1 | Schedule - List - 2927 W Pikes Peak Ave (exported on Jul 22, 2026) | |||||||||||||||||||||||||
2 | ID # | Title | Complete | Percent Complete | Phase | Duration | Start | End | Assigned To | Accepted | Pending | Declined | Pred 1 Id | Pred 1 Type | Pred 1 Lag | Pred 2 Id | Pred 2 Type | Pred 2 Lag | Pred 3 Id | Pred 3 Type | Pred 3 Lag | Pred 4 Id | Pred 4 Type | Pred 4 Lag | ||
3 | 1 | Schematic Design Phase 1 | TRUE | 100 | 25 | 7/11/2024 | 8/14/2024 | 0 | 0 | 0 | ||||||||||||||||
4 | 2 | Finalize Concept Site Plan | TRUE | 100 | 5 | 9/18/2024 | 9/24/2024 | 0 | 0 | 0 | ||||||||||||||||
5 | 3 | PCSA Payment 2 | TRUE | 100 | 1 | 9/24/2024 | 9/24/2024 | 0 | 0 | 0 | ||||||||||||||||
6 | 4 | Finalize Backgrounds | TRUE | 100 | 15 | 9/25/2024 | 10/15/2024 | 0 | 0 | 0 | 2 | FS | 0 | |||||||||||||
7 | 5 | Construction Documents Development | TRUE | 100 | 23 | 10/16/2024 | 11/15/2024 | 0 | 0 | 0 | 4 | FS | 0 | |||||||||||||
8 | 6 | MEP Engineering | TRUE | 100 | 23 | 10/16/2024 | 11/15/2024 | 0 | 0 | 0 | 4 | FS | 0 | |||||||||||||
9 | 7 | Draft Development Site Plan | TRUE | 100 | 10 | 11/4/2024 | 11/15/2024 | 0 | 0 | 0 | ||||||||||||||||
10 | 8 | Dig open Hole for Soil test | TRUE | 100 | 1 | 11/11/2024 | 11/11/2024 | 0 | 0 | 0 | ||||||||||||||||
11 | 9 | Perform soils testing | TRUE | 100 | 1 | 11/12/2024 | 11/12/2024 | 0 | 0 | 0 | 8 | FS | 0 | |||||||||||||
12 | 10 | Development Plan Review 1 | TRUE | 100 | 17 | 11/15/2024 | 12/11/2024 | 0 | 0 | 0 | 15 | SS | -16 | |||||||||||||
13 | 11 | Civil Engineering | TRUE | 100 | 15 | 11/18/2024 | 12/10/2024 | 0 | 0 | 0 | 7 | FS | 0 | |||||||||||||
14 | 12 | Landscape Design | TRUE | 100 | 8 | 11/18/2024 | 11/27/2024 | 0 | 0 | 0 | 7 | FS | 0 | |||||||||||||
15 | 13 | PPRBD Submittal & Review | TRUE | 100 | 40 | 11/18/2024 | 1/17/2025 | 0 | 0 | 0 | 6 | FS | 0 | 5 | FS | 0 | ||||||||||
16 | 14 | Traffic Impact Study | TRUE | 100 | 23 | 12/10/2024 | 1/14/2025 | 0 | 0 | 0 | ||||||||||||||||
17 | 15 | Submit Development Plan | TRUE | 100 | 1 | 12/11/2024 | 12/11/2024 | 0 | 0 | 0 | 11 | FS | 0 | |||||||||||||
18 | 16 | Revise Development Plan | TRUE | 100 | 10 | 12/12/2024 | 12/27/2024 | 0 | 0 | 0 | 10 | FS | 0 | |||||||||||||
19 | 17 | Resubmit Development Plan | TRUE | 100 | 1 | 1/2/2025 | 1/2/2025 | 0 | 0 | 0 | 16 | FS | 2 | |||||||||||||
20 | 18 | Development Plan Review 2 | TRUE | 100 | 15 | 1/7/2025 | 1/27/2025 | 0 | 0 | 0 | 17 | SS | 3 | |||||||||||||
21 | 19 | Contract Review & Signing | TRUE | 100 | 23 | 3/24/2025 | 4/23/2025 | 0 | 0 | 0 | ||||||||||||||||
