ActivityOwnerSupporting DocumentWeek 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Week 10Week 11Week 12
3
Month 1Month 2Month 3Post Go-live & Floor-Walking support
29
1. Planning EUT Strategy
30
Kick off briefing meeting with OCS Training Coordinator (virtual or face-to-face) - and deliver EUT Package as backgroundTJ/Center
31
Training Kick-off : Explaining Strategy and services- meeting with Highpoint TJ/Center/HP
32
1.1. Training Plan
33
Review Course Syllabus (and existing developed materials)TJ/CenterSummary Course Syllabus
34
Appoint Center Teams (Trainers/Seminar facilitators, Logistics, ICT Helpdesk, Floor-Walkers, Communications)Center
35
Training Plan document started (internal CGIAR purposes)Center/TJTraining Plan Document template
36
Complete the SOW - confirm Train the Trainer requirements Center PMSOW - Unit4 doc
37
Complete the TRD for Highpoint Center/HPTRD.DOC
38
Highpoint to prepare an update Course Syllabus for the CenterHighpointCourse Syllabus - center
39
Agree Course syllabus (delivery methodology) / new courses required? and evaluate if the course is needed in a different interface than the default (Self Service/ Smart Client)TJ/HP/Center
40
Exercise to map # of Users to Courses / locations (estimate) CenterRole to course mapping.xls
41
Training Plan document finalizedCenter / TJTraining Plan template
42
1.2 Course Schedule / User Mapping
43
Confirm delegate list for each course and Classroom Course ScheduleHP/Center/TJ
44
Highpoint to quote costs for TTT/ Localization / delivery and confirm availabilityHighpointPricing Schedule.doc
45
Agree and confirm requirements for localization from HP Trainers for logistics: book flights/ visas/ accommodation (6-weeks prior to course delivery) Center
46
Highpoint to quote ticket(s) for approval by DSWAINHighpoint / TJ
47
Communicate with classroom-based delegates about EUT (6 weeks prior to course delivery)Center Training Coord.
48
Training DB - confirm location and other details including the date it will be made available to Highpoint

Center Training Coord.Training database checklist.xls
49
Confirm process for restoring training database to its original baseline and how we create a new baseline once we have loaded the data required.Center/OCS/Highpoint
50
2. Localization / Training DB
51
Prepare list of SystemBuilders/ Experts to be contacted for localization (name, email, skype, phone)Center Training Coord./ TJ
52
Pre-Localization Review Center Functional leads
53
UAT COMPLETE/ SIGNED-OFF - Input: LDD sent to Highpoint / WorkflowsHP/CenterLDD shared with HP
54
Training DB: Make training database available to Highpoint: Copy of Center's UAT DB to EUT Environment (Collate Data requirements/Load Data) following UAT sign-offHP/Center/OSU
55
Training DB: : Review training DB and apply initial training dataHighpoint
56
Localization: Load Data/ Amend material as required with input from Center system builders/ expertsHP/CenterCGIAR Control Document.xls
57
Localization: Functional lead-review -> Sign-off localization documents.
HighpointCGIAR Control Document.xls
58
Training DB: All materials finished ready for QC. All additional files (Supplier invoices, purchase invoices etc loaded onto training environment and accessable to delegates)Highpoint /Center
59
Quality Control - All courses (duration 2 days) / materials avaiable for upload to workspacesHighpoint
60
Training Workspace (LMS or Intranet)
61
Ensure all center users login to IRRI.ORG / CGXchange (for LMS)Center
62
Identify LMS Administrators / Support for Centers (Helpdesk)Center
63
Structure the Learning Programs / Map Users to Learning Programs (mainly for LMS)Center/TJ/HP
64
Setup course content and Learning Programs on LMS/ IntranetHP / TJ/ Center
65
Upload staff list on the LMSHP
66
LMS virtual Training to Center Administrators / Pilot LMSHP / TJ/ Center
67
Communicate:Pre-LMS / Intranet rollout for staff to take the self-study/ e-Learning pre-requisite courses prior to classroom-based trainingCenter/HP
68
3. Training Delivery
69
Center to fill-out the Training Preparations check-listCenterTraining Preparation Checklist
70
Center Trainers to practice / test Courses they will deliverCenter Trainersusing the course Lesson Plan
71
Printing/Binding of materials for classroom-basedCenter
72
Check . Test access to Training DB from Training Room/PCsCenter
73
Check if all necessary support documents to the Training EnvironmentHP / Center
74
Training Delivery -> Train the Trainer (1-day) HP/Center
75
Training Delivery -> Classroom-based/Seminar Training starts (2-3 weeks depending on Center size / depending on whether regions are being rolled out at the same time too)HP/Center
76
Training Delivery - reset the database when requiredHP/Center
77
Training Delivery -> communicate with staff to login to LMS/Intranet to invite them to access the self-paced e-Learning course (ALL staff) - deliver seminars to learn how to access LMS / Intranet resourcesCenter
78
Delegates to fill out the Course EvaluationsTC / End-Users
79
Trainers to follow-up with questions/concerns from usersCenter
80
Go Live! OCS Support in placeÖ
81
4. Floor-Walking (post Go-live)
82
Providing support to end-users post training (on their desks if required) / continue user training Center Helpdesk / Floor-walkers
83
Notes: required steps should be repeated for roll-outs in other Center country offices/ regions.