1 | FDP Form 7-20% Component of the IRA Utilization | |||||||||||||||||||||
2 | 20% COMPONENT OF THE IRA UTILIZATION | |||||||||||||||||||||
3 | For the Fourth Quarter FY, 2020 | |||||||||||||||||||||
4 | ||||||||||||||||||||||
5 | City : ANTIPOLO | |||||||||||||||||||||
6 | Program/Project | Location | Total Cost | Date Started | Target Completion Date | Project Status | No. of Extentions, if any | Remarks | ||||||||||||||
7 | % of Completion | Total Cost Incurred to Date | ||||||||||||||||||||
8 | SOCIAL DEVELOPMENT | |||||||||||||||||||||
9 | Purchase, Construction & Improvement of Government Facilities-Health | |||||||||||||||||||||
10 | Payment for the "Additional Repair & Rehabilitation of City Health Office at M.Santos St. Brgy.San Roque Antipolo City" | Barangay San Roque | 4,480,000.00 | 21-Nov-19 | 28-Aug-20 | 100% | 4,480,000.00 | paid | ||||||||||||||
11 | Payment for the "Repair/Rehabilitation/Improvement at Brgy.San Isidro and Brgy.San Jose Antipolo City (2019-Package 65)" | Barangay San Jose | 493,191.60 | 7-Nov-19 | 2-Mar-20 | 100% | 493,191.60 | paid | ||||||||||||||
12 | Various Improvement of Rizal Provincial Hospital System – Annex I at NHA Ave., Brgy. Dela Paz, Antipolo City | Barangay Dela Paz | 2,286,500.00 | 21-Nov-19 | 19-May-20 | 35% | 800,275.00 | Suspended due to COVID | ||||||||||||||
13 | Sub-Total | 7,259,691.60 | 5,773,466.60 | |||||||||||||||||||
14 | Development Project- Health Services Others | |||||||||||||||||||||
15 | Purchase of Folding Bed and Beddings for the use at the isolation facilities in Antipolo City Purchase Order No. 20200862 dated August 28,2020 | City wide - Isolation Facilities | 1,645,000.00 | 1-Aug-20 | 31-Aug-20 | 100% | 1,645,000.00 | paid | ||||||||||||||
16 | Purchase of medical equipment | City wide - ACHS | 355,000.00 | 1-Mar-20 | 31-Mar-20 | 100% | 355,000.00 | paid | ||||||||||||||
17 | Purchase of Hospital Medical Equipment with PR#2001021 dated January 3,2020 | City wide - ACHS | 44,300.00 | 1-Jan-20 | 31-Jan-20 | 100% | 44,300.00 | paid | ||||||||||||||
18 | Purchase of medical equipment, instruments and furniture for RPHS-Antipolo Annex I and ACHS Annex IV mambugan | City wide - ACHS | 121,250.00 | 1-Mar-20 | 31-Mar-20 | 100% | 121,250.00 | paid | ||||||||||||||
19 | Purchase of medical equipment, instruments and furniture for RPHS-Antipolo Annex I & ACHS-Annex IV Mambugan | City wide - ACHS | 461,800.00 | 1-Mar-20 | 31-Mar-20 | 100% | 461,800.00 | paid | ||||||||||||||
20 | Purchase of Oxygen Regulator with PO#20200997 dated October 2,2020 | City wide - ACHS | 64,000.00 | 1-Oct-20 | 31-Oct-20 | 100% | 64,000.00 | paid | ||||||||||||||
21 | Payment For The Purchase Of Tens Machine & Accessories Packheater Table | City wide - ACHS | 58,000.00 | 4-Aug-20 | 16-Oct-20 | 100% | 58,000.00 | payment in process | ||||||||||||||
22 | Sub-Total | 2,749,350.00 | 2,749,350.00 | |||||||||||||||||||
23 | Purchase, Construction and Improvement of Government Facilities-Housing and Community Development | |||||||||||||||||||||
24 | Improvement of Water System and Construction of 2" Diameter Casing Artesian Well at Brgy. San Roque and Brgy. San Jose, Antipolo City (2020 – Package 23) b. Construction of 2" Diameter Casing Artesian Well at Tanza 1, Phase 4, Brgy. San Jose, Antipolo City | Barangay San Jose | 392,224.02 | 7-Sep-20 | 15-Jan-21 | 100% | 392,224.02 | payment in process | ||||||||||||||
