Project Management Timeline
2
3
WORK PACKAGES AND TASKS202320242025
4
SepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAug
5
Work Package 1: Review and Assessment of the State of the Field
6
Task 1.1. Cataloguing of all national best practicesD1
7
Task 1.2 Systematic review of fieldM1
8
Work Package 2: Quantitative Analysis
9
Task 2.1. Design of research instruments using quantitative research methodsD2
10
Task 2.2. Data collection and engaging of participants in quantitative research methodsM2
11
Work Package 3: Qualitative Analysis
12
Task 3.1. Design of research instruments using qualitative research methodsD3
13
Task 3.2. Data collection and engaging of participants in qualitative research methodsM3
14
Work Package 4: Best Practice Observations and International Benchmarking
15
Task 4.1. Design of research observation scheduleD4
16
Task 4.2. Research visit to undertake observations of international best practiceM4
17
Work Package 5: Dissemination and Policy Recommendations
18
Task 5.1. Presentation of project findings at national and international conferences
19
Task 5.2. Delivery of policy recommendations to key stakeholdersD5
20
Work Package 6: Management
21
Task 6.1. Formation of Executive Committee and Advisory Board
22
Task 6.2. Weekly meetings with project team
23
DeliverablesMilestones
24
D1. Review paper demonstrating the state of the fieldM1. Completion of review
25
D2. Research instrument for qualitative analysisM2. Completion of qualitative analysis
26
D3. Research Instrument for quantitative analysisM3. Completion of quantitative analysis
27
D4. Commentary paper highlighting gaps in international best practiceM4. Completion of international benchmarking
28
D5. Policy recommendations
29
For more resources and templates for early career researchers see www.JosephRoche.ie/Resources and the SAGE textbook "Essential Skills for Early Career Researchers"