NO.
JENIS PEKERJAAN
8
URAIAN PEKERJAAN VOLUME REALISASI VOLUME SAT BOBOTPROGRESS PEKERJAAN KET85.89%
9
MATERIALUPAHs/d MINGGU LALUMINGGU INIs/d MINGGU INI100.00%
10
VOLUMEPROGRES BOBOTVOLUMEPROGRES BOBOTVOLUMEPROGRES BOBOT
11
I
PEKERJAAN PERSIAPAN
12
1
Pembersihan
1.00 - 881,250.00 1.00 ls0.05% 1.00 100%0.05% - 0% 1.00 100%0.05%
13
2
Mobilisasi tenaga & alat
1.00 - 1,762,500.00 1.00 ls0.10% 0.90 90%0.09% - 0% 0.90 90%0.09%
14
3
Mess pekerja ( di sediakan owner )
1.00 by owner by owner 1.00 ls0.00% - 0.00% - -
15
4
Air kerja & listrik kerja ( di sediakan owner )
1.00 by owner by owner 1.00 ls0.00% - 0.00% - -
16
5Pengukuran 1.00 - 587,500.00 1.00 ls0.03% 1.00 100%0.03% - 0% 1.00 100%0.03%
17
6
pekerjaan bongkaran existing
248.30 - 13,712,334.37 248.30 m20.76% 248.30 100%0.76% - 0% 248.30 100%0.76%
18
Sub Jumlah - 16,943,584.37 0.00% - 0.00% - -
19
0.00% - 0.00% - -
20
II
PEKERJAAN KONSTRUKSI BARU - 2 LANTAI
0.00% - 0.00% - -
21
A
PEKERJAAN BONGKARAN
0.00% - 0.00% - -
22
1
Bongkar bangunan existing + buang
1.00 - 11,112,650.63 1.00 ls0.62% 0.80 80%0.50% - 0% 0.80 80%0.50%
23
0.00% - 0.00% - -
24
Sub Jumlah - 11,112,650.63 0.00% - 0.00% - -
25
0.00% - 0.00% - -
26
B
PEKERJAAN TANAH
0.00% - 0.00% - -
27
1
Galian pondasi setempat + buang
37.57 - 2,895,895.99 37.57 m30.16% 37.57 100%0.16% - 0% 37.57 100%0.16%
28
2
Galian pondasi stroust Ø25-6mtr
- - - - m'0.00% - 100%0.00% - 0% - 100%0.00%
29
3
Galian pondasi bore pile Ø30-15mtr
157.00 - 20,504,200.00 157.00 m'1.14% 157.00 100%1.14% - 0% 157.00 100%1.14%
30
4
Urugan pasir di bawah pondasi pilecap
1.58 346,662.33 49,116.68 1.58 m30.02% 1.58 100%0.02% - 0% 1.58 100%0.02%
31
5
Sirtu urg + pemadatan
11.68 2,366,781.94 404,218.91 11.68 m30.15% 11.68 100%0.15% - 0% 11.68 100%0.15%
32
6
Urug tanah kembali
6.38 - 188,950.91 6.38 m30.01% 6.38 100%0.01% - 0% 6.38 100%0.01%
33
0.00% - 0.00% - 0% - 0.00%
34
Sub Jumlah 2,713,444.27 24,042,382.49 0.00% - 0.00% - 0% - 0.00%
35
0.00% - 0.00% - 0% - 0.00%
36
C
PEKERJAAN BETON
0.00% - 0.00% - -
37
1
Lantai kerja
1.63 1,018,831.90 406,244.51 1.63 m30.08% 1.63 100%0.08% - 0% 1.63 100%0.08%
38
2
Pondasi stroust Ø25-6mtr
- - - - m30.00% - 100%0.00% - 0% - 100%0.00%
39
3
Pondasi stroust Ø30-15mtr
11.09 24,387,483.74 13,180,408.93 11.09 m32.09% 11.09 100%2.09% - 0% 11.09 100%2.09%
40
4Pile cap 4.34 14,456,625.66 4,818,875.22 4.34 m31.07% 4.34 100%1.07% - 0% 4.34 100%1.07%
41
5Sloof 2.74 11,065,883.32 3,688,627.77 2.74 m30.82% 2.74 100%0.82% - 0% 2.74 100%0.82%
42
6Pedestal 0.61 2,414,038.08 804,679.36 0.61 m30.18% 0.61 100%0.18% - 0% 0.61 100%0.18%
43
7
Pekerjaan kolom
1.02 4,003,674.27 1,334,558.09 1.02 m30.30% 1.02 100%0.30% - 0% 1.02 100%0.30%
44
8
Pekerjaan balok