22 | 20 | Real Estate Closing | TRUE | 100 | 1 | 6/11/2025 | 6/11/2025 | 0 | 0 | 0 | ||||||||||||||||
23 | 21 | Hazardous Materials Testing and results | TRUE | 100 | 8 | 6/12/2025 | 6/23/2025 | 0 | 0 | 0 | 20 | FS | 0 | |||||||||||||
24 | 22 | Mobilization And Subcontractor Contract Work | TRUE | 100 | 36 | 6/12/2025 | 7/31/2025 | 0 | 0 | 0 | 20 | FS | 0 | |||||||||||||
25 | 23 | Safety Plan Meeting | TRUE | 100 | 1 | 6/12/2025 | 6/12/2025 | Cameron Wolf, Casey Copley, Lee Chapin | 0 | 0 | 0 | 20 | FS | 0 | ||||||||||||
26 | 24 | site walk w/ abatement companies | TRUE | 100 | 4 | 6/25/2025 | 6/30/2025 | 0 | 0 | 0 | ||||||||||||||||
27 | 25 | Deposit City Assurance to DRE and Pull Permit | TRUE | 100 | 2 | 7/8/2025 | 7/9/2025 | Casey Copley | 0 | 0 | 0 | |||||||||||||||
28 | 26 | Issue contract to QECS Abatement sub and schedule | TRUE | 100 | 1 | 7/9/2025 | 7/9/2025 | Casey Copley | 0 | 0 | 0 | |||||||||||||||
29 | 27 | Abatement Permit Waiting Period | TRUE | 100 | 10 | 7/10/2025 | 7/23/2025 | 0 | 0 | 0 | ||||||||||||||||
30 | 28 | SHC Demo Mark-out | TRUE | 100 | 1 | 7/16/2025 | 7/16/2025 | 0 | 0 | 0 | ||||||||||||||||
31 | 29 | Construction Mobilization | TRUE | 100 | 1 | 7/21/2025 | 7/21/2025 | 0 | 0 | 0 | ||||||||||||||||
32 | 30 | Contract electrical & plumbing safe off | TRUE | 100 | 1 | 7/22/2025 | 7/22/2025 | 0 | 0 | 0 | 31 | SS | -1 | |||||||||||||
33 | 31 | Safe Off Electric & Plumbing | TRUE | 100 | 4 | 7/23/2025 | 7/28/2025 | Strive Electric | 0 | 0 | 0 | 33 | SS | -4 | ||||||||||||
34 | 32 | Abatement Mobilization | TRUE | 100 | 3 | 7/24/2025 | 7/28/2025 | 0 | 0 | 0 | ||||||||||||||||
35 | 33 | Hazardous material demo | TRUE | 100 | 43 | 7/29/2025 | 9/26/2025 | Quality Environmental Control Specialists (QECS) | 0 | 0 | 0 | 27 | FS | 3 | ||||||||||||
36 | 34 | Complete Irrigation Plan | TRUE | 100 | 5 | 8/5/2025 | 8/11/2025 | 0 | 0 | 0 | ||||||||||||||||
37 | 35 | Interior Demolition of Non Hazardous Materials | TRUE | 100 | 37 | 8/12/2025 | 10/2/2025 | Quality Environmental Control Specialists (QECS) | 0 | 0 | 0 | 31 | FS | 0 | ||||||||||||
38 | 36 | OC Meeting (PM & Clients) | TRUE | 100 | 1 | 8/13/2025 | 8/13/2025 | 0 | 0 | 0 | ||||||||||||||||
39 | 37 | Get Excavator Under Contract | TRUE | 100 | 1 | 8/26/2025 | 8/26/2025 | 0 | 0 | 0 | ||||||||||||||||
40 | 38 | Call In Locates | TRUE | 100 | 1 | 9/17/2025 | 9/17/2025 | 0 | 0 | 0 | ||||||||||||||||
41 | 39 | Site/Exterior Demolition Phase 1 | TRUE | 100 | 12 | 9/17/2025 | 10/2/2025 | 0 | 0 | 0 | 33 | SS | 14 | 37 | FS | 14 | 34 | FS | 5 | |||||||
