1 | CONSOLIDATED QUARTERLY REPORT ON GOVERNMENT PROJECTS, PROGRAMS OR ACTIVITIES | |||||||||||||||||||||||||
2 | FOR THE 1ST QUARTER , CY 2022 | |||||||||||||||||||||||||
3 | ||||||||||||||||||||||||||
4 | PROVINCIAL GOVERNMENT OF BOHOL | |||||||||||||||||||||||||
5 | ||||||||||||||||||||||||||
6 | PROGRAM OR PROJECT | LOCATION | TOTAL COST | DISBURSEMENTS | DATE STARTED | TARGET COMPLETION DATE | PROJECT STATUS | No. of Extensions, if any | REMARKS | |||||||||||||||||
7 | Total Disbursements from the previous quarter | Disbursements for the quarter | % of Completion | Total Cost Incurred to Date | ||||||||||||||||||||||
8 | DOTr - PANGLAO BOHOL INTERNATIONAL AIRPORT PROJECT | Panglao, Bohol | 159,073,600.00 | 152,403,594.83 | 87,827.40 | 95.86% | 152,491,422.23 | on-going project | ||||||||||||||||||
9 | ANIMAL RELIEF AND OPERATION FROM THE BUREAU OF ANIMAL INDUSTRY | N/A | 1,000,000.00 | 971,032.00 | - | 97.10% | 971,032.00 | project completed - remaining fund balance for return to NGA | ||||||||||||||||||
10 | DOH - SUBSIDY FOR THE PURCHASE OF REPRODUCTIVE HEALTH COMMODITIES AND CONDUCT OF FAMILY PLANNING ACTIVITIES | N/A | 2,368,881.00 | 2,313,100.95 | - | 97.65% | 2,313,100.95 | Trust Fund account still for reconciliation | ||||||||||||||||||
11 | DOH - REPAIR/ENHANCEMENT OF HEALTH FACILITY OF CATIGBIAN DISTRICT HOSPITAL | Catigbian | 100,000.00 | - | - | 0.00% | - | on-going project | ||||||||||||||||||
12 | DOH - REPAIR/ENHANCEMENT OF HEALTH FACILITY OF CONG. NATALIO CASTILLO MEMORIAL HOSPITAL | Loon | 100,000.00 | 73,961.89 | - | 73.96% | 73,961.89 | on-going project | ||||||||||||||||||
13 | DOH - REPAIR/ENHANCEMENT OF HEALTH FACILITY OF CONG. SIMEON TORIBIO MEMORIAL HOSPITAL | Carmen | 100,000.00 | 93,963.08 | - | 93.96% | 93,963.08 | on-going project | ||||||||||||||||||
14 | DOH - REPAIR/ENHANCEMENT OF HEALTH FACILITY OF GARCIA MEMORIAL PROVINCIAL HOSPITAL | Talibon | 100,000.00 | 99,980.00 | - | 99.98% | 99,980.00 | project completed; remaining mimimal fund balance for return to the NGA | ||||||||||||||||||
15 | DOH - REPAIR/ENHANCEMENT OF HEALTH FACILITY OF PROV'L. HEALTH OFFICE | Tagbilaran city, Bohol | 700,000.00 | 464,000.00 | - | 66.29% | 464,000.00 | on-going project | ||||||||||||||||||
16 | DOH - REPAIR/ENHANCEMENT OF HEALTH FACILITY OF TEODORO B. GALAGAR DISTRICT HOSPITAL | Jagna | 200,000.00 | 141,956.50 | - | 70.98% | 141,956.50 | on-going project | ||||||||||||||||||
17 | DOH - PERFORMANCE BASED GRANT OF THE NATIONAL TUBERCULOSIS ELIMINATION PROGRAM | N/A | 1,200,000.00 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
18 | DOH - TRAINING COURSES ON LEPROSY AND INTEGRATED DISABILITY MANAGEMENT | N/A | 725,000.00 | 113,439.00 | - | 15.65% | 113,439.00 | on-going program | ||||||||||||||||||
19 | DOH - ESTABLISHMENT AND OPERATION OF PROVINCIAL EMERGENCY OPERATION | N/A | 600,000.00 | 210,110.95 | - | 35.02% | 210,110.95 | on-going program | ||||||||||||||||||
20 | DOH - PERFORMANCE BASED GRANT TO THE NATIONAL RABIES PREVENTION & CONTROL PROGRAM | N/A | 150,000.00 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
