Create professional Gantt charts in GanttPRO in a few clicks
3
4
construction-templates1/4/2021
5
Color
WBS Number
Task name / Title
Assigned to
Planned start date
Planned end date
Deadline
Progress (%)
Duration (hours)
Estimated hours
Time log (minutes)
StatusPriority
Task description
Cost
Actual cost
6
1ZONING2/3/20214/9/202103840000
7
1.1Land Use2/3/20214/4/2021036000OpenMedium00
8
1.2Easements, Set Backs2/6/20214/9/2021036000OpenMedium00
9
1.3
Access, Street Improvements
2/6/20214/9/2021036000OpenMedium00
10
1.4Utilities Available2/6/20214/9/2021036000OpenMedium00
11
2HOUSE PLANS2/10/20214/16/202103840000
12
2.1Purchase Standard Plans2/10/20214/11/2021036000OpenMedium00
13
2.2Architect Original Drawings2/10/20214/11/2021036000OpenMedium00
14
2.3Specifications2/10/20214/11/2021036000OpenMedium00
15
2.4Architect Manage Job2/13/20214/16/2021036000OpenMedium00
16
2.5Engineer-Loads & Spans2/13/20214/16/2021036000OpenMedium00
17
2.6Draftsman2/13/20214/16/2021036000OpenMedium00
18
3LOT SURVEY2/17/20214/23/202103840000
19
3.1House & Driveway2/17/20214/18/2021036000OpenMedium00
20
3.2Well Locaton2/17/20214/18/2021036000OpenMedium00
21
3.3Septic Location2/17/20214/18/2021036000OpenMedium00
22
3.4Fire Hydrant & Truck Access2/20/20214/23/2021036000OpenMedium00
23
3.5Plot Plan2/20/20214/23/2021036000OpenMedium00
24
4FINANCIAL - LOAN2/21/20214/25/202103680000
25
4.1Land Cost2/21/20214/24/2021036000OpenMedium00
26
4.2Interest on Land2/24/20214/25/2021036000OpenMedium00
27
4.3Interest on Const. Loan2/24/20214/25/2021036000OpenMedium00
28
4.4Points, Etc.2/24/20214/25/2021036000OpenMedium00
29
5SEWER & WATER HOOKUP2/27/20214/30/2021036000OpenMedium00
30
6HEALTH PERMIT2/27/20215/2/202103760000
31
6.1Fees2/27/20214/30/2021036000OpenMedium00
32
6.2Percolation Test2/28/20215/1/2021036000OpenMedium00
33
6.3Soils Engineer3/3/20215/2/2021036000OpenMedium00
34
7INSURANCE3/3/20215/2/2021036000OpenMedium00
35
8LOT CLOSING COSTS3/3/20215/2/2021036000OpenMedium00
36
9BUILDING PERMITS3/6/20215/7/202103600000
37
9.1Fees3/6/20215/7/2021036000OpenMedium00
38
9.2Inspection Schedule3/6/20215/7/2021036000OpenMedium00
39
10PRELIMINARY LIST ONLY3/7/20215/8/2021036000OpenMedium00
40
11BUILD PHASE3/10/20215/9/2021036000OpenMedium00
41
12SPECIAL & DRY IN MATERIALS3/10/20215/14/202103840000
42
12.1Rough Hardware, Misc.3/10/20215/9/2021036000OpenMedium00
43
12.2Lolly Columns3/13/20215/14/2021036000OpenMedium00
44
12.3Steel Beams3/13/20215/14/2021036000OpenMedium00
45
12.4Rough Lumber, Trusses3/13/20215/14/2021036000OpenMedium00
46
13WINDOWS/OPENINGS3/17/20215/16/202103600000
47
13.1Windows, Grills, Screens3/17/20215/16/2021036000OpenMedium00
48
13.2Exterior Doors,Screens3/17/20215/16/2021036000OpenMedium00
49
13.3Skylights and Light Tubes3/17/20215/16/2021036000OpenMedium00
50
14DEMOLITION3/20/20215/21/2021036000OpenMedium00
51
15LOT CLEARING3/20/20215/23/202103760000
52