25 | Repair/Improvement of Sitio Hall and Construction of Drainage Canal at Brgy. San Jose and Brgy. Cupang, Antipolo City (2020 – Package 25) a. Repair/Improvement of Sitio Hall at Sitio San Joseph, Brgy. San Jose, Antipolo City | Barangay San Jose | 670,362.22 | 7-Sep-20 | 15-Jan-21 | 100% | 670,362.22 | payment in process | ||||||||||||||
26 | Repair/ Improvement of 2” Diameter Casing Artesian Well and Water Distribution System at Brgy. Calawis and Brgy. San Isidro, Antipolo City (Package 40 – 2020) b. Improvement of 2” Diameter Casing Artesian Well at Purok 3, Brgy. Calawis, Antipolo City | Barangay Calawis | 222,042.96 | 10-Dec-20 | 9-May-21 | 0% | - | To start | ||||||||||||||
27 | Sub-Total | 1,284,629.20 | 1,062,586.24 | |||||||||||||||||||
28 | Total - Social Development | 11,293,670.80 | 9,585,402.84 | |||||||||||||||||||
29 | ||||||||||||||||||||||
30 | ECONOMIC DEVELOPMENT | |||||||||||||||||||||
31 | Purchase, Construction and Improvement of Government Facilities - Economic Services | |||||||||||||||||||||
32 | To record first & final payment for the "Concreting of Road w/ Riprap in front of Covered Court Creek at Sitio PCUP-RPG Ville Brgy.San Jose Antipolo City" | Barangay San Jose | 1,185,383.25 | 11-May-20 | 18-Aug-20 | 100% | 1,185,383.25 | paid | ||||||||||||||
33 | Road Concreting Of Road Lot 1 (With Pin No. 177-01-012-023-041) At Josephina Subdivision, Brgy. Mambugan, Antipolo City | Barangay Mambugan | 1,217,327.69 | 4-May-20 | 3-Sep-20 | 100% | 1,217,327.69 | paid | ||||||||||||||
34 | Road Concreting Of Road Lot 3 (With Pin No. 177-01-012-023-029) At Josephina Subdivision, Brgy. Mambugan, Antipolo City | Barangay Mambugan | 233,506.75 | 4-May-20 | 3-Sep-20 | 100% | 233,506.75 | paid | ||||||||||||||
35 | Road Concreting Of Road Lot 4 (With Pin No. 177-01-012-023-019) At Josephina Subdivision, Brgy. Mambugan, Antipolo City | Barangay Mambugan | 375,425.56 | 4-May-20 | 3-Sep-20 | 100% | 375,425.56 | paid | ||||||||||||||
36 | Payment for the "Road Concreting of Road Lot 2 (with Pin No.177-01-012-023-036) at Josephina Subdivision Brgy.Mambugan" | Barangay Mambugan | 1,835,500.00 | 4-May-20 | 25-Aug-20 | 100% | 1,835,500.00 | paid | ||||||||||||||
37 | Payment for the "Construction of Stone Masonry Riverwall along the Creek Lower Buhanginan, Sitio Tagbac, Brgy. San Jose, Antipolo City" | Barangay San Jose | 965,726.69 | 4-May-20 | 8-Sep-20 | 100% | 965,726.69 | paid | ||||||||||||||
38 | Payment for the "Improvement of Road and Drainage at Knights of Columbus, Brgy. San Roque, Antipolo City | Barangay San Roque | 2,982,000.00 | 6-Nov-19 | 8-Jul-20 | 100% | 2,982,000.00 | paid | ||||||||||||||
39 | Payment for the "Concreting of Rosal St., at Bermuda Heights Subdivision, Brgy. San Luis, Antipolo City" | Barangay San Luis | 694,500.00 | 4-May-20 | 26-Aug-20 | 100% | 694,500.00 | paid | ||||||||||||||
40 | Payment for the "Improvement of Road with Drainage System at Sto. Niño Street, Milagros Estate Subdivision, Barangay Dalig" | Barangay Dalig | 2,486,500.01 | 28-Apr-20 | 22-Sep-20 | 100% | 2,486,500.01 | paid | ||||||||||||||