21 | FINANCIAL ASSISTANCE FOR CONG. NATALIO CASTILLO DISTRICT HOSPITAL | Loon | 15,000,000.00 | 11,993,989.50 | - | 79.96% | 11,993,989.50 | Trust Fund account still for reconciliation | ||||||||||||||||||
22 | FINANCIAL ASSISTANCE FOR MARIBOJOC HOSPITAL | Maribojoc | 5,000,000.00 | 4,994,571.08 | - | 99.89% | 4,994,571.08 | Trust Fund account still for reconciliation | ||||||||||||||||||
23 | FINANCIAL ASSISTANCE FOR CONSTRUCTION OF CONG. NATALIO CASTILLO MEMORIAL HOSPITAL | Loon | 56,718,750.00 | - | - | 0.00% | - | Trust Fund account for verification | ||||||||||||||||||
24 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) - CATIGBIAN DISTRICT HOSPITAL** | Catigbian | 2,794,416.57 | 2,116,212.76 | 28,046.10 | 76.73% | 2,144,258.86 | on-going program | ||||||||||||||||||
25 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) - CONG. NATALIO P. CASTILLO SR. MEMORIAL HOSPITAL** | Loon | 2,218,416.57 | 1,488,269.00 | 587,057.75 | 93.55% | 2,075,326.75 | on-going program | ||||||||||||||||||
26 | DOH - CONSULTANCY SERVICES GEOTECH EVALUATION AND STRUCTURAL PLAN PREPARATION (LOON HOSPITAL BUILDING)) | Loon | 300,000.00 | - | - | 0.00% | - | Trust Fund account for verification | ||||||||||||||||||
27 | DOH - MEDICAL ASSISTANCE PROGRAM ( MAP) - PRES. CARLOS P. GARCIA MUNICIPAL HOSPITAL | Pitogo | 6,335,975.00 | 219,761.40 | - | 3.47% | 219,761.40 | on-going program | ||||||||||||||||||
28 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) - CLARIN COMMUNITY HOSPITAL | Clarin | 700,000.00 | 696,244.00 | - | 99.46% | 696,244.00 | on-going program | ||||||||||||||||||
29 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) -FRANCISCO DAGOHOY MUNICIPAL HOSPITAL**/*** | Dagohoy | 574,978.58 | 536,943.60 | - | 93.38% | 536,943.60 | on-going program | ||||||||||||||||||
30 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) -CANDIJAY COMMUNITY HOSPITAL** | Candijay | 5,176,916.57 | 3,707,082.22 | 36,655.64 | 72.32% | 3,743,737.86 | on-going program | ||||||||||||||||||
31 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) - GARCIA MEMORIAL PROVINCIAL HOSPITAL** | Talibon | 3,550,000.00 | 2,180,350.45 | 93,851.50 | 64.06% | 2,274,201.95 | on-going program | ||||||||||||||||||
32 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) -TEODORO B. GALAGAR DISTRICT HOSPITAL** | Jagna | 4,966,816.57 | 3,875,938.00 | - | 78.04% | 3,875,938.00 | on-going program | ||||||||||||||||||
33 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) - CONG. SIMEON TORIBIO MEMORIAL HOSPITAL** | Carmen | 6,218,866.57 | 4,278,065.49 | 114,000.00 | 70.62% | 4,392,065.49 | on-going program | ||||||||||||||||||
34 | DOH - MEDICAL ASSISTANCE PROGRAM (MAP) - MARIBOJOC COMMUNITY HOSPITAL** | Maribojoc | 74,978.57 | - | - | 0.00% | - | newly implemented program | ||||||||||||||||||
35 | DOH - TSEKAP SURGICAL CARAVAN | N/A | 199,845.00 | 67,450.00 | - | 33.75% | 67,450.00 | on-going program | ||||||||||||||||||
36 | DOH - IMPLEMENTATION OF COMMUNITY BASED TREATMENT AND REHABILITATION PROGRAM | N/A | 999,840.00 | - | 484,800.00 | 48.49% | 484,800.00 | on-going program | ||||||||||||||||||
