| D | E | F | G | H | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | AA | |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 | Task Name | Job Description | Duration | Start | Finish | % Progres | |||||||||||||||
2 | Instrumen | 7 days | 4/9/26 7:30 | 4/16/26 7:30 | |||||||||||||||||
3 | Instrument STG BB | 6,57 days | 4/9/26 7:30 | 4/15/26 21:15 | |||||||||||||||||
4 | Control Valve | 3,39 days | 4/9/26 7:30 | 4/12/26 16:45 | |||||||||||||||||
5 | Boiler & Steam System | 2,32 days | 4/9/26 7:30 | 4/11/26 15:15 | |||||||||||||||||
6 | Start work | 0 days | 4/9/26 7:30 | 4/9/26 7:30 | |||||||||||||||||
7 | F6P-2001BO/TCD-2433A1 : BOILER #2 | Cek, service ditempat, ganti Oring TCD-2433A1 | 0,16 days | 4/9/26 7:30 | 4/9/26 11:15 | ||||||||||||||||
8 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/9/26 7:30 | 4/9/26 7:45 | 100 | ||||||||||||||||
9 | Overall visual check | 0,25 hrs | 4/9/26 7:45 | 4/9/26 8:00 | 100 | ||||||||||||||||
10 | Restroke Control Valve langsung dari DCS dan catat opening feedback CV di DCS dan di lapangan sebelum dan sesudah perbaikan. | 0,75 hrs | 4/9/26 8:00 | 4/9/26 8:45 | 100 | ||||||||||||||||
11 | Check dan service ganti oring | 2 hrs | 4/9/26 8:45 | 4/9/26 10:45 | 100 | ||||||||||||||||
12 | Check fungsi ketika sinyal fail--> Open atau Close. | 0,25 hrs | 4/9/26 10:45 | 4/9/26 11:00 | 100 | ||||||||||||||||
13 | Overall check | 0,25 hrs | 4/9/26 11:00 | 4/9/26 11:15 | 100 | ||||||||||||||||
14 | F6P-TV2433A1 : ACTUATOR CONTROL DAMPER ECONOMIZER | Restroke | 0,08 days | 4/9/26 7:30 | 4/9/26 9:30 | ||||||||||||||||
15 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/9/26 7:30 | 4/9/26 7:45 | 100 | ||||||||||||||||
16 | Overall visual check | 0,25 hrs | 4/9/26 7:45 | 4/9/26 8:00 | 100 | ||||||||||||||||
17 | Restroke Control Valve langsung dari DCS dan catat opening feedback CV di DCS dan di lapangan sebelum dan sesudah perbaikan. | 0,75 hrs | 4/9/26 8:00 | 4/9/26 8:45 | 100 | ||||||||||||||||
18 | Check dan service accessoris control valve. | 0,25 hrs | 4/9/26 8:45 | 4/9/26 9:00 | 100 | ||||||||||||||||
19 | Check fungsi ketika sinyal fail--> Open atau Close. | 0,25 hrs | 4/9/26 9:00 | 4/9/26 9:15 | 100 | ||||||||||||||||
20 | Overall check | 0,25 hrs | 4/9/26 9:15 | 4/9/26 9:30 | 100 | ||||||||||||||||
21 | F6P-TV2433A2 : ACTUATOR CONTROL DAMPER ECONOMIZER | Restroke | 0,08 days | 4/9/26 9:15 | 4/9/26 11:15 | ||||||||||||||||
22 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/9/26 9:15 | 4/9/26 9:30 | 100 | ||||||||||||||||
23 | Overall visual check | 0,25 hrs | 4/9/26 9:30 | 4/9/26 9:45 | 100 | ||||||||||||||||
24 | Restroke Control Valve langsung dari DCS dan catat opening feedback CV di DCS dan di lapangan sebelum dan sesudah perbaikan. | 0,75 hrs | 4/9/26 9:45 | 4/9/26 10:30 | 100 | ||||||||||||||||
25 | Check dan service accessoris control valve. | 0,25 hrs | 4/9/26 10:30 | 4/9/26 10:45 | 100 | ||||||||||||||||
26 | Check fungsi ketika sinyal fail--> Open atau Close. | 0,25 hrs | 4/9/26 10:45 | 4/9/26 11:00 | 100 | ||||||||||||||||