41 | Payment for the "Construction of Stone Masonry Riverwall (Portion) along Labahan Creek at Palemon Street Crestview Subdivision Brgy.Cupang Antipolo City" | Barangay Cupang | 2,295,800.00 | 1-Sep-20 | 3-Nov-20 | 100% | 2,295,800.00 | paid | ||||||||||||||
42 | Reblocking of Road (Portion) of Gumamela St. at Lornaville Subd., Brgy. San Roque, Antipolo City (2020-Package 10) | Barangay San Roque | 1,256,945.00 | 4-May-20 | 15-Sep-20 | 100% | 1,256,945.00 | paid | ||||||||||||||
43 | Payment for the "Rehabilitation of Drainage Canal and Road Concreting at Road Lot 1 Peace Viilage Phase-3 Brgy.San Luis Antipolo City" | Barangay San Luis | 2,582,200.00 | 11-May-20 | 8-Oct-20 | 100% | 2,582,200.00 | paid | ||||||||||||||
44 | Payment for the "Concreting of road 1 and Construction of Drainage Canal at Bayugo-Padi Heights Subdivision Brgy.San Luis Antipolo City"" | Barangay San Luis | 2,575,000.00 | 1-Sep-20 | 24-Nov-20 | 100% | 2,575,000.00 | paid | ||||||||||||||
45 | Payment for the Improvement/Concreting (Portion) of Road, Construction of Lined Canal Drainage (Boulders and Grouted Riprap Stone Protection at Calawis-Apis Road Site 3 Brgy.Calawis Antipolo City | Barangay Calawis | 4,976,700.00 | 6-Nov-19 | 22-Sep-20 | 100% | 4,976,700.00 | paid | ||||||||||||||
46 | Payment for the "Concreting of Road with Drainage System, Zapanta Compound M.L. Quezon Extension Brgy.San Roque Antipolo City " | Barangay San Roque | 7,488,000.00 | 7-Feb-20 | 8-Oct-20 | 100% | 7,488,000.00 | paid | ||||||||||||||
47 | Road Concreting (Portion) And Construction Of Riprap (Portion) At Raod Lot 8, Sanchez Realty Subd., Brgy. Cupang Antipolo City (2020 Package 5) | Barangay Cupang | 427,905.53 | 28-Apr-20 | 19-Oct-20 | 100% | 427,905.53 | payment in process | ||||||||||||||
48 | Concreting Of Road With Drainage System (PhaseII) At Zapanta Compound, M.L. Quezon Extension, Brgy. San Roque Antipolo City | Barangay San Roque | 1,987,500.00 | 28-Apr-20 | 15-Oct-20 | 100% | 1,987,500.00 | payment in process | ||||||||||||||
49 | Concreting (Portion) Of Road And Construction Of Drainage System At Road Lot 6, Sitio Taguete, Spring Valley 1 Subd. Zone 6, Cupang, Antipolo City | Barangay Cupang | 1,352,840.00 | 6-Mar-19 | 3-Aug-19 | 100% | 1,352,840.00 | payment in process | ||||||||||||||
50 | Improvement of Martinez Street, Brgy. San Roque, Antipolo City | Barangay San Roque | 2,527,800.00 | 4-May-20 | 1-Sep-20 | 100% | 2,527,800.00 | payment in process | ||||||||||||||
51 | Concreting of Ilang-Ilang St. at Bermuda Heights Subd., Brgy. San Luis, Antipolo City | Barangay San Luis | 1,309,733.86 | 1-Sep-20 | 30-Dec-20 | 100% | 1,309,733.86 | payment in process | ||||||||||||||
52 | Construction of Drainage System Phase III at Maguey Road, Barangay San Isidro, Antipolo City | Barangay San Isidro | 4,179,416.94 | 1-Sep-20 | 29-Jan-21 | 80% | 3,343,533.55 | construction in progress | ||||||||||||||
53 | Construction of Drainage System Phase IV at Maguey Road, Barangay San Luis, Antipolo City | Barangay San Luis | 4,179,996.44 | 1-Sep-20 | 28-Jan-21 | 100% | 4,179,996.44 | payment in process | ||||||||||||||
54 | Improvement of Drainage Canal at Dela Paz St. (Portion), Brgy. Dela Paz, Antipolo City | Barangay Dela Paz | 3,003,783.96 | 1-Sep-20 | 30-Dec-20 | 100% | 3,003,783.96 | payment in process | ||||||||||||||