37 | DOH - PERFORMANCE BASED GRANT - NATIONAL DENGUE PREVENTION AND CONTROL PROGRAM ACTIVITIES | N/A | 250,000.00 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
38 | DOH - PERFORMANCE BASED GRANT TO SOCIAL HYGIENE CLINIC AND NASPCP PROGRAMS OF LGU | N/A | 300,000.00 | - | - | 0.00% | - | on-going program | ||||||||||||||||||
39 | DOH - LIFESTYLE RELATED PREVENTION AND CONTROL PROGRAM (NCD MAINTENANCE MEDS) | N/A | 1,621,970.00 | 429,759.75 | 776,800.00 | 74.39% | 1,206,559.75 | on-going program | ||||||||||||||||||
40 | KOREA FOUNDATION BOHOL CRISIS INTERVENTION CENTER | N/A | 178,921.50 | 173,849.90 | - | 97.17% | 173,849.90 | Trust Fund account still for reconciliation | ||||||||||||||||||
41 | DOH - MATERNAL, NEONATAL, CHILD HEALTH AND NUTRITION | N/A | 12,564,238.69 | 10,039,901.50 | - | 79.91% | 10,039,901.50 | Trust Fund account still for reconciliation | ||||||||||||||||||
42 | DOH - START-UP FUNDS FOR THE PROVINCIAL INVESTMENT PLAN FOR HEALTH (PIPH) | N/A | 22,513,884.80 | 8,928,569.29 | 210,620.00 | 40.59% | 9,139,189.29 | on-going program; total cost still for reconciliation | ||||||||||||||||||
43 | DILG - BOHOL EARTHQUAKE ASSISTANCE PROGRAM | N/A | 2,389,494,190.00 | 2,363,996,969.34 | 84,879.95 | 98.94% | 2,364,081,849.29 | on-going program | ||||||||||||||||||
44 | FINANCIAL ASSISTANCE FOR ROLL-OUT STRATEGY OF THE LGU DISASTER PREPAREDNESS MANUALS | N/A | 250,000.00 | 164,700.00 | - | 65.88% | 164,700.00 | Trust Fund account still for reconciliation | ||||||||||||||||||
45 | DILG - KALSADA/CMGP CONCRETING OF POBLACION (BUENAVISTA)-BONOTBOT-TIGUMAN-OVERLAND ROAD | Buenavista | 50,000,000.00 | 44,160,790.80 | 5,780,562.11 | 99.88% | 49,941,352.91 | on-going project; remaining fund balance for return to source agency | ||||||||||||||||||
46 | DILG - KALSADA/CMGP CONCRETING OF PILAR-BAGACAY ROAD | Pilar | 36,307,711.00 | 17,156,744.52 | 12,117,255.19 | 80.63% | 29,273,999.71 | on-going project | ||||||||||||||||||
47 | DILG - KALSADA/CMGP CONCRETING OF POBLACION (TALIBON)-SAN FRANCISCO ROAD | Talibon | 20,000,000.00 | 19,970,166.53 | - | 99.85% | 19,970,166.53 | project completed; remaining fund balance for return to source agency | ||||||||||||||||||
48 | DILG - KALSADA/CMGP CONCRETING OF POBLACION (CARMEN)-VALLEHERMOSO ROAD | Carmen | 30,000,000.00 | 21,785,684.56 | 8,164,292.79 | 99.83% | 29,949,977.35 | on-going project; remaining fund balance for return to source agency | ||||||||||||||||||
49 | DPWH - SLRF-MVUC GUINDULMAN MAYUGA-LOMBOG ROAD | Guindulman | 21,614,662.00 | 15,092,848.08 | - | 69.83% | 15,092,848.08 | on-going project | ||||||||||||||||||
50 | DBM - LGSF CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CONG. PABLO MALASARTE NATIONAL HIGHSCHOOL | Cabad, Balilihan | 10,000,000.00 | 573,864.63 | - | 5.74% | 573,864.63 | Trust Fund account still for reconciliation | ||||||||||||||||||
51 | DILG - LGSF ( RESCUE EQUIPMENT) | Cortes | 4,600,000.00 | - | - | 0.00% | - | on-going project | ||||||||||||||||||
52 | DILG - LGSF ( INTEGRATED COMMUNITY FOOD PRODUCTION) | Cortes | 4,200,000.00 | 3,806,549.50 | - | 90.63% | 3,806,549.50 | Trust Fund account still for reconciliation | ||||||||||||||||||