27 | Overall check | 0,25 hrs | 4/9/26 11:00 | 4/9/26 11:15 | 100 | ||||||||||||||||
28 | F6P-TV2433B : ACTUATOR CONTROL DAMPER ECONOMIZER | Restroke | 0,17 days | 4/9/26 11:00 | 4/9/26 15:00 | ||||||||||||||||
29 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/9/26 11:00 | 4/9/26 11:15 | 100 | ||||||||||||||||
30 | Overall visual check | 0,25 hrs | 4/9/26 11:15 | 4/9/26 11:30 | 100 | ||||||||||||||||
31 | Restroke Control Valve langsung dari DCS dan catat opening feedback CV di DCS dan di lapangan sebelum dan sesudah perbaikan. | 0,75 hrs | 4/9/26 13:30 | 4/9/26 14:15 | 100 | ||||||||||||||||
32 | Check dan service accessoris control valve. | 0,25 hrs | 4/9/26 14:15 | 4/9/26 14:30 | 100 | ||||||||||||||||
33 | Check fungsi ketika sinyal fail--> Open atau Close. | 0,25 hrs | 4/9/26 14:30 | 4/9/26 14:45 | 100 | ||||||||||||||||
34 | Overall check | 0,25 hrs | 4/9/26 14:45 | 4/9/26 15:00 | 100 | ||||||||||||||||
35 | F6P-FV2414A : ACTUATOR FLOW CONTROL DAMPER | Restroke | 0,08 days | 4/9/26 14:45 | 4/9/26 16:45 | ||||||||||||||||
36 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/9/26 14:45 | 4/9/26 15:00 | 100 | ||||||||||||||||
37 | Overall visual check | 0,25 hrs | 4/9/26 15:00 | 4/9/26 15:15 | 100 | ||||||||||||||||
38 | Restroke Control Valve langsung dari DCS dan catat opening feedback CV di DCS dan di lapangan sebelum dan sesudah perbaikan. | 0,75 hrs | 4/9/26 15:15 | 4/9/26 16:00 | 100 | ||||||||||||||||
39 | Check dan service accessoris control valve. | 0,25 hrs | 4/9/26 16:00 | 4/9/26 16:15 | 100 | ||||||||||||||||
40 | Check fungsi ketika sinyal fail--> Open atau Close. | 0,25 hrs | 4/9/26 16:15 | 4/9/26 16:30 | 100 | ||||||||||||||||
41 | Overall check | 0,25 hrs | 4/9/26 16:30 | 4/9/26 16:45 | 100 | ||||||||||||||||
42 | F6P-FV2414B : ACTUATOR CONTROL DAMPER AIR INLET MILL B | Restroke | 0,15 days | 4/9/26 16:30 | 4/9/26 20:00 | ||||||||||||||||
43 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/9/26 16:30 | 4/9/26 16:45 | 100 | ||||||||||||||||
44 | Overall visual check | 0,25 hrs | 4/9/26 16:45 | 4/9/26 17:00 | 100 | ||||||||||||||||
45 | Restroke Control Valve langsung dari DCS dan catat opening feedback CV di DCS dan di lapangan sebelum dan sesudah perbaikan. | 0,75 hrs | 4/9/26 17:00 | 4/9/26 19:15 | 100 | ||||||||||||||||
46 | Check dan service accessoris control valve. | 0,25 hrs | 4/9/26 19:15 | 4/9/26 19:30 | 100 | ||||||||||||||||
47 | Check fungsi ketika sinyal fail--> Open atau Close. | 0,25 hrs | 4/9/26 19:30 | 4/9/26 19:45 | 100 | ||||||||||||||||
48 | Overall check | 0,25 hrs | 4/9/26 19:45 | 4/9/26 20:00 | 100 | ||||||||||||||||
49 | F6P-XV2416A : ACTUATOR COAL PRIMARY HOT CONTROL DAMPER | Restroke | 0,08 days | 4/10/26 7:30 | 4/10/26 9:30 | ||||||||||||||||
50 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/10/26 7:30 | 4/10/26 7:45 | 100 | ||||||||||||||||
51 | Overall visual check | 0,25 hrs | 4/10/26 7:45 | 4/10/26 8:00 | 100 | ||||||||||||||||
