| E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | AA | AB | AC | AD | AE | AF | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Health | WBS | Task Name | Current Duration | Current Start | Current Finish | Predecessors | % Complete | Status | Assigned to | Baseline Start | Baseline Finish | Include in Summary Timeline | Parent_Program | Child_Program | Project_Code | Project_Name | Project_Sponsor | Chair | Vice_Chair | Liaison | Staff_Lead | Project_Manager | Project_Status | Project_Health | Baseline Start2 | Baseline Finish2 | Variance |
2 | 534d | 15-Jan-2026 | 1-Feb-2028 | 4% | In Progress | TRUE | On-Schedule | On-Target | 01/15/26 | 12/27/27 | -26d | |||||||||||||||||
3 | 1 | PROJECT CONTROL | 534d | 15-Jan-2026 | 1-Feb-2028 | 10% | In Progress | TRUE | 01/15/26 | 12/27/27 | -26d | |||||||||||||||||
4 | 1.1 | Project start confirmed | 0 | 15-Jan-2026 | 15-Jan-2026 | 100% | Complete | 01/15/26 | 01/15/26 | 0 | ||||||||||||||||||
5 | 1.2 | Adopt/Confirm charter | 25d | 15-Jan-2026 | 18-Feb-2026 | 3 | 100% | Complete | 01/15/26 | 02/18/26 | 0 | |||||||||||||||||
6 | 1.3 | Confirmation of Team | 18d | 15-Jan-2026 | 9-Feb-2026 | 3 | 80% | Complete | 01/15/26 | 02/09/26 | 0 | |||||||||||||||||
7 | 1.4 | Appointment of Team Chair | 21d | 15-Jan-2026 | 12-Feb-2026 | 3 | 25% | Complete | 01/15/26 | 01/30/26 | -9d | |||||||||||||||||
8 | 1.5 | Appointment of Liaison to GNSO Council | 21d | 15-Jan-2026 | 12-Feb-2026 | 3 | 85% | Complete | 01/15/26 | 03/25/26 | 29d | |||||||||||||||||
9 | 1.6 | Chair / Staff preparations | 15d | 13-Feb-2026 | 5-Mar-2026 | 6 | 0% | Complete | 02/02/26 | 02/13/26 | -14d | |||||||||||||||||
10 | 1.7 | Project Management | 513d | 13-Feb-2026 | 1-Feb-2028 | 0% | In Progress | 02/02/26 | 12/27/27 | -26d | ||||||||||||||||||
11 | 1.7.1 | Develop and confirm Project Plan | 27d | 13-Feb-2026 | 23-Mar-2026 | 6 | 0% | In Progress | 02/02/26 | 03/13/26 | -6d | |||||||||||||||||
12 | 1.7.2 | Obtain project plan approval from GNSO Council | 18d | 24-Mar-2026 | 16-Apr-2026 | 10 | 0% | In Progress | 03/16/26 | 04/24/26 | 6d | |||||||||||||||||
13 | 1.7.3 | Develop monthly Project Packages and deliver to Group & Council | 468d | 17-Apr-2026 | 1-Feb-2028 | 11 | 0% | In Progress | 04/27/26 | 08/13/27 | -122d | |||||||||||||||||
14 | 1.7.4 | Leadership Sub team | 382d | 13-Feb-2026 | 2-Aug-2027 | 0% | In Progress | 02/02/26 | 08/13/27 | 9d | ||||||||||||||||||
15 | 1.7.4.1 | On-going preparation and planning of group activities | 382d | 13-Feb-2026 | 2-Aug-2027 | 6 | 0% | In Progress | 02/02/26 | 08/13/27 | 9d | |||||||||||||||||
16 | 1.7.5 | Close project and transition project to implementation | 1d | 10-Dec-2027 | 10-Dec-2027 | 82 | 0% | In Progress | 12/27/27 | 12/27/27 | 11d | |||||||||||||||||
17 | 2 | GROUP DELIBERATIONS | 230d | 6-Mar-2026 | 21-Jan-2027 | 0% | In Progress | TRUE | 02/16/26 | 10/28/26 | -61d | |||||||||||||||||
18 | 2.1 | First meeting of Team | 1d | 6-Mar-2026 | 6-Mar-2026 | 8 | 0% | In Progress | 02/16/26 | 02/16/26 | -14d | |||||||||||||||||
19 | 2.2 | Overview & initial discussion of all Policy Topics | 15d | 6-Mar-2026 | 26-Mar-2026 | 8 | 0% | In Progress | 02/16/26 | 03/06/26 | -14d | |||||||||||||||||