55 | Improvement of Drainage Canal and Concreting of Road at Portion of Napoleon Street & Louis Street, Edward VIII Street, Kingsville Subdivision, Barangay Mayamot & Barangay Mambugan, Antipolo City | Barangay Mayamot and Barangay Mambugan | 6,985,000.50 | 19-Oct-20 | 18-Mar-21 | 15% | 1,047,750.08 | Suspended due to the concern of Home Owners Assoc. | ||||||||||||||
56 | Repair of Dilapidated Stand Alone Comfort Room and Improvement/ Construction of Roads with Drainage System at Brgy. San Jose, Antipolo City (2020 – Package 29) b.Improvement/Construction of Roads with Drainage System for Alley-4 (Portion) at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City | Barangay San Jose | 281,540.00 | 22-Oct-20 | 21-Mar-21 | 100% | 281,540.00 | payment in process | ||||||||||||||
57 | Repair of Dilapidated Stand Alone Comfort Room and Improvement/ Construction of Roads with Drainage System at Brgy. San Jose, Antipolo City (2020 – Package 29) c. Improvement/Construction of Roads with Drainage System for Pathway-2 at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City | Barangay San Jose | 137,540.00 | 22-Oct-20 | 21-Mar-21 | 100% | 137,540.00 | payment in process | ||||||||||||||
58 | Rehabilitation and Improvement of Drainage Canal and Road at M. Santos Extension, Barangay San Jose, Antipolo City | Barangay San Jose | 4,985,127.05 | 19-Oct-20 | 18-Mar-21 | 60% | 2,991,076.23 | construction in progress | ||||||||||||||
59 | Imprvt./ Concreting of Olympus St., at La Montana Estates, Brgy. Sta. Cruz, Antipolo City | Barangay Sta. Cruz | 2,466,500.00 | 10-Dec-20 | 9-Apr-21 | 30% | 739,950.00 | construction in progress | ||||||||||||||
60 | Various Improvement/ Construction of Roads with Drainage System at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City (Package 36 – 2020) a. Improvement/ Construction of Roads with Drainage System for Alley-3 (Portion) at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City | Barangay San Jose | 379,986.28 | 10-Dec-20 | 9-May-21 | 20% | 75,997.26 | construction in progress | ||||||||||||||
61 | Various Improvement/ Construction of Roads with Drainage System at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City (Package 36 – 2020) b. Improvement/ Construction of Roads with Drainage System for Alley-5 (Portion) at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City | Barangay San Jose | 167,763.05 | 10-Dec-20 | 9-May-21 | 20% | 33,552.61 | construction in progress | ||||||||||||||
62 | Various Improvement/ Construction of Roads with Drainage System at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City (Package 36 – 2020) c. Improvement/ Construction of Roads with Drainage System for Alley-6 (Portion) at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City | Barangay San Jose | 244,231.38 | 10-Dec-20 | 9-May-21 | 20% | 48,846.28 | construction in progress | ||||||||||||||
63 | Various Improvement/ Construction of Roads with Drainage System at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City (Package 36 – 2020) d. Improvement/ Construction of Roads with Drainage System for Road-4 (Portion) at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City | Barangay San Jose | 166,808.62 | 10-Dec-20 | 9-May-21 | 20% | 33,361.72 | construction in progress | ||||||||||||||
