| A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | AA | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Maintenance Reserve 3 Year Projection Plans | ||||||||||||||||||||||||||
2 | School | Maintenance | FY24 Priority | FY24 Projected Budget | FY25 Projected Budget | FY26 Projected Budget | Comments | Bid/RFP | Door system Ray has actual quotes. Sq ft costs from vendors | ||||||||||||||||||
3 | HUHS | Roof work- FY24 replace 36,184 sq. ft EPDM roofing over gym, auditorium, and art areas Last replaced in 2000. We have already repaired roof leaks in this area this year. FY 25 replace 37,750 sq. ft. EPDM roofing over the library, LRC, and administrative areas FY 26 replace 9,152 sq. ft. over the cafeteria | Must Phased project | $452,300 | $471,875 | $114,400 | gym and art wing 12.50 per sq st. | ||||||||||||||||||||
4 | HUHS | Flooring upgrades Replace carpet in the LRC. The existing carpet is 10 years old and we have been receiving several concerns about IAQ in this area. We have had the area tested and the results were negative for any harmful contaminants. The replacement carpet is significantly easier to maintain and less prone to harboring harmful contaminants. | Must | $46,000 | $30,000 | $30,000 | FY24 Learning Resource Center carpet needs to be replace with Flotex carpeting due to air quality concerns. Ongoing not critical. | ||||||||||||||||||||
5 | HUHS | Folding partitions Replace existing failed or failing folding classroom partitions in the MS | Must | $25,000 | $25,000 | Middle school | |||||||||||||||||||||
6 | HUHS | Parking Lot Repairs: Ongoing repairs to fill potholes and broken asphalt | Must | $20,000 | $20,000 | $20,000 | |||||||||||||||||||||
7 | HUHS | Kate's garden wrought iron fence Install security fence with access controls in order to make the area secure for student use during the school day | Must | $25,000 | Security barrier | ||||||||||||||||||||||
8 | HUHS | Walls for Humanities Classrooms: Install fixed walls in place of the failed folding partitions | Must | $20,000 | Between classrooms, moveable partitions non-functional. Need framed walls vs. folding partitions | ||||||||||||||||||||||
9 | HUHS | HVAC Upgrade: Replacement and upgrade ventilation equipment to meet current standards. | Schedule for FY25 & FY26 | $1,600,000 | $1,600,000 | Phase 1 is +/- 20% of the building | |||||||||||||||||||||
10 | HUHS | Door Replacements: Replace exterior door systems that are failing due to age and abuse | Schedule for FY25 & FY26 | $50,000 | |||||||||||||||||||||||
11 | HUHS | Entry Door Replacements: Replace Entrance doors due to age and abuse | $35,000 | $35,000 | Steel doors, 1 next to Ray office and 1 by the gym and then the following year | ||||||||||||||||||||||
12 | HUHS | Rekeying building Locks- Rekeying entire building. Old locks need to be replaced and rekeyed. | Needed | $40,000 | |||||||||||||||||||||||
13 | CBMS | Replacement of back door Replace back door by band room due to age and structural failure | Needed | $8,000 | This may want to be budgeted out of GF current year projects | ||||||||||||||||||||||
14 | CBMS | Flooring: Replace outdated flooring in halls and classrooms. New materials save approximately $.50/ sqft annually in maintenance supplies. | Push out | $35,000 | $25,000 | ||||||||||||||||||||||
15 | CBMS | HVAC control upgrade: Control modules within the system are outdated and should be replaced before they fail | Must | $54,000 | $54,000 | $54,000 | Outdate system, TCV is going to evaluate this system. All other schools are under Control Tech Updated pricing as of 2/14/2023 | ||||||||||||||||||||
16 | CBMS | Resurfacing of the Gym Floor: Resurfacing required due to damage over the years. | Must | $30,000 | Placeholder waiting on contractor to give a price | ||||||||||||||||||||||
17 | CBMS | Additional access controls: Adding 4 doors to the access control system. This will resolve a safety concern with teachers taking classes outside and allowing easy access back into the building vs. walking around the building to enter through one of the access controlled doors. | Must | $25,000 | TBD/The could possible be budgeted out of the GF. Safety issue. | ||||||||||||||||||||||
18 | CBMS | Parking lot repairs: Ongoing repairs to fill potholes and broken asphalt | Must | $15,000 | $15,000 | $15,000 | |||||||||||||||||||||