0.83 3,302,982.58 1,100,994.20 0.83 m30.25% 0.83 100%0.25% - 0% 0.83 100%0.25%
45
9
Dak beton atap
3.77 13,515,282.36 4,505,094.12 3.77 m31.00% 3.77 100%1.00% - 0% 3.77 100%1.00%
46
10
Tangga beton
4.01 15,989,009.84 5,329,669.96 4.01 m31.19% 4.01 100%1.19% - 0% 4.01 100%1.19%
47
0.00% - 0.00% - 0% - 0%0.00%
48
Sub Jumlah 90,153,811.75 35,169,152.16 0.00% - 0.00% - 0% - 0%0.00%
49
0.00% - 0.00% - 0% - 0%0.00%
50
D
PEKERJAAN BAJA
0.00% - 0.00% - 0% - 0%0.00%
51
1HB 200 5,480.89 87,369,169.02 28,160,728.36 5,480.89 kg6.44% 5,480.89 100%6.44% - 0% 5,480.89 100%6.44%
52
2WF250 750.52 11,963,825.48 3,856,166.23 750.52 kg0.88% 750.52 100%0.88% - 0% 750.52 100%0.88%
53
3WF200 3,193.51 50,906,743.95 16,408,202.16 3,193.51 kg3.75% 3,193.51 100%3.75% - 0% 3,193.51 100%3.75%
54
- balok atap - WF 200
466.72 7,439,843.50 2,398,001.66 466.72 kg0.55% 466.72 100%0.55% - 0% 466.72 100%0.55%
55
- joint T 47.68 760,040.70 244,975.43 47.68 kg0.06% 47.68 100%0.06% - 0% 47.68 100%0.06%
56
- voute 47.68 760,040.70 244,975.43 47.68 kg0.06% 47.68 100%0.06% - 0% 47.68 100%0.06%
57
- balok atap kudakuda - WF 200
506.02 8,066,293.25 2,599,918.20 506.02 kg0.59% 506.02 100%0.59% - 0% 506.02 100%0.59%
58
- joint T 12.16 193,835.88 62,476.96 12.16 kg0.01% 12.16 100%0.01% - 0% 12.16 100%0.01%
59
- WF 200 untuk balkon
109.85 1,751,077.92 564,405.39 109.85 kg0.13% 109.85 100%0.13% - 0% 109.85 100%0.13%
60
- WF 200 untuk tambahan area tangga
117.32 1,870,083.22 602,763.04 117.32 kg0.14% 117.32 100%0.14% - 0% 117.32 100%0.14%
61
3.1
Pekerjaan Gording CNP 150x50x20 x2,3
382.31 6,094,209.31 1,964,278.42 382.31 kg0.45% 363.19 95%0.43% - 0% 363.19 95%0.43%
62
Pekerjaan Zeltech
75.79 6,745,310.00 1,591,590.00 75.79 m20.46% 72.00 95%0.44% - 0% 72.00 95%0.44%
63
Rangka atap baja ringan/galvalum
75.79 4,812,665.00 3,630,341.00 75.79 m20.47% 72.00 95%0.45% - 0% 72.00 95%0.45%
64
pekerjaan Listplank (conwood)
35.80 1,682,600.00 1,299,540.00 35.80 m10.00% - 0.00% - 0% - 0%0.00%
65
pasang triplek HMR
79.79 - 3,750,130.00 79.79 m20.21% 75.80 95%0.20% - 0% 75.80 95%0.20%
66
pek. Pasang genteng
79.79 - 3,016,062.00 79.79 m20.17% 75.80 95%0.16% - 0% 75.80 95%0.16%
67
pek. Bubungan
24.80 - 1,185,440.00 24.80 m10.07% 19.84 80%0.05% - 0% 19.84 80%0.05%
68
pek. Partisi double GRC Lt.3
4.95 314,325.00 237,105.00 4.95 m20.03% 3.47 70%0.02% - 0% 3.47 70%0.02%
69
finish cat lispank
10.74 306,653.85 134,416.60 10.74 m20.02% 8.59 80%0.02% - 0% 8.59 80%0.02%
70
Pekerjaan penambahan rangka + penutup lispang
35.80 1,682,600.00 1,299,540.00 71.60 m10.17% 68.02 95%0.16% - 0% 68.02 95%0.16%
71
4Plat joint 1.00 15,023,976.46 4,842,509.68 1.00 ls1.11% 1.00 100%1.11% - 0% 1.00 100%1.11%
72
5