42 | 40 | Landscaping Demo | TRUE | 100 | 8 | 9/19/2025 | 9/30/2025 | 0 | 0 | 0 | 35 | FS | -10 | |||||||||||||
43 | 41 | Contract exterior green lit subcontractors | TRUE | 100 | 1 | 9/30/2025 | 9/30/2025 | 0 | 0 | 0 | 57 | SS | -20 | |||||||||||||
44 | 42 | Fence Post Installation (Playground) | TRUE | 100 | 5 | 9/30/2025 | 10/6/2025 | Colorado Springs Fence Co | 0 | 0 | 0 | |||||||||||||||
45 | 43 | Roofing, Gutters & Downspouts | TRUE | 100 | 10 | 9/30/2025 | 10/13/2025 | 0 | 0 | 0 | ||||||||||||||||
46 | 44 | Saw Cut Demo Layout | TRUE | 100 | 1 | 9/30/2025 | 9/30/2025 | Casey Copley, Whitcomb Plumbing | 0 | 0 | 0 | 35 | FS | -3 | ||||||||||||
47 | 45 | Curb, Gutter, Sidewalk, Footings | TRUE | 100 | 30 | 10/1/2025 | 11/11/2025 | 0 | 0 | 0 | ||||||||||||||||
48 | 46 | Fence Post Layout | TRUE | 100 | 1 | 10/1/2025 | 10/1/2025 | Casey Copley | 0 | 0 | 0 | |||||||||||||||
49 | 47 | Sawcutting | TRUE | 100 | 2 | 10/1/2025 | 10/2/2025 | 0 | 0 | 0 | 44 | FS | 0 | |||||||||||||
50 | 48 | Underground Rough Plumbing | TRUE | 100 | 6 | 10/7/2025 | 10/14/2025 | Whitcomb Plumbing | 0 | 0 | 0 | 47 | FS | 2 | 39 | FS | -2 | |||||||||
51 | 49 | Exterior updating Work | TRUE | 100 | 7 | 10/14/2025 | 10/22/2025 | 0 | 0 | 0 | ||||||||||||||||
52 | 50 | Confirm Project Pricing | TRUE | 100 | 53 | 10/15/2025 | 1/2/2026 | 0 | 0 | 0 | 35 | FS | 8 | 33 | FS | 8 | ||||||||||
53 | 51 | Underground plumbing rough inspection | TRUE | 100 | 1 | 10/15/2025 | 10/15/2025 | 0 | 0 | 0 | 48 | FS | 0 | |||||||||||||
54 | 52 | Backfill and Pourback | TRUE | 100 | 3 | 10/16/2025 | 10/20/2025 | 0 | 0 | 0 | 51 | FS | 0 | |||||||||||||
55 | 53 | Framing Materials Delivery | TRUE | 100 | 1 | 10/21/2025 | 10/21/2025 | 0 | 0 | 0 | 52 | FS | 0 | |||||||||||||
56 | 54 | Efflorescence and french drain install | TRUE | 100 | 11 | 10/24/2025 | 11/7/2025 | Colorado Water & Mold Restoration | 0 | 0 | 0 | |||||||||||||||
57 | 55 | Framing Layout | TRUE | 100 | 2 | 10/24/2025 | 10/27/2025 | 0 | 0 | 0 | 52 | FS | 3 | |||||||||||||
58 | 56 | Framing | TRUE | 100 | 56 | 10/28/2025 | 1/20/2026 | Pursuit of Excellence | 0 | 0 | 0 | 55 | FS | 0 | ||||||||||||
59 | 57 | Install Downspout Drainage | TRUE | 100 | 3 | 10/28/2025 | 10/30/2025 | G & K's Landscaping & Construction | 0 | 0 | 0 | |||||||||||||||
60 | 58 | Upper level box walk | TRUE | 100 | 1 | 11/10/2025 | 11/10/2025 | 0 | 0 | 0 | ||||||||||||||||
61 | 59 | Flatwork & Ramp | TRUE | 100 | 26 | 11/12/2025 | 12/19/2025 | 0 | 0 | 0 | 45 | FS | 0 | |||||||||||||
