Total Civil Phase 1rate amount
5
Cement OPC1325.418439bags8501126605.673
6
Cement PPC1038.040923bags760788911.1016
7
Sand (Khasro)4729.941159cu.ft56.66666667268029.999
8
Sand (double washed)983.8306642cu.ft63.3333333362309.2754
9
Aggregate6880.232734cu.ft76.66666667527484.5096
10
Brick89937.06399No.151349055.96
11
Rebar32005.76642kgs1183776680.438
12
13
Total civil cost
7899076.957
14
plumbing materials
0.03236972.3087
15
electric wires
0.03236972.3087
16
labour cost
0.251974769.239
17
company overhead
0.07552935.387
18
contengency
0.05394953.8478
19
20
21
Grand Total
11295680.05
22
23
24
25
26
SNDescriptionNo.
Length
Breadth
Height
Quantity
Unit
Remarks
27
1Site Clearance00.00 ft^2
Lumpsum
28
29
2Earthwork
30
2.1Excavation
31
2.1.1Footing (F1)68862,304.00 ft^3
6" extra on both sides
32
2.1.2Footing (F2)37771,029.00 ft^3
33
2.1.3Footing (F3)3667756.00 ft^3
34
FOR TIE BEAM WALL ALL ROUND338251,140.00 ft^3
35
427251,080.00 ft^3
36
6,309.00 ft^3
37
38
39
40
41
6,309.00
42
31 Layer brick soling of second class
43
Below Footing
44
3.1.1Footing (F1)688384.00
45
Footing(F2)377147.00
46
Footing(F3)366108.00
47
Footing(F4)0000.00
48
3.1.2For tie beam wall all round3382228.00
49
4272216.00
50
1,083.00
51
52
53
54
55
56
3.1.4Ground floor brick soling befor PCC
57
all round38271,026.00
58
59
2,109.00 ft^2
60
3.2Sand Filling above Brick Soling of atleast half inch
61
3.2.1Footing (F1)688384.00 ft^2
62
Footing(F2)377147.00 ft^2
63
Footing(F3)366108.00 ft^2
64
Footing(F4)0000.00 ft^2
65
ft^2
66
3.2.2For tie beam wall all round3382228.00
67
4272216.00
68
1,083.00 ft^2
69
70
71
72
73
74
3.2.3Ground floor Sand Filling above brick befor PCC
75
all round38271,026.00
76
1,026.00
77
2,109.00 ft^2
78
475mm ThickP.C.C (1:2:4)
79
4.1Footing (F1)6880.33126.72
80
4.2Footing(F2)3770.3348.51 ft^3
81
Footing(F3)3660.3335.64 ft^3
82
Footing(F4)0000.330.00
83
84
4.3For tie beam wall all round34020.3379.20
85
42720.3371.28
86
361.35
87
88
89
90
91
92
4.5Ground floor PCC
93
all round38270.33338.58
94
338.58
95
699.93 ft^3
96
ft^3
97
5
Concrete for RCC work of minimum strenght M20 1:1.5:3
98
5.1Footing
99
5.1.1Footing (F1)6881.75672.00
100
Footing (F2)3771.75257.25 ft^3