15.1Debris Removal & Clearing3/20/20215/21/2021036000OpenMedium00
53
15.2Dump Fee3/21/20215/22/2021036000OpenMedium00
54
15.3Bury Stumps, etc.3/24/20215/23/2021036000OpenMedium00
55
16DRIVEWAY, rough3/24/20215/28/202103840000
56
16.1Grade3/24/20215/23/2021036000OpenMedium00
57
16.2Base Rock, Culverts3/27/20215/28/2021036000OpenMedium00
58
17UTILITIES3/27/20215/29/202103680000
59
17.1Temporary at startup3/27/20215/28/2021036000OpenMedium00
60
17.2Transfer to permanent3/28/20215/29/2021036000OpenMedium00
61
18WELL or PUBLIC WATER3/31/20215/30/2021036000OpenMedium00
62
19SEPTIC or PUBLIC SEWER3/31/20215/30/2021036000OpenMedium00
63
20LAYOUT HOUSE FOOTPRINT4/3/20216/4/202103600000
64
20.1Establish Finish Floor Height4/3/20216/4/2021036000OpenMedium00
65
20.2Set Back Distances4/3/20216/4/2021036000OpenMedium00
66
21DIG FOUNDATION4/3/20216/4/2021036000OpenMedium00
67
22ROCK PROBLEM4/4/20216/5/2021036000OpenMedium00
68
23PREPARE FOR FOOTINGS4/7/20216/6/202103600000
69
23.1Lay out and excavate4/7/20216/6/2021036000OpenMedium00
70
23.2Form, Rebar, Grade Pegs4/7/20216/6/2021036000OpenMedium00
71
24POUR FOOTINGS & PADS4/10/20216/11/202103600000
72
24.1Yds. of Concrete4/10/20216/11/2021036000OpenMedium00
73
25SET BRICK POINTS4/10/20216/11/2021036000OpenMedium00
74
26TERMITE TREATMENT4/11/20216/12/2021036000OpenMedium00
75
27RADON CONTROL4/14/20216/13/2021036000OpenMedium00
76
28FOUNDATION WALLS4/14/20216/20/202104000000
77
28.1Block/Course4/14/20216/13/2021036000OpenMedium00
78
28.2Piers4/17/20216/18/2021036000OpenMedium00
79
28.3Pour Wall, Yds. Of Concrete4/17/20216/18/2021036000OpenMedium00
80
28.4Lintels, Rebar4/17/20216/18/2021036000OpenMedium00
81
28.5Parging4/18/20216/19/2021036000OpenMedium00
82
28.6Cement, Sand, etc.4/21/20216/20/2021036000OpenMedium00
83
29WATERPROOF FOUNDATION.4/21/20216/20/2021036000OpenMedium00
84
30COLUMNS/BEAMS SET4/21/20216/20/2021036000OpenMedium00
85
31UNDERGROUND PLUMBING4/24/20216/25/2021036000OpenMedium00
86
32BRICK/STONE, to finish grade4/24/20216/25/2021036000OpenMedium00
87
33GARAGE DOORS4/25/20216/27/202103680000
88
33.1Openers4/25/20216/26/2021036000OpenMedium00
89
33.2Trim, Backing, Weatherstrip4/28/20216/27/2021036000OpenMedium00
90
34DRAIN TILE4/28/20216/27/2021036000OpenMedium00
91
35FIRE PLACE - INTERIOR5/1/20217/2/202103600000
92
35.1Pour Hearth5/1/20217/2/2021036000OpenMedium00
93
35.2Firebox, or Set Prefab5/1/20217/2/2021036000OpenMedium00
94
35.3Brick or Stone Facing5/1/20217/2/2021036000OpenMedium00
95
36PREPARE CONC. SLABS ETC.5/5/20217/9/202103840000
96
36.1
Gravel, Wire, Poly, Grade Stakes
5/5/20217/4/2021036000OpenMedium00
97
36.2Labor to Prepare for Slab5/5/20217/4/2021036000OpenMedium00
98
36.3Rebar, Wire, form boards5/5/20217/4/2021036000OpenMedium00
99
36.4
Labor-Prepare, Form other Conc.
5/8/20217/9/2021036000OpenMedium00
100
36.5
Deck & Post Hole footings, etc.
5/8/20217/9/2021036000OpenMedium00