19 | CBMS | Classroom Folding Partitions: Replace existing failed or failing folding classroom partitions | Needed | $25,000 | $25,000 | $25,000 | Phased project. These folding partitions are failing and need to be replaced. | ||||||||||||||||||||
20 | Fayston | Replace preschool playground fencing: Replace existing preschool playground wire fencing with chain link fencing. This is to resolve a safety concern. | Must | $12,000 | Safety concern-just chicken wire currently | ||||||||||||||||||||||
21 | Fayston | Roof replacement: Replace 75% of the existing standing seam roof over 3 years. The first section has been experiencing some roof leaks over the past few years. | Need | $95,900 | $150,300 | $119,200 | Some leaks that have been patched. Gutters over the kitchen doors would be rolled into this project. water and ice drips delivery door by kitchen. | ||||||||||||||||||||
22 | Fayston | Flooring: Replace outdated flooring in halls and classrooms. New materials save approximately $.50/ sqft annually in maintenance supplies. | Need | $10,000 | $ 10,000 | Carpet/Flooring the remainder of the Halls 3 class rooms, however the Preschool space is a need. Plan to phase this work in each summer | |||||||||||||||||||||
23 | Fayston | Parking Lot and curb repair: Repair parking lot and curbs in entrance loop | $15,000 | ||||||||||||||||||||||||
24 | Fayston | HVAC DDC: This is the only school in our district without Direct Digital Control(DDC) of the HVAC systems. These controls allow us to regulate the systems to maximize efficiencies and better regulate heat and ventilation in the building. | Must | $85,000 | High Priority | ||||||||||||||||||||||
25 | Fayston | Repave Basketball Court: Resurface paved court due to cracking | Need | $21,160 | Should be done but not a priority ashalt is cracking | ||||||||||||||||||||||
26 | Moretown | Drainage/Stormwater/Parking lot-Town Directed, overall price unknown, engineering in process | $28,751.00 | Town Estimate of School Share $54,315 Total, parking lot amount? | |||||||||||||||||||||||
27 | Moretown | Flooring: Replace outdated flooring in halls and classrooms. New materials save approximately $.50/ sqft annually in maintenance supplies. | Partial must | $25,000 | $25,000 | $25,000 | One area in the basement is a priority | ||||||||||||||||||||
28 | Moretown | Entrance Door replacement: Replace Entrance doors due to age and abuse | Must | $15,000 | Safety issue a lot of rot | ||||||||||||||||||||||
29 | Moretown | HVAC: Replacement and upgrade ventilation equipment to meet current standards. | TBD | TBD | Most likely pushed to FY25 | ||||||||||||||||||||||
30 | Moretown | Water Softener: Install water softening system to reduce minerals in the water and address water aesthetics(taste) | Must | $18,000 | |||||||||||||||||||||||
31 | Moretown | Replace membrane portion of roof (plan for 2029) | $112,000 for FY29 Placeholder | ||||||||||||||||||||||||
32 | Moretown | Repaint Gym Walls | Needed | $13,720 | |||||||||||||||||||||||
33 | Warren | Enclose the gym: Installation of a wall between the hallway and the gym to reduce noise from the gym. | Possibly a much bigger project than expected | $18,000 | Ray walked the Fire Marshal through the project and he connerns about egress on the upper level (issues egress that goes through class rooms, three classrooms in the basement-only 1 has a second means or egress. we might need to install egress windows) This cost will increase with egress issues, fire door installation, additional walls possibly enclosing the library as well. We need to have the architect look at these. The Fire Marshal is going to send us his recommendations/requirements. | ||||||||||||||||||||||
34 | Warren | Flooring: Replace outdated flooring in halls and classrooms. New materials save approximately $.50/ sqft annually in maintenance supplies. | Must | $9,850 | $15,000 | $15,000 | Back stairway tripping hazard | ||||||||||||||||||||
35 | Warren | Asbestos abatement: Required if replacing floors | $3,500 | $8,000 | Flooring abatement | ||||||||||||||||||||||
36 | Warren | Sprinkler system: Replace sprinkler pumps. Currently seeking additional proposals | Must | $30,000 | Getting quotes | ||||||||||||||||||||||
37 | Waitsfield | Kitchen upgrade to Commercial | $1,045,849 | Approved by the Board to move forward | |||||||||||||||||||||||