Angkur baut & Mur baut
1.00 7,511,988.23 2,421,254.84 1.00 ls0.55% 1.00 100%0.55% - 0% 1.00 100%0.55%
73
6
Railling (jilumesh+ramgka hollow+plat strip+cat)
- - - - m'0.00% - 0.00% - 0% - 0%0.00%
74
7
Hand railling (kayu+rangka besi)
33.60 26,440,156.09 2,644,015.61 33.60 m'1.62% 33.60 100%1.62% - 0% 33.60 100%1.62%
75
- Railling balkon (ramgka hollow 40x40 & hollow 20x20 + cat powder coatting black fin )
5.50 1,357,125.00 581,625.00 5.50 0.11% 5.50 100%0.11% - 0% 5.50 100%0.11%
76
7Grouting 0.05 639,576.00 95,175.00 0.05 m30.04% 0.05 100%0.04% - 0% 0.05 100%0.04%
77
8
Kanopi lantai 1 (rangka besi + siku 40 + polycarbonate)
1.00 22,569,051.25 5,618,443.82 1.00 unit1.57% 0.60 60%0.94% - 0% 0.60 60%0.94%
78
9
Kanopi lantai 2 (rangka besi + siku 40 + polycarbonate)
1.00 28,211,314.06 7,023,054.77 1.00 unit1.96% 0.60 60%1.18% - 0% 0.60 60%1.18%
79
0.00% -
80
Sub Jumlah 294,472,503.90 96,477,134.59 0.00% -
81
0.00% -
82
E
PEKERJAAN PASANGAN
0.00% -
83
1
Pas. Pondasi rollag
18.82 1,866,346.23 802,663.66 18.82 m'0.15% 18.82 100%0.15% - 0% 18.82 100%0.15%
84
2
Pas. Pondasi batu kali
5.49 3,703,804.68 642,712.98 5.49 m30.24% 5.49 100%0.24% - 0% 5.49 100%0.24%
85
3
Pas. Plat lantai Ciiton
54.00 41,589,431.91 9,027,502.55 54.00 m22.82% 54.00 100%2.82% - 0% 54.00 100%2.82%
86
4
Pas. Dinding bata merah
160.01 13,798,397.92 5,934,307.58 160.01 m21.10% 160.01 100%1.10% - 0% 160.01 100%1.10%
87
5
Pas. Dinding bata ringan (tutup plester)
- - - - m20.00% - 0.00% - 0% - 0%0.00%
88
5
Pas. Plesteran
375.96 6,184,599.58 13,943,179.74 375.96 m21.12% 375.96 100%1.12% - 0% 375.96 100%1.12%
89
6Pas. Aci 408.57 4,500,664.92 9,310,975.59 408.57 m20.77% 408.57 100%0.77% - 0% 408.57 100%0.77%
90
7
Pas. Benangan
108.20 197,059.25 1,558,420.83 108.20 m'0.10% 108.20 100%0.10% - 0% 108.20 100%0.10%
91
- benangan opening kusen aluminium
109.20 1,202,906.25 2,488,572.45 109.20 m10.21% 109.20 100%0.21% - 0% 109.20 100%0.21%
92
8
Pas. Lantai tegel + poles
35.19 by owner 2,672,320.49 35.19 m20.15% 31.67 90%0.13% - 0% 31.67 90%0.13%
93
- Poles lantai tegel
35.19 - 971,752.91 35.19 m20.05% - 0%0.00% - 0% - 0%0.00%
94
8.a
Pas. Lantai keramik
84.67 by owner 6,429,363.53 84.67 m20.36% 67.74 80%0.29% - 0% 67.74 80%0.29%
95
9
Pas. Lantai keramik 40x40
- by owner - - m20.00% - 0.00% - 0% - 0%0.00%
96
10
Waterproofing + screed
27.00 - 7,208,919.34 27.00 m20.40% 27.00 100%0.40% - 0% 27.00 100%0.40%
97
Pasang dinding motif bata expose
182.75 by owner 27,412,800.00 182.75 m21.53% 173.61 95%1.45% - 0% 173.61 95%1.45%
98
Pasangan siku pengaman pada sudut batu tempel
98.27 m'
99
Pasang roster
18.09 by owner 1,373,652.84 18.09 m20.08% 14.47 80%0.06% - 0% 14.47 80%0.06%
100
Pasang roster
4.24 m2