20 | 2.3 | Understand Charter, organize materials and develop initial approach | 15d | 6-Mar-2026 | 26-Mar-2026 | 8 | 0% | In Progress | 02/16/26 | 02/27/26 | -19d | |||||||||||||||||
21 | 2.4 | Develop definitions and terminology | 15d | 6-Mar-2026 | 26-Mar-2026 | 8 | 0% | In Progress | 02/16/26 | 03/27/26 | 1d | |||||||||||||||||
22 | 2.5 | Input from other SO/ACs & GNSO SG/Cs | 46d | 6-Mar-2026 | 8-May-2026 | 0% | Not Started | 03/02/26 | 07/06/26 | 41d | ||||||||||||||||||
23 | 2.5.1 | Develop template for input | 10d | 6-Mar-2026 | 19-Mar-2026 | 8 | 0% | Not Started | 03/02/26 | 04/03/26 | 11d | |||||||||||||||||
24 | 2.5.2 | Announce input opportunity | 1d | 20-Mar-2026 | 20-Mar-2026 | 22 | 0% | Not Started | 04/06/26 | 04/06/26 | 11d | |||||||||||||||||
25 | 2.5.3 | Collect and collate input in to Review Tool | 15d | 23-Mar-2026 | 10-Apr-2026 | 23 | 0% | Not Started | 04/07/26 | 05/11/26 | 21d | |||||||||||||||||
26 | 2.5.4 | Group to review input and determine relevance to policy deliberations on issues within scope | 20d | 13-Apr-2026 | 8-May-2026 | 24 | 0% | Not Started | 05/12/26 | 07/06/26 | 41d | |||||||||||||||||
27 | 2.6 | Charter Policy Topics | 229d | 9-Mar-2026 | 21-Jan-2027 | 0% | Not Started | TRUE | 03/09/26 | 06/26/26 | -149d | |||||||||||||||||
28 | 2.6.1 | Topic 1 Deliberations - Initiating Associated Domain Check | 94d | 9-Mar-2026 | 16-Jul-2026 | 0% | Not Started | 03/09/26 | 05/01/26 | -54d | ||||||||||||||||||
29 | 2.6.1.1 | Understand topic and determine need to deliberate | 10d | 9-Mar-2026 | 20-Mar-2026 | 17 | 0% | Not Started | 03/09/26 | 03/13/26 | -5d | |||||||||||||||||
30 | 2.6.1.2 | Deliberate policy considerations and determine approach | 10d | 9-Mar-2026 | 20-Mar-2026 | 17 | 0% | Not Started | 03/09/26 | 03/13/26 | -5d | |||||||||||||||||
31 | 2.6.1.3 | Deliberate policy issues | 80d | 27-Mar-2026 | 16-Jul-2026 | 0% | Not Started | 03/16/26 | 04/17/26 | -64d | ||||||||||||||||||
32 | 2.6.1.3.1 | Charter Question 1- What triggers the requirement to investigate associated domain names? | 10d | 27-Mar-2026 | 9-Apr-2026 | 18 | 0% | Not Started | 03/16/26 | 04/17/26 | 6d | |||||||||||||||||
33 | 2.6.1.3.2 | Charter Question 2 - What criteria should be used to define “association” between domains? What elements can be considered to establish such “association”? | 30d | 10-Apr-2026 | 21-May-2026 | 31 | 0% | Not Started | ||||||||||||||||||||
34 | 2.6.1.3.3 | Charter Question 3 - Defining "investigation": What constitutes a "reasonable investigation" by a registrar? What investigation steps are required or recommended? Are the criteria for investigation proportionate and necessary? What is the impact of this investigation on domain name registrants? | 30d | 10-Apr-2026 | 21-May-2026 | 31 | 0% | Not Started | ||||||||||||||||||||
35 | 2.6.1.3.4 | Charter Question 4 - What data access and privacy safeguards are necessary to protect both registrants and registrars during associated domain checks? | 20d | 22-May-2026 | 18-Jun-2026 | 33 | 0% | Not Started | ||||||||||||||||||||
36 | 2.6.1.3.5 | Charter Question 5 - If the associated domain checks have an adverse impact on domain name registrants, are there corresponding remedies? | 20d | 19-Jun-2026 | 16-Jul-2026 | 34 | 0% | Not Started | ||||||||||||||||||||