53 | DILG - LGSF ( CORE LOCAL ROAD CONSTRUCTION/MAINTENANCE/ REHABILITATION)*** | Danao | 1,260,000.00 | 1,260,000.00 | - | 100.00% | 1,260,000.00 | project completed; unused fund returned to the source agency already | ||||||||||||||||||
54 | DILG - REHAB/ REPAIR OF WATERWORKS SYSTEM FOR THE MUNICIPALITY OF CORTES | Cortes | 8,123,242.79 | 6,786,192.08 | - | 83.54% | 6,786,192.08 | on-going project | ||||||||||||||||||
55 | REHABLILITATION OF SEAWEEDS AND AQUAFORMS | N/A | 27,000,000.00 | 25,982,878.67 | - | 96.23% | 25,982,878.67 | project completed; remaining fund balance for return to source agency | ||||||||||||||||||
56 | PROVINCIAL ROAD MANAGEMENT FACILITY PRMF Project | N/A | 81,355,021.02 | 79,772,489.44 | - | 98.05% | 79,772,489.44 | Trust Fund account still for reconciliation | ||||||||||||||||||
57 | PHILIPPINE RURAL DEVELOPMENT PROJECT - PRDP (EQUITY)** | N/A | 77,868,974.14 | 43,554,692.13 | 823,720.40 | 56.99% | 44,378,412.53 | LGU share for PRDP on-going projects | ||||||||||||||||||
58 | PRDP - REHABILITATION OF ALEGRIA - BUGHO FMR (LP) | Loboc, Bohol | 43,019,100.59 | 43,019,100.58 | - | 100.00% | 43,019,100.58 | on-going project; fund downloaded is based on WIP billings | ||||||||||||||||||
59 | PRDP - REHABILITATION OF ALEGRIA - BUGHO FMR (GOP) | Loboc, Bohol | 5,377,387.57 | 5,377,387.57 | - | 100.00% | 5,377,387.57 | on-going project; fund downloaded is based on WIP billings | ||||||||||||||||||
60 | PRDP - COCO BASED PRODUCTION AND MARKETING ENTERPRISE- LOON, BOHOL (LP) | Loon, Bohol | 480,000.00 | 480,000.00 | - | 100.00% | 480,000.00 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
61 | PRDP - COCO BASED PRODUCTION AND MARKETING ENTERPRISE- LOON, BOHOL (GOP) | Loon, Bohol | 160,000.00 | 160,000.00 | - | 100.00% | 160,000.00 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
62 | PRDP - BOHOL DAIRY PROCESSING AND MARKETING- UBAY, BOHOL (LP) | Ubay, Bohol | 4,372,200.00 | 3,183,620.58 | 77,161.20 | 74.58% | 3,260,781.78 | on-going project | ||||||||||||||||||
63 | PRDP - BOHOL DAIRY PROCESSING AND MARKETING- UBAY, BOHOL (GOP) | Ubay, Bohol | 1,457,400.00 | 1,061,206.86 | 25,720.40 | 74.58% | 1,086,927.26 | on-going project | ||||||||||||||||||
64 | PRDP - REHABILITATION OF DEL CARMEN WESTE VIA TAGUBAS (LP) | Balilihan, Bohol | 22,172,102.79 | 22,172,102.08 | - | 100.00% | 22,172,102.08 | project completed - remaining minimal fund balance represents payable to contractor due to overrecoupment | ||||||||||||||||||
65 | PRDP - REHABILITATION OF DEL CARMEN WESTE VIA TAGUBAS (GOP) | Balilihan, Bohol | 2,771,512.85 | 2,771,512.76 | - | 100.00% | 2,771,512.76 | project completed - remaining minimal fund balance represents payable to contractor due to overrecoupment | ||||||||||||||||||
66 | PRDP - REHABILITATION OF DAGNAWAN - DAGOHOY FMR (LP)** | Inabanga, Bohol | 92,433,837.78 | 62,263,264.50 | - | 67.36% | 62,263,264.50 | on-going project; fund downloaded is based on WIP billings | ||||||||||||||||||
67 | PRDP - REHABILITATION OF DAGNAWAN - DAGOHOY FMR (GOP) | Inabanga, Bohol | 7,782,908.07 | 7,782,908.06 | - | 100.00% | 7,782,908.06 | on-going project; fund downloaded is based on WIP billings | ||||||||||||||||||