38 | Waitsfield | Replace Main Entrance doors: Replace doors to allow for more secure access control hardware | $25,000 | ||||||||||||||||||||||||
39 | Waitsfield | Roof replacement of the school : Roof is at the end of it's warranteed life | $500,000 | ||||||||||||||||||||||||
40 | Brookside | Flooring: Replace outdated flooring in halls and classrooms. New materials save approximately $.50/ sqft annually in maintenance supplies. | $25,000 | $25,000 | This could be pushed off to FY25 | ||||||||||||||||||||||
41 | Brookside | Front Steps: Replace concrete steps on the front of the North and South Buildings | Must | $30,033 | Safety Issue | ||||||||||||||||||||||
42 | Brookside | Playground Basketball Court: Replace existing playground court due to asphalt heaving, safety concern | Must | $62,191 | Not safe for students to play on | ||||||||||||||||||||||
43 | Brookside | Replace Entrance Doors: Replace entrance doors on the front of the south building due to age | Must | $19,400 | $20,000 | $20,000 | Orginal Door | ||||||||||||||||||||
44 | Brookside | Replace Windows: Replace windows due to age. Requested grant funding from Efficiency VT to help offset costs. First phase in south building. @nd phase is the gym, third and fourth phases TBD | Maybe | $160,000 | $100,000 | $160,000 | |||||||||||||||||||||
45 | Brookside | North Building rear entrance: Replace existing structure due to structural deterioration. Still waiting for engineers' updated Opinion of Cost. | Must | $100,000 | air lock entry to maintain the interity, the footings need to be replace-This is an emergency exit. This is a potential safety issue | ||||||||||||||||||||||
46 | Brookside | HVAC Upgrade: This is a 3 year project, Year 1- install additional ventilation ducting to areas underserved, Year 2 replace 2 HVAC units, Year 3 complete humidity controls throughout the buildings | Must | $100,000 | $500,000 | $1,400,000 | |||||||||||||||||||||
47 | ALL SCHOOLS | Fluorescent Lighting Upgrades: VT law prohibits the sale of fluorescent light bulbs after December 31, 2023. This necessitates replacing all fluorescent fixtures with LED fixtures. | $250,000 | TBD | TBD | May be able to spread this out into 2026, we are working with a plan with effeciency Vermont. Green Mountain Electrical Supply believes ROI paybak of project costs within 18 months. Electric savings and engery costs. We had consultants come out and walk thru the HS the third week in January. At this time they have been to 6 schools and anticipate doing the last site review on2/17. Once we have their plan we will meet with Efficiency VT to discuss the incentives grants. | |||||||||||||||||||||
48 | Total | $3,023,654 | $3,698,175 | $3,647,600 | |||||||||||||||||||||||
49 | |||||||||||||||||||||||||||
50 | |||||||||||||||||||||||||||
51 | |||||||||||||||||||||||||||
52 | |||||||||||||||||||||||||||
53 | |||||||||||||||||||||||||||
54 | |||||||||||||||||||||||||||
55 | |||||||||||||||||||||||||||
56 | |||||||||||||||||||||||||||
57 | |||||||||||||||||||||||||||
58 | |||||||||||||||||||||||||||
59 | |||||||||||||||||||||||||||
60 | |||||||||||||||||||||||||||
61 | |||||||||||||||||||||||||||
62 | |||||||||||||||||||||||||||
63 | |||||||||||||||||||||||||||
64 | |||||||||||||||||||||||||||
65 | |||||||||||||||||||||||||||
66 | |||||||||||||||||||||||||||
67 | |||||||||||||||||||||||||||
68 | |||||||||||||||||||||||||||
69 | |||||||||||||||||||||||||||
70 | |||||||||||||||||||||||||||
71 | |||||||||||||||||||||||||||
72 | |||||||||||||||||||||||||||
73 | |||||||||||||||||||||||||||
74 | |||||||||||||||||||||||||||
75 | |||||||||||||||||||||||||||
76 | |||||||||||||||||||||||||||
77 | |||||||||||||||||||||||||||
78 | |||||||||||||||||||||||||||
79 | |||||||||||||||||||||||||||
80 | |||||||||||||||||||||||||||
81 | |||||||||||||||||||||||||||
82 | |||||||||||||||||||||||||||
83 | |||||||||||||||||||||||||||
84 | |||||||||||||||||||||||||||
85 | |||||||||||||||||||||||||||
86 | |||||||||||||||||||||||||||
87 | |||||||||||||||||||||||||||
88 | |||||||||||||||||||||||||||
89 | |||||||||||||||||||||||||||
90 | |||||||||||||||||||||||||||
91 | |||||||||||||||||||||||||||
92 | |||||||||||||||||||||||||||
93 | |||||||||||||||||||||||||||
94 | |||||||||||||||||||||||||||
95 | |||||||||||||||||||||||||||
96 | |||||||||||||||||||||||||||
97 | |||||||||||||||||||||||||||
98 | |||||||||||||||||||||||||||
99 | |||||||||||||||||||||||||||
100 |