37 | 2.6.1.3.6 | Charter Question 6 - What are appropriate timelines and thresholds for initiating and concluding the associated domain check? | 20d | 10-Apr-2026 | 7-May-2026 | 31 | 0% | Not Started | ||||||||||||||||||||
38 | 2.6.1.3.7 | Develop draft work product (incl. initial impact analysis) | 30d | 8-May-2026 | 18-Jun-2026 | 36 | 0% | Not Started | ||||||||||||||||||||
39 | 2.6.1.3.8 | Conduct First Reading + verbal and email response | 5d | 19-Jun-2026 | 25-Jun-2026 | 37 | 0% | Not Started | ||||||||||||||||||||
40 | 2.6.1.3.9 | Conduct Second Reading + verbal response + adoption or discard | 5d | 26-Jun-2026 | 2-Jul-2026 | 38 | 0% | Not Started | ||||||||||||||||||||
41 | 2.6.1.3.10 | Confirm draft as stable | 0 | 2-Jul-2026 | 2-Jul-2026 | 39 | 0% | Not Started | ||||||||||||||||||||
42 | 2.6.2 | Topic 2 Deliberations - Demonstrating Compliance | 95d | 3-Jul-2026 | 12-Nov-2026 | 0% | Not Started | 05/04/26 | 06/26/26 | -99d | ||||||||||||||||||
43 | 2.6.2.1 | Understand topic and determine need to deliberate | 10d | 3-Jul-2026 | 16-Jul-2026 | 40 | 0% | Not Started | 05/04/26 | 05/08/26 | -49d | |||||||||||||||||
44 | 2.6.2.2 | Deliberate policy considerations and determine approach | 10d | 3-Jul-2026 | 16-Jul-2026 | 40 | 0% | Not Started | 05/04/26 | 05/08/26 | -49d | |||||||||||||||||
45 | 2.6.2.3 | Deliberate policy issues | 85d | 17-Jul-2026 | 12-Nov-2026 | 0% | Not Started | 05/11/26 | 06/12/26 | -109d | ||||||||||||||||||
46 | 2.6.2.3.1 | Topic 2 - Charter Question - What specific requirements are necessary to implement this policy and what parts can be subject to best practices, or potentially left to the discretion of the contracted party? | 30d | 17-Jul-2026 | 27-Aug-2026 | 43 | 0% | Not Started | 05/11/26 | 06/12/26 | -54d | |||||||||||||||||
47 | 2.6.2.3.2 | Topic 2 - Charter Question - What metrics will be used to evaluate the policy's effectiveness? | 30d | 17-Jul-2026 | 27-Aug-2026 | 43 | 0% | Not Started | ||||||||||||||||||||
48 | 2.6.2.3.3 | Topic 2 - Charter Question - How can registrars demonstrate their compliance with the obligations to ICANN and what types of evidence and information can registrars submit? | 20d | 28-Aug-2026 | 24-Sep-2026 | 46 | 0% | Not Started | ||||||||||||||||||||
49 | 2.6.2.3.4 | Develop draft work product (incl. initial impact analysis) | 25d | 25-Sep-2026 | 29-Oct-2026 | 47 | 0% | Not Started | ||||||||||||||||||||
50 | 2.6.2.3.5 | Conduct First Reading + verbal and email response | 5d | 30-Oct-2026 | 5-Nov-2026 | 48 | 0% | Not Started | ||||||||||||||||||||
51 | 2.6.2.3.6 | Conduct Second Reading + verbal response + adoption or discard | 5d | 6-Nov-2026 | 12-Nov-2026 | 49 | 0% | Not Started | ||||||||||||||||||||
52 | 2.6.2.3.7 | Confirm draft as stable | 0 | 12-Nov-2026 | 12-Nov-2026 | 50 | 0% | Not Started | ||||||||||||||||||||
53 | 2.6.3 | Topic 3 - Impact Assessment | 50d | 13-Nov-2026 | 21-Jan-2027 | 0% | Not Started | |||||||||||||||||||||
54 | 2.6.3.1 | Consideration on Human Rights Impact and determine approach | 15d | 13-Nov-2026 | 3-Dec-2026 | 51 | 0% | Not Started | ||||||||||||||||||||
55 | 2.6.3.2 | Considerations for GPI and determine approach | 15d | 13-Nov-2026 | 3-Dec-2026 | 51 | 0% | Not Started | ||||||||||||||||||||
