ANALYSIS OF RATE FOR CONSTRUCTION OF 3 SPAN 10' EACH CULVERT 52' ROADWAY)
2
3
BASED ON MRS 1ST QTR. 2011
4
1Excavation all type of soil for structures.
5
Abutment2x52x10,5x8=8736,00Cft
6
Pier2x57,125x7,75x8=7083,50Cft
7
Wing Wall4x(8+1)x7x8=2016,00Cft9
8
4x(10+3.5)x6,5x8=2808,00Cft13,5
9
4x(14+7.75)x6,25x8=4350,00Cft21,75
10
4x(16+10.25)x5,75x8=4830,00Cft26,25
11
4x(20+14.75)x5,25x8=5838,00Cft34,75
12
4x(25.5+20.5)x5x8=7360,00Cft46
13
14
Toe Wall D/S2x5x2,875x6=172,50Cft
15
1x4,875x2,875x6=84,09Cft
16
Toe Wall U/S2x5x2,875x4=115,00Cft
17
1x4,875x2,875x4=56,06Cft
18
Total=43449,15Cft8537-34912,15
19
@Rs.2 996,95
Per %o Cft.
Rs.130 215
20
2P/L brick ballast 1-1/2" to 2" guage (1:6:12) complete in all respect
21
Abutment2x52x10,5x4=4368,00Cft
22
Pier1x57,125x7,75x4=1770,88Cft
23
Wing Wall4x(8+1)x7x4=1008,00Cft9
24
4x2x6,5x4=208,00Cft
25
4x4x6,25x4=400,00Cft
26
4x2x5,75x4=184,00Cft26,25
27
4x4x5,25x4=336,00Cft34,75
28
4x5,5x5x4=440,00Cft46
29
30
Toe Wall D/S2x5x2,875x0,5=14,38Cft
31
1x4,875x2,875x0,5=7,01Cft
32
Toe Wall U/S2x5x2,875x0,5=14,38Cft
33
1x4,875x2,875x0,5=7,01Cft
34
Total=8757,66Cft3271-5486,66
35
@Rs.6 577,95
Per %Cft.
Rs.576 074
36
31st class brick work in foundation and plinth in 1:4 cement sand mortar complete in all respect
37
Abutment
38
1st Step2x52x8,625x1=897,00Cft
39
2nd Step2x52x8,25x1=858,00Cft
40
3rd Step2x52x7,875x1=819,00Cft
41
4th Step2x52x7,5x1=780,00Cft
42
5th Step2x52x7,125x1,5=1111,50Cft
43
6th Step2x52x6,75x0,5=351,00Cft
44
7th Step2x52x6,375x0,5=331,50Cft
45
8th Step2x52x6x0,5=312,00Cft
46
9th Step2x52x5,625x0,5=292,50Cft
47
10Th Step2x52x5,25x0,5=273,00Cft
48
11th Step2x52x4,875x0,5=253,50Cft
49
12th Step2x52x4,5x0,5=234,00Cft
50
13th Step2x52x4,125x0,5=214,50Cft
51
14th Step2x52x3,75x0,5=195,00Cft
52
15th Step2x52x3,375x0,5=175,50Cft
53
16th Step2x52x3x0,5=156,00Cft
54
17th Step2x52x2,625x0,5=136,50Cft
55
18th Step2x52x2,25x0,5=117,00Cft
56
Pier
57
1st Step2x56,125x6,75x0,25=189,42Cft
58
2nd Step2x55,75x6,375x0,25=177,70Cft
59
3rd Step2x55,375x6x0,25=166,13Cft
60
4th Step2x55x5,625x0,25=154,69Cft
61
5th Step2x54,625x5,25x0,25=143,39Cft
62
6th Step2x54,25x4,875x0,25=132,23Cft
63
7th Step2x53,875x4,5x0,25=121,22Cft
64
8th Step2x53,5x4,125x0,25=110,34Cft
65
9th Step2x53,125x3,75x0,25=99,61Cft
66
10Th Step2x52,75x3,375x0,25=89,02Cft
67
11th Step2x52,375x3x0,25=78,56Cft
68
12th Step2x52x2,625x9,25=2525,25Cft
69
Wing Wall
70
Section at 6-6
71
1st Step4x(8+2.5)/2x5,25x3=330,75Cft5,25
72
2nd Step4x(8+3.5)/2x4,5x0,75=77,63Cft5,75
73
3rd Step4x(8+4.25)/2x3,75x0,75=68,91Cft6,125
74
4th Step4x(8+5)/2x3x0,75=58,50Cft6,5
75
5th Step4x(8+5.375)/2x2,625x0,75=52,66Cft6,6875
76
6th Step4x(8+5.75)/2x2,25x2,33=144,17Cft6,875
77
7th Step4x(6+3.75)/2x2,25x0,75=32,91Cft4,875
78
8th Step4x(4+1.75)/2x2,25x1,25=32,34Cft2,875
79
Section at 5-5
80
1st Step4x2x4,5x3=108,00Cft
81
2nd Step4x2x3,75x0,75=22,50Cft
82
3rd Step4x2x3x0,75=18,00Cft
83
4th Step4x2x2,625x0,75=15,75Cft
84
5th Step4x2x2,25x2,33=41,94Cft
85
Section at 4-4
86
1st Step4x4x4,125x3=198,00Cft
87
2nd Step4x4x3,375x0,75=40,50Cft
88
3rd Step4x4x2,625x0,75=31,50Cft
89
4th Step4x4x2,25x1,58=56,88Cft
90
5th Step4x2x2,25x0,75=13,50Cft
91
Section at 3-3
92
1st Step4x2x3,375x3=81,00Cft
93
2nd Step4x2x2,625x0,75=15,75Cft
94
3rd Step4x2x2,25x1,58=28,44Cft
95
Section at 2-2
96
1st Step4x4x3x3=144,00Cft
97
2nd Step4x4x2,25x1,58=56,88Cft0,83
98
3rd Step4x2x2,25x0,75=13,50Cft
99
Section at 1-1
100
1st Step4x5,5x2,625x3=173,25Cft