64 | Various Improvement/ Construction of Roads with Drainage System at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City (Package 36 – 2020) e. Improvement/ Construction of Roads with Drainage System for Pathway-1 at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City | Barangay San Jose | 151,097.69 | 10-Dec-20 | 9-May-21 | 20% | 30,219.54 | construction in progress | ||||||||||||||
65 | Various Improvement/ Construction of Roads with Drainage System at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City (Package 36 – 2020) f. Improvement/ Construction of Roads with Drainage System for Pathway-3 at Tolosa Ville, Phase 1, Sitio Elaved, Brgy. San Jose, Antipolo City | Barangay San Jose | 174,639.39 | 10-Dec-20 | 9-May-21 | 20% | 34,927.88 | construction in progress | ||||||||||||||
66 | Improvement/Construction of Drainage Canal at Jacksonville and Brookfield Street, Joyous Heights, Sitio Hinapao, Brgy. San Jose, Antipolo City | Barangay San Jose | 836,700.13 | 18-Dec-20 | 17-Apr-21 | 15% | 125,505.02 | construction in progress | ||||||||||||||
67 | Improvement/ Concreting of Various Roads at Brgy. Sta. Cruz, Antipolo City ( 2020 – Package 41 ) a. Imprvt./ Concreting of Rushmore St.,at La Montana Estates, Brgy. Sta. Cruz, Antipolo City | Barangay Sta. Cruz | 1,316,797.78 | 18-Dec-20 | 17-May-21 | 0% | - | To start | ||||||||||||||
68 | Improvement/ Concreting of Various Roads at Brgy. Sta. Cruz, Antipolo City ( 2020 – Package 41 ) b. Imprvt./ Concreting (Portion) of Mckinley St.,at La Montana Estates, Brgy. Sta. Cruz, Antipolo City | Barangay Sta. Cruz | 2,561,999.81 | 18-Dec-20 | 17-May-21 | 0% | - | To start | ||||||||||||||
69 | Construction of Road with Drainage Canal with Pin No. 008-022-145 at New Life Subdivision, Brgy. Cupang, Antipolo City | Barangay Cupang | 3,292,250.00 | 8-Jan-21 | 18-May-21 | 0% | - | For implementation | ||||||||||||||
70 | Construction of Road with Drainage Canal with Pin No. 008-022-102 at New Life Subdivision, Brgy. Cupang, Antipolo City | Barangay Cupang | 2,546,107.58 | 8-Jan-21 | 18-May-21 | 0% | - | For implementation | ||||||||||||||
71 | Various Improvements at Brgy. Mayamot, Antipolo City ( 2019 – Package 61 ) a. Improvement / Concreting of Access Road with Fence Leading to Mayamot National High School, Broadway Pines Subd., Brgy. Mayamot, Antipolo City | Barangay Mayamot | 993,251.00 | 6-Nov-19 | 5-Mar-20 | 0% | - | Suspended-(pending demolition of structure (private) | ||||||||||||||
72 | Improvement/Concreting of Access Road Leading to Mayamot National High School, (Along Jose Rementina Property), Broadway Pines Subdivision, Barangay Mayamot, Antipolo City | Barangay Mayamot | 491,500.00 | 7-Feb-20 | 6-Jun-20 | 0% | - | Suspended-(pending demolition of structure (private) | ||||||||||||||
73 | Total Economic Development | 80,298,331.94 | 56,863,874.90 | |||||||||||||||||||
74 | ||||||||||||||||||||||
75 | ENVIRONMENTAL DEVELOPMENT | |||||||||||||||||||||
76 | ||||||||||||||||||||||
77 | Management and Maintenance with rehabilitation of the Antipolo City Controlled Disposal Facility | Antipolo City Dumpsite - Tanza | 6,349,849.85 | 1-Jul-20 | 31-Jul-20 | 100% | 6,349,849.85 | paid | ||||||||||||||