52 | Restroke Control Valve langsung dari DCS dan catat opening feedback CV di DCS dan di lapangan sebelum dan sesudah perbaikan. | 0,75 hrs | 4/10/26 8:00 | 4/10/26 8:45 | 100 | ||||||||||||||||
53 | Check dan service accessoris control valve. | 0,25 hrs | 4/10/26 8:45 | 4/10/26 9:00 | 100 | ||||||||||||||||
54 | Check fungsi ketika sinyal fail--> Open atau Close. | 0,25 hrs | 4/10/26 9:00 | 4/10/26 9:15 | 100 | ||||||||||||||||
55 | Overall check | 0,25 hrs | 4/10/26 9:15 | 4/10/26 9:30 | 100 | ||||||||||||||||
56 | F6P-XV2416B : ACTUATOR DAMPER GAH PRIMARY HOT MILL B | Restroke | 0,08 days | 4/10/26 9:15 | 4/10/26 11:15 | ||||||||||||||||
57 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/10/26 9:15 | 4/10/26 9:30 | 100 | ||||||||||||||||
58 | Overall visual check | 0,25 hrs | 4/10/26 9:30 | 4/10/26 9:45 | 100 | ||||||||||||||||
59 | Restroke Control Valve langsung dari DCS dan catat opening feedback CV di DCS dan di lapangan sebelum dan sesudah perbaikan. | 0,75 hrs | 4/10/26 9:45 | 4/10/26 10:30 | 100 | ||||||||||||||||
60 | Check dan service accessoris control valve. | 0,25 hrs | 4/10/26 10:30 | 4/10/26 10:45 | 100 | ||||||||||||||||
61 | Check fungsi ketika sinyal fail--> Open atau Close. | 0,25 hrs | 4/10/26 10:45 | 4/10/26 11:00 | 100 | ||||||||||||||||
62 | Overall check | 0,25 hrs | 4/10/26 11:00 | 4/10/26 11:15 | 100 | ||||||||||||||||
63 | F6P-XV2417A : ACTUATOR COAL PRIMARY HOT CONTROL DAMPER | Restroke | 0,17 days | 4/10/26 10:45 | 4/10/26 14:45 | ||||||||||||||||
64 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/10/26 10:45 | 4/10/26 11:00 | 100 | ||||||||||||||||
65 | Overall visual check | 0,25 hrs | 4/10/26 11:00 | 4/10/26 11:15 | 100 | ||||||||||||||||
66 | Restroke Control Valve langsung dari DCS dan catat opening feedback CV di DCS dan di lapangan sebelum dan sesudah perbaikan. | 0,75 hrs | 4/10/26 11:15 | 4/10/26 14:00 | 100 | ||||||||||||||||
67 | Check dan service accessoris control valve. | 0,25 hrs | 4/10/26 14:00 | 4/10/26 14:15 | 100 | ||||||||||||||||
68 | Check fungsi ketika sinyal fail--> Open atau Close. | 0,25 hrs | 4/10/26 14:15 | 4/10/26 14:30 | 100 | ||||||||||||||||
69 | Overall check | 0,25 hrs | 4/10/26 14:30 | 4/10/26 14:45 | 100 | ||||||||||||||||
70 | F6P-XV2417B : ACTUATOR DAMPER PAF PRIMARY HOT MILL B | Restroke | 0,08 days | 4/10/26 14:15 | 4/10/26 16:15 | ||||||||||||||||
71 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/10/26 14:15 | 4/10/26 14:30 | 100 | ||||||||||||||||
72 | Overall visual check | 0,25 hrs | 4/10/26 14:30 | 4/10/26 14:45 | 100 | ||||||||||||||||
73 | Restroke Control Valve langsung dari DCS dan catat opening feedback CV di DCS dan di lapangan sebelum dan sesudah perbaikan. | 0,75 hrs | 4/10/26 14:45 | 4/10/26 15:30 | 100 | ||||||||||||||||
74 | Check dan service accessoris control valve. | 0,25 hrs | 4/10/26 15:30 | 4/10/26 15:45 | 100 | ||||||||||||||||
75 | Check fungsi ketika sinyal fail--> Open atau Close. | 0,25 hrs | 4/10/26 15:45 | 4/10/26 16:00 | 100 | ||||||||||||||||