62 | 60 | Order Windows ( 6 week lead time ) | TRUE | 100 | 26 | 12/5/2025 | 1/14/2026 | Davids window service | 0 | 0 | 0 | |||||||||||||||
63 | 61 | Slab Air Flow Testing for Radon | TRUE | 100 | 1 | 12/10/2025 | 12/10/2025 | 0 | 0 | 0 | ||||||||||||||||
64 | 62 | Asphalt repair and patch back | TRUE | 100 | 1 | 12/17/2025 | 12/17/2025 | 0 | 0 | 0 | 45 | FS | 0 | 59 | FS | -3 | ||||||||||
65 | 63 | Electrical box walk with client and electrician | TRUE | 100 | 1 | 12/17/2025 | 12/17/2025 | 0 | 0 | 0 | ||||||||||||||||
66 | 64 | Fencing Phase 1 | TRUE | 100 | 6 | 12/18/2025 | 12/29/2025 | 0 | 0 | 0 | 62 | FS | 0 | |||||||||||||
67 | 65 | Backfill remaining slab in lower level | TRUE | 100 | 1 | 12/26/2025 | 12/26/2025 | 0 | 0 | 0 | ||||||||||||||||
68 | 66 | Framing scope walk with Pino | TRUE | 100 | 1 | 1/5/2026 2:00 PM | 1/5/2026 3:00 PM | Casey Copley, Stephen Michaels | 0 | 0 | 0 | |||||||||||||||
69 | 67 | Rough Electric | FALSE | 75 | 71 | 1/14/2026 | 4/22/2026 | American Electrician, Colorado Water & Mold Restoration | 0 | 0 | 0 | 56 | FS | -5 | ||||||||||||
70 | 68 | Rough Mechanical | FALSE | 75 | 115 | 1/15/2026 | 6/25/2026 | Colorado Water & Mold Restoration | 0 | 0 | 0 | 56 | FS | -4 | 67 | SS | 0 | |||||||||
71 | 69 | Rough Plumbing | FALSE | 99 | 56 | 1/15/2026 | 4/2/2026 | Whitcomb Plumbing | 0 | 0 | 0 | 67 | SS | 1 | ||||||||||||
72 | 70 | Window Demo & Replacement Exterior | FALSE | 98 | 12 | 1/19/2026 | 2/3/2026 | Davids window service | 0 | 0 | 0 | 60 | FS | 2 | ||||||||||||
73 | 71 | Roofing flashing repair | TRUE | 100 | 1 | 1/30/2026 | 1/30/2026 | CS Quality Roofing | 0 | 0 | 0 | |||||||||||||||
74 | 72 | Rough Data & Security | FALSE | 96 | 67 | 2/9/2026 | 5/12/2026 | 0 | 0 | 0 | 67 | SS | 18 | |||||||||||||
75 | 73 | City Tap and asphalt | TRUE | 100 | 59 | 2/25/2026 | 5/18/2026 | Thorp Excavation | 0 | 0 | 0 | |||||||||||||||
76 | 74 | Fire pipe submittal approval | FALSE | 0 | 65 | 3/2/2026 | 6/1/2026 | 0 | 0 | 0 | ||||||||||||||||
77 | 75 | Radon System installation phase 1 | TRUE | 100 | 5 | 3/2/2026 | 3/6/2026 | 0 | 0 | 0 | ||||||||||||||||
78 | 76 | Temporary Structural Framing + finish main framing | TRUE | 100 | 3 | 3/2/2026 | 3/4/2026 | 0 | 0 | 0 | ||||||||||||||||
79 | 77 | Demo foundation walls | TRUE | 100 | 2 | 3/4/2026 | 3/5/2026 | 0 | 0 | 0 | 76 | FS | -1 | |||||||||||||
80 | 78 | Footing 2 saw cut and demo | TRUE | 100 | 1 | 3/6/2026 | 3/6/2026 | Amaya Concrete | 0 | 0 | 0 | 77 | FS | 0 | ||||||||||||
