 | Construction of MCF Toilet at Trenching Ground | Spillover | ₹1,219,303 | No | 12 Work 75% completed | Public protests | Dispute with public has solved . work restarted | |
44 | 42 | Vadakara | 478 | VATAKARA MUNICIPALITY 2024-25 CONSTRUCTION OF MCF AT KOTTAPPARAMBU | New | ₹1,000,000 | Yes | 02 Estimate prepared and submitted for TS | Land not available | Project not exists | |
45 | 43 | Vadakara | 537 | MCF Construction Chandhapparambu | New | ₹1,000,000 | Yes | | Land not available | project not exists |