76 | Overall check | 0,25 hrs | 4/10/26 16:00 | 4/10/26 16:15 | 100 | ||||||||||||||||
77 | F6P-XV2433 : ACTUATOR SHUTOFF DAMPER ECONOMIZER | Restroke | 0,15 days | 4/10/26 16:00 | 4/10/26 19:30 | ||||||||||||||||
78 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/10/26 16:00 | 4/10/26 16:15 | 100 | ||||||||||||||||
79 | Overall visual check | 0,25 hrs | 4/10/26 16:15 | 4/10/26 16:30 | 100 | ||||||||||||||||
80 | Restroke Control Valve langsung dari DCS dan catat opening feedback CV di DCS dan di lapangan sebelum dan sesudah perbaikan. | 0,75 hrs | 4/10/26 16:30 | 4/10/26 17:15 | 100 | ||||||||||||||||
81 | Check dan service accessoris control valve. | 0,25 hrs | 4/10/26 17:15 | 4/10/26 17:30 | 100 | ||||||||||||||||
82 | Check fungsi ketika sinyal fail--> Open atau Close. | 0,25 hrs | 4/10/26 19:00 | 4/10/26 19:15 | 100 | ||||||||||||||||
83 | Overall check | 0,25 hrs | 4/10/26 19:15 | 4/10/26 19:30 | 100 | ||||||||||||||||
84 | F6P-FV2403B : ACTUATOR CONTROL DAMPER OVERFIRE | Restroke | 0,08 days | 4/10/26 19:15 | 4/10/26 21:15 | 100 | |||||||||||||||
85 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/10/26 19:15 | 4/10/26 19:30 | 100 | ||||||||||||||||
86 | Overall visual check | 0,25 hrs | 4/10/26 19:30 | 4/10/26 19:45 | 100 | ||||||||||||||||
87 | Restroke Control Valve langsung dari DCS dan catat opening feedback CV di DCS dan di lapangan sebelum dan sesudah perbaikan. | 0,75 hrs | 4/10/26 19:45 | 4/10/26 20:30 | 100 | ||||||||||||||||
88 | Check dan service accessoris control valve. | 0,25 hrs | 4/10/26 20:30 | 4/10/26 20:45 | 100 | ||||||||||||||||
89 | Check fungsi ketika sinyal fail--> Open atau Close. | 0,25 hrs | 4/10/26 20:45 | 4/10/26 21:00 | 100 | ||||||||||||||||
90 | Overall check | 0,25 hrs | 4/10/26 21:00 | 4/10/26 21:15 | 100 | ||||||||||||||||
91 | F6P-LV2101 : CONTROL VALVE BFW TO STEAM DRUM | Restroke | 0,08 days | 4/11/26 7:30 | 4/11/26 9:30 | ||||||||||||||||
92 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/11/26 7:30 | 4/11/26 7:45 | 100 | ||||||||||||||||
93 | Overall visual check | 0,25 hrs | 4/11/26 7:45 | 4/11/26 8:00 | 100 | ||||||||||||||||
94 | Restroke Control Valve langsung dari DCS dan catat opening feedback CV di DCS dan di lapangan sebelum dan sesudah perbaikan. | 0,75 hrs | 4/11/26 8:00 | 4/11/26 8:45 | 100 | ||||||||||||||||
95 | Check dan service accessoris control valve. | 0,25 hrs | 4/11/26 8:45 | 4/11/26 9:00 | 100 | ||||||||||||||||
96 | Check fungsi ketika sinyal fail--> Open atau Close. | 0,25 hrs | 4/11/26 9:00 | 4/11/26 9:15 | 100 | ||||||||||||||||
97 | Overall check | 0,25 hrs | 4/11/26 9:15 | 4/11/26 9:30 | 100 | ||||||||||||||||
98 | F6P-LV2102 : CONTROL VALVE BYPASS BFW TO STEAM DRUM | Restroke, tuning saat 3 element | 0,08 days | 4/11/26 9:15 | 4/11/26 11:15 | ||||||||||||||||
99 | Persiapan/ Pengamanan Proses. | 0,25 hrs | 4/11/26 9:15 | 4/11/26 9:30 | 100 | ||||||||||||||||
100 | Overall visual check | 0,25 hrs | 4/11/26 9:30 | 4/11/26 9:45 | 100 |