56 | 2.6.3.3 | Consideration for Data Privacy Impat and determine approach | 15d | 13-Nov-2026 | 3-Dec-2026 | 51 | 0% | Not Started | ||||||||||||||||||||
57 | 2.6.3.4 | Consideration of Impact on Other/Existing Consensus Policies and determine approach | 15d | 13-Nov-2026 | 3-Dec-2026 | 51 | ||||||||||||||||||||||
58 | 2.6.3.5 | Develop draft work product | 15d | 4-Dec-2026 | 24-Dec-2026 | 53, 54, 55 | 0% | Not Started | ||||||||||||||||||||
59 | 2.6.3.6 | Conduct First Reading + verbal and email response | 15d | 25-Dec-2026 | 14-Jan-2027 | 57 | 0% | Not Started | ||||||||||||||||||||
60 | 2.6.3.7 | Conduct Second Reading + verbal response + adoption or discard | 5d | 15-Jan-2027 | 21-Jan-2027 | 58 | 0% | Not Started | ||||||||||||||||||||
61 | 2.6.3.8 | Confirm draft as stable | 0 | 21-Jan-2027 | 21-Jan-2027 | 59 | 0% | Not Started | ||||||||||||||||||||
62 | 2.7 | Key Group Events | 166d | 7-Mar-2026 | 23-Oct-2026 | 0% | Not Started | 03/07/26 | 10/28/26 | 3d | ||||||||||||||||||
67 | 3 | INITIAL REPORT | 295d | 27-Mar-2026 | 13-May-2027 | 0% | In Progress | TRUE | 03/30/26 | 05/07/27 | -4d | |||||||||||||||||
68 | 3.1 | Populate stable drafts as required | 200d | 27-Mar-2026 | 31-Dec-2026 | 20 | 0% | In Progress | 03/30/26 | 02/12/27 | 31d | |||||||||||||||||
69 | 3.2 | Discuss/approve findings and interim recommendations | 200d | 27-Mar-2026 | 31-Dec-2026 | 20 | 0% | In Progress | 02/15/27 | 02/26/27 | 41d | |||||||||||||||||
70 | 3.3 | Consolidate interim recommendations and findings | 20d | 1-Jan-2027 | 28-Jan-2027 | 68 | 0% | Not Started | 03/01/27 | 03/12/27 | 31d | |||||||||||||||||
71 | 3.4 | Finalize Draft Report for public comment | 15d | 29-Jan-2027 | 18-Feb-2027 | 69 | 0% | Not Started | 03/01/27 | 03/12/27 | 16d | |||||||||||||||||
72 | 3.5 | Approve Draft Report for public comment | 15d | 19-Feb-2027 | 11-Mar-2027 | 70 | 0% | Not Started | 03/15/27 | 03/19/27 | 6d | |||||||||||||||||
73 | 3.6 | Publish Initial Report | 1d | 12-Mar-2027 | 12-Mar-2027 | 71 | 0% | Not Started | TRUE | 03/19/27 | 03/19/27 | 5d | ||||||||||||||||
74 | 3.7 | Communicate Initial Report | 15d | 12-Mar-2027 | 1-Apr-2027 | 71 | 0% | Not Started | 03/22/27 | 03/26/27 | -4d | |||||||||||||||||
75 | 3.8 | Public comment forum on the Initial Report (45 days) +14 Days | 45d | 12-Mar-2027 | 13-May-2027 | 71 | 0% | Not Started | 03/22/27 | 05/07/27 | -4d | |||||||||||||||||
76 | 4 | FINAL REPORT | 80d | 14-May-2027 | 2-Sep-2027 | 0% | Not Started | TRUE | 05/10/27 | 08/06/27 | -19d | |||||||||||||||||
77 | 4.1 | Review of public comments | 60d | 14-May-2027 | 5-Aug-2027 | 74 | 0% | Not Started | TRUE | 05/10/27 | 06/18/27 | -34d | ||||||||||||||||
78 | 4.2 | Continue deliberations of policy topics towards a Final Report | 60d | 14-May-2027 | 5-Aug-2027 | 74 | 0% | Not Started | 05/10/27 | 07/16/27 | -14d | |||||||||||||||||
79 | 4.3 | Build Final Report & Final Deliberations | 70d | 14-May-2027 | 19-Aug-2027 | 74 | 0% | Not Started | 07/19/27 | 07/23/27 | -19d | |||||||||||||||||
80 | 4.4 | Determine consensus levels on interim recommendations | 10d | 20-Aug-2027 | 2-Sep-2027 | 78 | 0% | Not Started | 07/26/27 | 08/06/27 | -19d | |||||||||||||||||
