ITEM #DESCRIPTION
QUANTITY
UNITUNIT COST
(Labor+ Material)
TOTAL COST
(Labor+ Material)
TRADE COST
7
Division 01 — General Requirements
8
Supervision1.0LS0.0$0
9
Permits1.0LS0.0$0
10
Final Cleanup1.0LS0.0$0
11
Mobilization Costs 1.0LS0.0$0
12
Project Overheads1.0LS0.0$0
13
Bonds1.0LS0.0$0
14
Temporary Control & Facilities1.0LS0.0$0
15
Subtotal (General Requirements)$0
16
02 — Site Construction
17
DEMOLITION
18
8EXISTING 6" STEP TO BE REMOVED11.95FT12.0$143
19
913" RWD TO BE REMOVED1EA60.0$60
20
1032" RWD TO BE REMOVED1EA69.6$70
21
1119" RWD TO BE REMOVED1EA62.4$62
22
1237" RWD TO BE REMOVED1EA76.8$77
23
135-10" RWD TREES TO BE REMOVED1EA48.0$48
24
1410" RWD TO BE REMOVED1EA52.8$53
25
1511" MAPLE TO BE REMOVED1EA55.2$55
26
16EXISTING WALLS TO BE REMOVED90.86FT15.0$1,363
27
17REMOVE DOORS4EA65.0$260
28
SITEWORK$0
29
18EXCAVATION AND DISPOSE48CY95.0$4,560
30
19AC (AIR CONDITION)1EA2500.0$2,500
31
20PROTECTIVE TREE FENCE106.96FT18.0$1,925
32
21WM (WATER METER)1EA350.0$350
33
34
Subtotal (Site Construction)$11,526
35
Division 03 — Concrete
36
CONCRETE WORK
37
2216" PILE (#3 SPIRAL TIE AT 3" PITCH IN TOP HALF OF PIER AND AT 6" PITCH IN BOTTOM HALF OF PIER )25.45741917CY850.0$21,639
38
232'-0" SQUARE X 18" DEEP PAD FOOTING FOR COLUMN, REINFORCED0.4444444444CY1250.0$556
39
24BEAM 8" WIDTH X 18" DEEP GRADE BEAM, REINFORCED9.608296296CY900.0$8,647
40
252'-4" WIDTH X 12" DEEP CONCRETE FOOTING2.3CY890.0$2,047
41
42
Subtotal (CONCRETE)$32,889
43
Division 05 — Metals
44
26STRAP45.0FT15.0$675
45
27FRAMING METALS1.0LS3500.0$3,500
46
Subtotal (METALS)$4,175
47
Division 06 — Wood and Plastics
48
WALL FRAMING
49
282 x 6 INTERIOR INSULATION310.8FT4.5$1,399
50
292 X 6 WITHOUT INSULATION101.0FT4.5$454
51
302 X 4 INTERIOR STUD WALL411.1FT3.2$1,316
52
312 x 4 INTERIOR INSULATION688.2SQ FT3.2$2,202
53
32EXTERIOR STUD WALL879.7FT4.5$3,959
54
33TOP PLATE648.0FT2.0$1,296
55
34BOTTOM PLATE324.0FT2.0$648
56
357/8" PLYWOOD SHEATHING3311.0SQ FT4.0$13,244
57
FLOOR/ROOF FRAMING$0
58
362 X 8 AT 16" O.C. WITH TYP. FLOOR SHEATHING PER PLAN1460.0FT5.6$8,176
59
37NEW ROOF TRUSS3284.0SQ FT12.0$39,408
60
38TYPICAL ROOF SHEATHING3284.0SQ FT4.2$13,793
61
39FLOOR SHEATHING1952.0SQ FT4.0$7,808
62
40DRAG TRUSS1556.0SQ FT3.8$5,913
63
FRAMING LUMBER
64
416 X 10 CEILING BEAM3.9FT18.2$71
65
424 X 10 BEAM13.5FT16.0$216
66
436 X 10 HEADER10.0FT18.2$183
67
446 X 12 CONT.HEADER34.3FT26.8$920
68
455.25 X 11.875 LVL HEADER65.3FT19.0$1,240
69
464 X 10 HEADER6.7FT16.0$107
70
474 X 12 HEADER3.1FT22.0$68
71
484 X 4 POST2.0EA35.0$70
72
494 X 6 POST4.0EA55.0$220
73
506 X 6 KING POST10.0EA68.0$680
74
512- 2 X 6 TRIM11.0EA25.0$275
75
522- 2 X 4 TRIM3.0EA19.0$57
76
FINISH CARPENTRY
77
53KITCHEN COUNTER TOP26.59SQ FT45.0$1,197
78
54KITCHEN TOP CABINETS15.81FT45.0$711
79
55KITCHEN LOWER CABINETS11.56FT185.0$2,139
80
56CLOSET MILLWORK43.91FT455.0$19,979
81
57LAUNDRY COUNTER TOP18.7SQ FT45.0$842
82
58LAUNDRY TOP CABINETS9.63FT185.0$1,782
83
59LAUNDRY LOWER CABINETS9.59FT185.0$1,774
84
Subtotal (Wood and Plastics)$132,145
85
Division 07 — Thermal and Moisture Protection
86
60WALL INSULATION3686.0SQ FT2.1$7,741
87
61FLOOR INSULATION2655.0SQ FT2.0$5,310
88
62ROOF INSULATION3284.0SQ FT2.3$7,553
89
Subtotal (Thermal and Moisture Protection )$20,604
90
Division 08 — Doors and Windows
91
DOORS & FRAMES
92
632'-6" DOOR2.0EA1150.0$2,300
93
642'-8" DOOR7.0EA100.0$700
94
653'-0" DOOR3.0EA1280.0$3,840
95
662'-2" DOOR3.0EA650.0$1,950
96
HARDWARE
97
67NO. OF SETS15.0EA155.0$2,325
98
WINDOWS
99
6816' X 8' WINDOW4.0EA3360.0$13,440
100
696' X 6' WINDOW3.0EA1680.0$5,040
101
7010' X 6' WINDOW1.0EA2240.0$2,240