78 | Management and Maintenance with rehabilitation of the Antipolo City Controlled Disposal Facility | Antipolo City Dumpsite - Tanza | 6,349,849.85 | 1-Aug-20 | 31-Aug-20 | 100% | 6,349,849.85 | paid | ||||||||||||||
79 | Management and Maintenance with rehabilitation of the Antipolo City Controlled Disposal Facility | Antipolo City Dumpsite - Tanza | 6,349,849.85 | 1-Sep-20 | 30-Sep-20 | 100% | 6,349,849.85 | paid | ||||||||||||||
80 | Collection and Hauling with Operation & Maintanance of Transfer Station | Antipolo City Transfer Station | 12,708,011.25 | 1-Jul-20 | 31-Jul-20 | 100% | 12,708,011.25 | paid | ||||||||||||||
81 | Collection and Hauling with Operation & Maintanance of Transfer Station | Antipolo City Transfer Station | 12,708,011.25 | 1-Aug-20 | 31-Aug-20 | 100% | 12,708,011.25 | paid | ||||||||||||||
82 | Collection and Hauling with Operation & Maintanance of Transfer Station | Antipolo City Transfer Station | 12,708,011.25 | 1-Sep-20 | 30-Sep-20 | 100% | 12,708,011.25 | paid | ||||||||||||||
83 | Payment For Management And Maintenance With Rehabilitation Of The Antipolo City Controlled Disposal Facility For The Period Covering Nov. 1-30, 2020 | Antipolo City Dumpsite - Tanza | 6,349,849.85 | 1-Nov-20 | 30-Nov-20 | 100% | 6,349,849.85 | payment in process | ||||||||||||||
84 | Payment For Garbage Collection & Hauling Operation And Maintenance Of A Transfer Station Facility Of Antipolo City For The Period Covering Nov. 1-30, 2020 | Antipolo City Transfer Station | 12,708,011.25 | 1-Nov-20 | 30-Nov-20 | 100% | 12,708,011.25 | payment in process | ||||||||||||||
85 | Payment For Management And Maintenance With Rehabilitation Of The Antipolo City Controlled Disposal Facility For The Period Covering Dec. 1-31, 2020 | Antipolo City Dumpsite - Tanza | 6,349,849.85 | 1-Dec-20 | 31-Dec-20 | 100% | 6,349,849.85 | payment in process | ||||||||||||||
86 | Payment For Garbage Collection & Hauling Operation And Maintenance Of A Transfer Station Facility Of Antipolo City For The Period Covering Dec. 1-31, 2020 | Antipolo City Transfer Station | 12,708,011.25 | 1-Dec-20 | 31-Dec-20 | 100% | 12,708,011.25 | payment in process | ||||||||||||||
87 | Payment For Garbage Collection & Hauling Operation And Maintenance Of A Transfer Station Facility Of Antipolo City For The Period Covering Oct. 1-31, 2020 | Antipolo City Transfer Station | 12,708,011.25 | 1-Oct-20 | 31-Oct-20 | 100% | 12,708,011.25 | payment in process | ||||||||||||||
88 | Payment For Management And Maintenance With Rehabilitation Of The Antipolo City Controlled Disposal Facility For The Period Covering Oct. 1-31, 2020 | Antipolo City Dumpsite - Tanza | 6,349,849.85 | 1-Oct-20 | 31-Oct-20 | 100% | 6,349,849.85 | payment in process | ||||||||||||||
89 | Total Environmental Development | 114,347,166.60 | 114,347,166.60 | |||||||||||||||||||
90 | Grand Total | 205,939,169.34 | 180,796,444.34 | |||||||||||||||||||
91 | ||||||||||||||||||||||
92 | We hereby certify that we have reviewed the contents and hereby attest to the veracity and correctness of the data or information contained in this document. | |||||||||||||||||||||
93 | ||||||||||||||||||||||
94 | ||||||||||||||||||||||
95 | ||||||||||||||||||||||
96 | ||||||||||||||||||||||
97 | PRISCILLA R. PADUA (SGD.) | ANDREA B. YNARES (SGD.) | ||||||||||||||||||||
98 | OIC- City Budget Office | City Mayor | ||||||||||||||||||||