81 | 4.5 | Adopt final recommendations and report | 5d | 20-Aug-2027 | 26-Aug-2027 | 78 | 0% | Not Started | 07/26/27 | 08/06/27 | -14d | |||||||||||||||||
82 | 4.6 | Submission of Final Report to the GNSO Council | 0 | 26-Aug-2027 | 26-Aug-2027 | 80 | 0% | Not Started | TRUE | 08/06/27 | 08/06/27 | -14d | ||||||||||||||||
83 | 5 | POST GROUP TASKS | 75d | 27-Aug-2027 | 9-Dec-2027 | 0% | Not Started | 08/09/27 | 12/24/27 | 11d | ||||||||||||||||||
84 | 5.1 | Approval of Final Report and Recommendations by the GNSO Council | 20d | 27-Aug-2027 | 23-Sep-2027 | 81 | 0% | Not Started | 08/09/27 | 10/08/27 | 11d | |||||||||||||||||
85 | 5.2 | Report to the Board | 20d | 24-Sep-2027 | 21-Oct-2027 | 83 | 0% | Not Started | 10/11/27 | 11/05/27 | 11d | |||||||||||||||||
86 | 5.3 | Publish Recommendations for Public Comment | 35d | 22-Oct-2027 | 9-Dec-2027 | 84 | 0% | Not Started | 11/08/27 | 12/24/27 | 11d | |||||||||||||||||
87 | 5.4 | Inform GAC if Recommendations affect public policy | 20d | 22-Oct-2027 | 18-Nov-2027 | 84 | 0% | Not Started | 11/08/27 | 11/19/27 | 1d | |||||||||||||||||
88 | ||||||||||||||||||||||||||||
89 | PDP CHECKLIST | 1d | 6-Mar-2026 | 6-Mar-2026 | 08/08/25 | 12/24/26 | 209d | |||||||||||||||||||||
90 | 1 | PDP CHECKLIST | 1d | 6-Mar-2026 | 6-Mar-2026 | 08/08/25 | 12/24/26 | 209d | ||||||||||||||||||||
91 | 1.1 | Request for an Issue Report | 1d | 6-Mar-2026 | 6-Mar-2026 | GNSO Council | 08/08/25 | 08/08/25 | -151d | |||||||||||||||||||
92 | 1.2 | Preliminary Issue Report | 1d | 6-Mar-2026 | 6-Mar-2026 | Policy Staff | 09/08/26 | 09/08/26 | 131d | |||||||||||||||||||
93 | 1.3 | Public Comment Forum on the Preliminary Issue Report | 1d | 6-Mar-2026 | 6-Mar-2026 | Policy Staff | 09/08/26 | 11/02/26 | 171d | |||||||||||||||||||
94 | 1.4 | Final Issue Report | 1d | 6-Mar-2026 | 6-Mar-2026 | Policy Staff | 12/01/26 | 12/01/26 | 191d | |||||||||||||||||||
95 | 1.5 | Initiation of the PDP | 1d | 6-Mar-2026 | 6-Mar-2026 | GNSO Council | 12/10/26 | 12/10/26 | 198d | |||||||||||||||||||
96 | 1.6 | Drafting of the WG Charter | 1d | 6-Mar-2026 | 6-Mar-2026 | GNSO Council, Policy Staff | 12/16/26 | 12/24/26 | 209d | |||||||||||||||||||
97 | 1.7 | Approval of the WG Charter | 1d | 6-Mar-2026 | 6-Mar-2026 | GNSO Council | 01/15/26 | 01/15/26 | -37d | |||||||||||||||||||
98 | 1.8 | Input from other SO/ACs/GNSO SG/C | 1d | 6-Mar-2026 | 6-Mar-2026 | Working Group | 03/07/26 | 03/17/26 | 7d | |||||||||||||||||||
99 | 1.9 | Initial Report | 1d | 6-Mar-2026 | 6-Mar-2026 | Working Group, Policy Staff | 01/08/26 | 01/08/26 | -42d | |||||||||||||||||||
100 | 1.10 | Public Comment Forum on the Initial Report | 1d | 6-Mar-2026 | 6-Mar-2026 | Policy Staff | 01/01/26 | 01/01/26 | -47d | |||||||||||||||||||
101 | 1.11 | Publication of Draft Final Report (Optional) | 1d | 6-Mar-2026 | 6-Mar-2026 | Working Group, Policy Staff | 01/01/26 | 01/01/26 | -47d | |||||||||||||||||||
102 | 1.12 | Final Report | 1d | 6-Mar-2026 | 6-Mar-2026 | GNSO Council | 01/01/26 | 01/01/26 | -47d | |||||||||||||||||||
103 | 1.13 | Approval of Final Report and Recommendations | 1d | 6-Mar-2026 | 6-Mar-2026 | GNSO Council | 01/01/26 | 01/01/26 | -47d | |||||||||||||||||||
104 | 1.14 | Report to the Board | 1d | 6-Mar-2026 | 6-Mar-2026 | GNSO Council, Policy Staff | 01/01/26 | 01/01/26 | -47d |