68 | PRDP - BATUAN NATIVE CHICKEN BREEDING AND CHICKS HARDENING FACILITIES AND MARKETING (LP) | Batuan | 3,700,653.00 | 3,700,653.00 | - | 100.00% | 3,700,653.00 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
69 | PRDP - BATUAN NATIVE CHICKEN BREEDING AND CHICKS HARDENING FACILITIES AND MARKETING (GOP) | Batuan | 1,233,551.00 | 1,233,551.00 | - | 100.00% | 1,233,551.00 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
70 | PRDP - VIRGIN COCONUT OIL (VCO) PROCESSING AND MARKETING ENTERPRISE (LP) | Jagna, Bohol | 2,046,000.00 | 2,046,000.00 | - | 100.00% | 2,046,000.00 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
71 | PRDP - VIRGIN COCONUT OIL (VCO) PROCESSING AND MARKETING ENTERPRISE (GOP) | Jagna, Bohol | 682,000.00 | 682,000.00 | - | 100.00% | 682,000.00 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
72 | PRDP - VIRGIN COCONUT OIL (VCO) PROCESSING AND MARKETING ENTERPRISE - CIVIL WORKS (LP) | Jagna, Bohol | 2,242,087.58 | 2,227,883.93 | - | 99.37% | 2,227,883.93 | on-going project | ||||||||||||||||||
73 | PRDP - VIRGIN COCONUT OIL (VCO) PROCESSING AND MARKETING ENTERPRISE CIVIL WORKS - (GOP) | Jagna, Bohol | 747,362.53 | 742,627.97 | - | 99.37% | 742,627.97 | on-going project | ||||||||||||||||||
74 | PRDP - SEAWEEDS PRODUCTION, CONSOLIDATION & MARKETING ENTERPRISE (LP) | Getafe, Bohol | 6,726,000.00 | 4,326,000.00 | 2,394,000.00 | 99.91% | 6,720,000.00 | on-going project | ||||||||||||||||||
75 | PRDP - SEAWEEDS PRODUCTION, CONSOLIDATION & MARKETING ENTERPRISE (GOP) | Getafe, Bohol | 2,242,000.00 | 1,442,000.00 | 798,000.00 | 99.91% | 2,240,000.00 | on-going project | ||||||||||||||||||
76 | PRDP - SEAWEEDS PRODUCTION, CONSOLIDATION & MARKETING ENTERPRISE - CIVIL WORKS (LP) | Getafe, Bohol | 4,365,138.82 | 4,353,000.00 | - | 99.72% | 4,353,000.00 | on-going project | ||||||||||||||||||
77 | PRDP - SEAWEEDS PRODUCTION, CONSOLIDATION & MARKETING ENTERPRISE - CIVIL WORKS (GOP) | Getafe, Bohol | 1,455,046.27 | 1,451,000.00 | - | 99.72% | 1,451,000.00 | on-going project | ||||||||||||||||||
78 | GEF - AGUINING MARINE SANCTUARY REHABILITATION PRES. CPG, BOHOL | CPG, BOHOL | 2,474,706.67 | 1,552,912.93 | - | 62.75% | 1,552,912.93 | on-going project | ||||||||||||||||||
79 | GEF - ASINAN FISH SANCTUARY REHABILITATION BUENAVISTA, BOHOL | Buenavista, Bohol | 2,041,466.67 | 1,447,572.34 | - | 70.91% | 1,447,572.34 | on-going project | ||||||||||||||||||
80 | GEF - BILANGBILANGAN EAST MARINE SANCTUARY REHABILITATION BIEN UNIDO | Bien Unido | 2,149,040.00 | 1,291,443.67 | - | 60.09% | 1,291,443.67 | on-going project | ||||||||||||||||||
81 | GEF - EAST SEAWEEDS DEVELOPMENT PROJECT BILANGBILANGAN, BIEN UNIDO | Bien Unido | 799,568.00 | 799,568.00 | - | 100.00% | 799,568.00 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
82 | GEF - CATABAN MARINE SANCTUARY REHABILITATION, TALIBON | Talibon | 2,551,512.00 | 1,700,929.66 | - | 66.66% | 1,700,929.66 | on-going project | ||||||||||||||||||
83 | GEF - GUINDACPAN MARINE SANCTUARY | Guindacpan, Talibon | 2,660,496.00 | 1,754,192.49 | - | 65.93% | 1,754,192.49 | on-going project | ||||||||||||||||||