81 | 79 | Open Hole observation Footing 2 | TRUE | 100 | 1 | 3/9/2026 | 3/9/2026 | 0 | 0 | 0 | 78 | FS | 0 | |||||||||||||
82 | 80 | Footing rebar | TRUE | 100 | 1 | 3/10/2026 | 3/10/2026 | 0 | 0 | 0 | 79 | FS | 0 | |||||||||||||
83 | 81 | Footing inspection | TRUE | 100 | 1 | 3/11/2026 | 3/11/2026 | Casey Copley, Stephen Michaels | 0 | 0 | 0 | 80 | FS | 0 | ||||||||||||
84 | 82 | Pour Footing 2 and cure time | TRUE | 100 | 5 | 3/12/2026 | 3/18/2026 | 0 | 0 | 0 | 81 | FS | 0 | |||||||||||||
85 | 83 | Set Steel Posts and Beams & Complete all Framing | TRUE | 100 | 5 | 3/26/2026 | 4/1/2026 | 0 | 0 | 0 | 82 | FS | 5 | |||||||||||||
86 | 84 | Receive new Ducting / Staging | TRUE | 100 | 1 | 3/30/2026 | 3/30/2026 | 0 | 0 | 0 | ||||||||||||||||
87 | 85 | Rough Plumbing Inspection | TRUE | 100 | 1 | 4/3/2026 | 4/3/2026 | 0 | 0 | 0 | 69 | FS | 0 | |||||||||||||
88 | 86 | City tap re start | FALSE | 75 | 45 | 4/23/2026 | 6/25/2026 | Thorp Excavation | 0 | 0 | 0 | |||||||||||||||
89 | 87 | Rough Electrical Inspection walls and floor | TRUE | 100 | 2 | 4/23/2026 | 4/24/2026 | 0 | 0 | 0 | 67 | FS | 0 | |||||||||||||
90 | 88 | Install Playground Footers | TRUE | 100 | 20 | 4/27/2026 | 5/22/2026 | Casey Copley | 0 | 0 | 0 | |||||||||||||||
91 | 89 | Additional Framing (Self Perform ) Chases & Doors | FALSE | 0 | 22 | 4/29/2026 | 5/29/2026 | Casey Copley | 0 | 0 | 0 | |||||||||||||||
92 | 90 | Wall Backing | TRUE | 100 | 13 | 5/20/2026 | 6/8/2026 | 0 | 0 | 0 | 69 | FS | 33 | |||||||||||||
93 | 91 | Mechanical roof boot install WH | TRUE | 100 | 1 | 5/21/2026 | 5/21/2026 | Casey Copley, CS Quality Roofing | 0 | 0 | 0 | |||||||||||||||
94 | 92 | Fire wet system pre walk | TRUE | 100 | 1 | 5/27/2026 | 5/27/2026 | 0 | 0 | 0 | ||||||||||||||||
95 | 93 | Drywall pre walk 2 | TRUE | 100 | 1 | 5/28/2026 | 5/28/2026 | Casey Copley, Drywall Solutions Ltd | 0 | 0 | 0 | |||||||||||||||
96 | 94 | Radon System re connections | TRUE | 100 | 1 | 5/28/2026 | 5/28/2026 | 0 | 0 | 0 | ||||||||||||||||
97 | 95 | Shade Sail Design | FALSE | 0 | 12 | 5/29/2026 | 6/15/2026 | 0 | 0 | 0 | ||||||||||||||||
98 | 96 | shade sail engineering site meeting 1pm | TRUE | 100 | 1 | 6/2/2026 | 6/2/2026 | Caleb Strickler, Casey Copley, Lee Chapin | 0 | 0 | 0 | |||||||||||||||
99 | 97 | Fire System Rough - In-Wall & Ceiling | FALSE | 0 | 39 | 6/4/2026 | 7/29/2026 | 0 | 0 | 0 | 74 | FS | 2 | |||||||||||||
100 | 98 | Plumbing mop sink relocation | TRUE | 100 | 1 | 6/9/2026 | 6/9/2026 | Whitcomb Plumbing | 0 | 0 | 0 | |||||||||||||||