84 | GEF - HINGOTANAN WEST MARINE PROTECTED AREA | Bien Unido | 2,149,040.00 | 1,291,443.66 | - | 60.09% | 1,291,443.66 | on-going project | ||||||||||||||||||
85 | GEF - SEAWEEDS NURSERY, PRODUCTION, AND TRADING PROJECT- GUINDACPAN, TALIBON | Talibon | 1,264,497.60 | 1,264,497.60 | - | 100.00% | 1,264,497.60 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
86 | GEF - SEAWEEDS PRODUCTION AND TRADING- CATABAN, TALIBON | Cataban, Talibon | 1,285,505.60 | 1,285,505.60 | - | 100.00% | 1,285,505.60 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
87 | GEF - SEAWEEDS PRODUCTION AND MARKETING- AGUINING, PRES. GARCIA | Aguining, Pres. Garcia | 800,000.00 | 800,000.00 | - | 100.00% | 800,000.00 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
88 | GEF - SEAWEED PRODUCTION AND TRADING - SINANDIGAN, UBAY | Sinandigan, Ubay | 799,568.00 | 799,568.00 | - | 100.00% | 799,568.00 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
89 | GEF - SEAWEEDS PRODUCTION AND TRADING- ASINAN- BUENAVISTA | Asinan, Buenavista | 1,206,000.00 | 1,206,000.00 | - | 100.00% | 1,206,000.00 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
90 | GEF - HINGOTANAN WEST SEAWEED DEVELOPMENT- BIEN UNIDO | Bien Unido | 798,851.20 | 798,851.20 | - | 100.00% | 798,851.20 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
91 | GEF - MARINE PROTECTED AREA REHABILITATION- SINANDIGAN, UBAY | Sinandigan, Ubay | 2,152,978.67 | 1,390,685.69 | - | 64.59% | 1,390,685.69 | on-going project | ||||||||||||||||||
92 | GEF - MARINE SANCTUARY REHABILITATION - SIDLAKAN, PRES. GARCIA | Sidlakan, Pres. Garcia | 2,314,706.67 | 1,699,201.74 | - | 73.41% | 1,699,201.74 | on-going project | ||||||||||||||||||
93 | GEF - SEAWEED PRODUCTION AND TRADING - SAGUISE, PRES. GARCIA | Saguise, Pres. Garcia | 800,000.00 | 800,000.00 | - | 100.00% | 800,000.00 | on-going project; waiting for the liquidaton report from the recipient proponent group | ||||||||||||||||||
94 | PCSO - PAMASKONG ALAY FOR VICTIMS OF YOLANDA | N/A | 4,275,032.64 | 2,600,709.27 | - | 60.83% | 2,600,709.27 | Trust Fund account still for reconciliation | ||||||||||||||||||
95 | DSWD - GPBP PROJECT 2014 | N/A | 4,736,000.00 | 2,467,502.15 | - | 52.10% | 2,467,502.15 | Trust Fund account still for reconciliation | ||||||||||||||||||
96 | DBM - LGSF CONSTRUCTION OF FOOTBRIDGE JANOPOL-SEVILLA ; CONSTRUCTION OF MULTI-PURPOSE BUILDING AT CONG. PABLO MALASARTE HS CABAD, BALILIHAN | Balilihan | 10,000,000.00 | 3,397,237.09 | - | 33.97% | 3,397,237.09 | Trust Fund account still for reconciliation | ||||||||||||||||||
97 | REHABILITATION OF PRES. CARLOS P. GARCIA MUSEUM | N/A | 482,500.00 | 439,105.79 | - | 91.01% | 439,105.79 | project completed; remaining fund balance for return to the NGA | ||||||||||||||||||
98 | FINANCIAL ASSISTANCE FOR ANTI-DENGUE CAMPAIGN | N/A | 181,740.00 | 39,990.00 | - | 22.00% | 39,990.00 | on-going project | ||||||||||||||||||
99 | NCCA - INSTITUTE OF LIVING TRADITIONS | N/A | 2,249,827.00 | 832,196.50 | - | 36.99% | 832,196.50 | on-going project | ||||||||||||||||||
100 | NCCA - TUBURAN BOHOL | N/A | 149,845.00 | 111,441.00 | - | 74.37% | 111,441.00 | on-going project | ||||||||||||||||||